2026 T2 Construction Manager Analysis

Jobs, inspection timeliness, QC, return fixes and misc work — per CM, for every job whose major tasks finished in the period.

Built September 9, 2026 from exports dated September 9, 2026 · Owner: Ed Marshall <ed@cascade.build>

2026 T2  ·  May 1 – August 31, 2026  ·  944 jobs

Per-CM scorecard

Construction ManagerJobs & profitabilityTask inspectionsQCReturn fixesMisc tasksReorders
CreditedFullHalfRevenueCycle (bus. days)LaborMaterialGross profitMargin %TotalOn time %QC'dQC'd %WaitingOn time %Median bus. days lateCountPer jobCountPer job$CountPer job$
Construction ManagerJobsInspectionsQC'dReturn fixes

Head to head

How these numbers are built

Where the QC figures come from.
717 of the 944 cohort jobs have a completed old-system QC walk, and a further 100 have a QC Checkoff (the new system, live from late July) with no old walk. 127 jobs (13%) have no QC record in either system — 51 of them are archived and count neither for nor against anyone, 76 are still open and are counted as waiting. Of the 503 May/June jobs, 30 have none. “Archived” here means the job’s Status field reading Archive or Warranty. The old-system date is read from the complete export of QC Walk tasks — 2,482 tasks, 2,415 of them completed — rather than from the job record. 19 cohort jobs have an old walk task that was created but never completed; 208 have no old walk task at all. An earlier version of this report (9 Sep, morning) was built from a job export that unintentionally excluded every job with a completed old-system walk, and is superseded by this one.

Two more things to know.
1. The cohort is heavily back-loaded: 229 of 944 jobs (24%) finished major tasks in August, ramping week by week through the month. 2026 T2 is effectively August plus a tail.
2. Inspections on cohort jobs run from December 2025 to September 2026, because work on a job starts well before its major tasks finish. All of them count — the cohort is defined by the job, not by the inspection date.