DR Horton — Jobs with Open Invoices 91+ Days Past Due

As of July 29, 2026 · Billing from QuickBooks (A/R aging detail, accrual) · Tasks, POs & costs from TrackVia
30
Jobs
$270,079
Total open balance
$268,238
Open & 91+ days past due
52
Open invoices
348 days
Oldest past-due invoice

All jobs (sorted by open balance)

JobOpen invoicesInvoiced (open inv.)Open balanceOldest overdueHard costs (labor+mat.)Total revenue billed
114-Palomino-DR Horton4$33,777.00$33,777.00181d$33,317$35,367
Bldg 102-Long Valley Townhomes-DR Horton3$33,366.46$33,366.46266d$32,069$37,237
125-Montreux-DR Horton4$28,988.00$28,988.00114d$26,807$28,988
116-Palomino-DR Horton6$28,724.00$28,724.00129d$24,977$28,724
102-Montreux-DR Horton3$26,313.00$26,313.00166d$-15,755$26,313
101-Montreux-DR Horton1$34,595.00$21,303.00216d$18,967$35,869
Bldg 3-Midtown Village-DR Horton3$26,377.00$17,165.0095d$65,622$67,700
204-Cherry Wood-DR Horton1$30,889.00$17,094.00220d$26,912$33,216
Bldg 43-Pointe West-DR Horton4$17,622.00$11,022.00188d$11,334$18,322
234-Cherry Wood-DR Horton1$27,151.00$8,788.00220d$26,428$28,622
Bldg 33-Old Sorrel Ranch-DR Horton1$27,764.38$8,764.38222d$23,184$29,564
253-Long Valley-DR Horton1$4,721.72$4,721.72170d$23,103$27,461
4077-Long Valley Rambler-DR Horton1$3,159.64$3,159.64348d$14,023$19,483
Metal Shade Structures-Western Acres Townhomes-DR Horton1$3,141.60$3,141.60224d$518$3,927
263-Long Valley-DR Horton1$2,556.77$2,556.77108d$22,917$30,018
Bldg 4-Midtown Village-DR Horton1$2,474.85$2,474.85101d$65,041$67,440
Bldg 41-Pointe West-DR Horton1$8,811.00$2,211.00174d$9,558$8,811
Bldg 42-Pointe West-DR Horton1$8,811.00$2,211.00203d$8,419$9,511
47-Mountainside Estates-DR Horton2$2,115.61$2,115.61114d$25,772$26,560
Bldg 13-Dixon Creek-DR Horton2$2,003.92$2,003.92109d$35,661$45,031
Bldg 2-Midtown Village-DR Horton1$1,931.49$1,931.49111d$50,921$54,840
Bldg 14-Dixon Creek-DR Horton1$1,730.40$1,730.4099d$31,143$44,754
124-Montreux-DR Horton1$5,683.00$1,469.0094d$24,653$28,622
Bldg 28-Old Sorrel Ranch-DR Horton1$1,300.00$1,300.00264d$655$1,300
46-Mountainside Estates-DR Horton1$1,150.45$1,150.45109d$19,747$24,633
117-Palomino-DR Horton1$1,019.90$1,019.90102d$19,028$21,957
129-Old Sorrel Ranch-DR Horton1$930.00$930.00110d$1,316$1,930
106-Montreux-DR Horton1$1,111.00$238.00123d$27,835$30,030
123-Montreux-DR Horton1$34,595.00$209.00166d$34,462$34,595
113-Old Sorrel Ranch-DR Horton1$200.00$200.00169d$28,229$24,863
Total52$403,014.19$270,079.19$716,863$875,690
"Invoiced (open inv.)" is the original amount of the still-open invoices only. "Total revenue billed" and cost figures come from TrackVia job profitability data.

114-Palomino-DR Horton

Palomino · Ogden Division · Status: 12. Archive · Cascade final: Apr 18, 2026
$33,777.00
Open balance (QB)
$35,367
Total revenue billed
$13,238
Labor costs (burdened)
$20,079
Material POs w/ tax
$33,317
Total hard costs
$2,050 (5.8%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77329Dec 30, 2025Jan 29, 2026181d overdue$13,844.00$13,844.00
77330Dec 30, 2025Jan 29, 2026181d overdue$14,389.00$14,389.00
77331Dec 30, 2025Jan 29, 2026181d overdue$3,726.00$3,726.00
77332Dec 30, 2025Jan 29, 2026181d overdue$1,818.00$1,818.00
Total open$33,777.00$33,777.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,157.29$5,323.14$13,844.00
Siding$3,856.60$6,532.69$14,389.00
Soffit/Fascia$888.25$1,645.43$3,726.00
Gutters$307.20$826.17$1,818.00
Insulation$0.00$826.17

Tasks — TrackVia (20)

TaskCompletedInspectionTeamTask pay
QC WalkApr 13, 2026 5:51 PMPassGeorge Contreras$3,127.00
4-Way PassDec 30, 2025 9:16 AMPassOffice Staff - Orem$0.00
Set ScaffDec 31, 2025 3:48 PMPassJuan Pablo Moreno$3,027.00
Misc. WorkFeb 18, 2026 11:11 AMPassMarcos Garcia Mendez$0.00
Misc. WorkFeb 8, 2026 2:49 PMPassKevin Nehemias $50.00
Paper/WireJan 02, 2026 8:54 PMPassSergio Aguilar$980.42
Stucco BrownJan 06, 2026 2:21 PMPassArmando Barajas$50.00
SidingJan 14, 2026 9:26 AMPassRaul Trujillo$-100.00
SidingJan 14, 2026 9:26 AMPassRaul Trujillo$50.00
VPO WorkJan 16, 2026 3:27 PMPassEnemecio Fonseca$0.00
PaintJan 16, 2026 5:26 PMPassJuan Rivera$0.00
HousewrapJan 2, 2026 8:56 PMPassSergio Aguilar$844.00
Stucco ColorJan 22, 2026 10:00 AMPassAngel Agustin Benitez$977.00
Remove ScaffJan 22, 2026 10:00 AMPassAngel Agustin Benitez$200.00
Remove TarpsJan 22, 2026 10:01 AMPassAngel Agustin Benitez$671.00
Soffit/FasciaJan 23, 2026 9:38 PMPassJairo Alexi Lopez Pirir$85.93
GuttersJan 24, 2026 12:03 PMPassMaria Estrada Olivarez$50.00
HW: Weather Barrier InspectionJan 5, 2026 11:30 AMPassCity Inspections$313.69
PW: Lath InspectionJan 5, 2026 11:30 AMPassCity Inspections$0.00
Set TarpsJan 6, 2026 3:35 PMPassArmando Barajas$0.00

Bldg 102-Long Valley Townhomes-DR Horton

Long Valley Townhomes · St. George Division · Status: 12. Archive · Cascade final: Nov 25, 2025
$33,366.46
Open balance (QB)
$37,237
Total revenue billed
$14,572
Labor costs (burdened)
$17,496
Material POs w/ tax
$32,069
Total hard costs
$5,169 (13.9%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
75852Oct 6, 2025Nov 5, 2025266d overdue$104.00$104.00
75853Oct 6, 2025Nov 5, 2025266d overdue$31,261.56$31,261.56
75855Oct 6, 2025Nov 5, 2025266d overdue$2,000.90$2,000.90
Total open$33,366.46$33,366.46

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$11,290.32$12,166.26$31,261.56
Rock$104.13$1,900.99$3,867.65
Brick$956.29$0.00
Siding$0.00$10.44$104.00
Gutters$379.20$0.00$2,000.90

Tasks — TrackVia (13)

TaskCompletedInspectionTeamTask pay
QC WalkNovember 19, 2025 10:51 AMPassDaniel Cid$741.60
WateringOct 20, 2025 2:01 PMPassJorge Castro$603.40
Stucco ColorOct 23, 2025 5:25 PMPassFrancisco Juarez$217.00
Paper/WireOctober 13, 2025 1:32 PMPassWilliam Garcia Garcia$0.00
Paper/WireOctober 13, 2025 2:59 PMPassAlexis Jimenez Altamirano$60.00
Brick Lath InspectionOctober 15, 2025 11:30 AMPassCity Inspections$1,663.00
PW: Lath InspectionOctober 15, 2025 11:30 AMPassCity Inspections$0.00
Stucco BrownOctober 18, 2025 4:00 PMPassJorge Castro$1,526.00
Scratch CoatOctober 18, 2025 4:02 PMPassJorge Castro$80.00
BrickOctober 22, 2025 3:44 PMPassMinor Escobar Rodriguez$204.00
Remove ScaffOctober 23, 2025 5:35 PMPassFrancisco Juarez$0.00
GuttersOctober 27, 2025 4:00 PMPassManolo Najarro-Garcia$1,679.00
Set ScaffOctober 8, 2025 2:36 PMPassNestor Preciado-Diaz$407.88

125-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 26, 2026
$28,988.00
Open balance (QB)
$28,988
Total revenue billed
$9,143
Labor costs (burdened)
$17,664
Material POs w/ tax
$26,807
Total hard costs
$2,181 (7.5%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
78925Feb 5, 2026Apr 6, 2026114d overdue$20,157.00$20,157.00
78926Feb 5, 2026Apr 6, 2026114d overdue$4,098.00$4,098.00
78927Feb 5, 2026Apr 6, 2026114d overdue$3,567.00$3,567.00
78928Feb 5, 2026Apr 6, 2026114d overdue$1,166.00$1,166.00
Total open$28,988.00$28,988.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$106.63$512.04
Rock$1,254.26$2,258.87$3,567.00
Siding$6,372.36$8,070.64$20,157.00
Soffit/Fascia$693.35$1,601.40$4,098.00
Gutters$296.40$557.28$1,166.00
Insulation$0.00$557.28

Tasks — TrackVia (17)

TaskCompletedInspectionTeamTask pay
PW: Lath InspectionFeb 10, 2026 4:16 PMPassCity Inspections$557.05
HW: Weather Barrier InspectionFeb 10, 2026 4:17 PMPassCity Inspections$0.00
Soffit/FasciaFeb 19, 2026 5:37 PMPassEveli Solis$0.00
SidingFeb 19, 2026 5:42 PMPassEveli Solis$0.00
Paper/WireFeb 26, 2026 2:00 PMPassJose Perez$321.60
4-Way PassFeb 5, 2026 9:23 AMPassOffice Staff - Orem$0.00
HousewrapFeb 6, 2026 7:48 PMPassMarcos Garcia Mendez$0.00
Return/FixMar 06, 2026 10:23 AMPassEveli Solis$978.00
Misc. WorkMar 09, 2026 5:08 PMPassWillson Garcia$823.56
GuttersMar 12, 2026 1:44 PMPassManolo Najarro-Garcia$0.00
Fix ScaffMar 12, 2026 8:01 PMPassJavier Vazquez$268.84
RockMar 14, 2026 2:47 PMPassMichel Martinez$0.00
QC WalkMar 16, 2026 8:41 AMPassAlex Saldana$727.52
Fix ScaffMar 17, 2026 4:30 PMPassJavier Vazquez$1,027.00
Scratch CoatMar 2, 2026 4:30 PMPassJose Perez$175.00
Misc. WorkMar 6, 2026 10:26 AMPassEveli Solis$266.00
Hardie Soffit/FasciaMar 6, 2026 10:28 AMPassEveli Solis$0.00

116-Palomino-DR Horton

Palomino · Ogden Division · Status: 12. Archive · Cascade final: Apr 18, 2026
$28,724.00
Open balance (QB)
$28,724
Total revenue billed
$11,990
Labor costs (burdened)
$12,987
Material POs w/ tax
$24,977
Total hard costs
$3,747 (13.0%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
78691Jan 21, 2026Mar 22, 2026129d overdue$1,287.00$1,287.00
78692Jan 21, 2026Mar 22, 2026129d overdue$14,434.00$14,434.00
78693Jan 21, 2026Mar 22, 2026129d overdue$343.00$343.00
78694Jan 21, 2026Mar 22, 2026129d overdue$3,547.00$3,547.00
78695Jan 21, 2026Mar 22, 2026129d overdue$7,650.00$7,650.00
78690Jan 28, 2026Apr 23, 202697d overdue$1,463.00$1,463.00
Total open$28,724.00$28,724.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,186.68$4,944.30$14,434.00
Rock$146.19$288.42$343.00
Siding$2,987.35$4,984.98$7,650.00
Soffit/Fascia$848.24$1,466.10$3,547.00
Gutters$288.00$699.94$1,287.00
Insulation$0.00$699.94

Tasks — TrackVia (24)

TaskCompletedInspectionTeamTask pay
QC WalkApr 13, 2026 5:52 PMPassGeorge Contreras$208.00
PaintFeb 09, 2026 5:07 PMPassKevin Nehemias $64.00
Soffit/FasciaFeb 16, 2026 9:40 AMPassKelvin Flores$700.72
Soffit/FasciaFeb 16, 2026 9:40 AMPassKelvin Flores$180.00
Remove TarpsFeb 17, 2026 1:45 PMPassGenaro Miramontes$1,638.12
Remove ScaffFeb 17, 2026 2:44 PMPassGenaro Miramontes$123.00
Fix ScaffFeb 22, 2026 3:04 PMPassEnemecio Fonseca$391.00
GuttersFeb 22, 2026 6:25 AMPassEnrique Godinez$380.00
ShuttersFeb 25, 2026 11:45 AMPassBaylor Bell$80.00
SidingFeb 5, 2026 5:15 PMPassMarcos Garcia Mendez$2,292.00
SidingFeb 5, 2026 5:15 PMPassMarcos Garcia Mendez$75.00
Stucco ColorFeb 5, 2026 9:56 AMPassAngel Agustin Benitez$1,472.97
RockFeb 9, 2026 9:05 AMPassSergio Vega$1,468.06
4-Way PassJan 21, 2026 6:18 PMPassOffice Staff - Orem$0.00
Set ScaffJan 24, 2026 9:29 AMPassSergio Aguilar$100.00
Paper/WireJan 24, 2026 9:31 AMPassSergio Aguilar$287.66
HousewrapJan 24, 2026 9:33 AMPassSergio Aguilar$375.00
HW: Weather Barrier InspectionJan 26, 2026 8:00 AMPassCity Inspections$75.00
PW: Lath InspectionJan 26, 2026 8:00 AMPassCity Inspections$782.47
Set TarpsJan 28, 2026 2:44 PMPassAngel Agustin Benitez$85.00
Scratch CoatJan 28, 2026 5:00 PMPassAngel Agustin Benitez$0.00
Stucco BrownJan 29, 2026 12:03 PMPassAngel Agustin Benitez$4,130.98
Misc. WorkMar 06, 2026 10:11 AMPassKelvin Flores$0.00
Misc. WorkMar 10, 2026 12:46 PMPassDiego Priego$0.00

102-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 04, 2026
$26,313.00
Open balance (QB)
$26,313
Total revenue billed
$10,058
Labor costs (burdened)
$-25,813
Material POs w/ tax
$-15,755
Total hard costs
$42,068 (159.9%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77589Dec 15, 2025Feb 13, 2026166d overdue$21,060.00$21,060.00
77590Dec 15, 2025Feb 13, 2026166d overdue$4,087.00$4,087.00
77591Dec 15, 2025Feb 13, 2026166d overdue$1,166.00$1,166.00
Total open$26,313.00$26,313.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Rock$0.00$2,457.36
Siding$7,783.98$2,550.55$21,060.00
Soffit/Fascia$738.10$1,373.65$4,087.00
Gutters$256.80$467.84$1,166.00
Insulation$0.00$467.84

Tasks — TrackVia (15)

TaskCompletedInspectionTeamTask pay
4-Way PassDec 15, 2025 2:01 PMPassOffice Staff - Orem$1,698.60
HW: Weather Barrier InspectionDec 18, 2025 10:30 AMPassCity Inspections$72.00
HousewrapDec 22, 2025 3:12 PMPassPedro Aguillar$55.00
PW: Lath InspectionDec 23, 2025 9:00 AMPassCity Inspections$95.00
Hardie Soffit/FasciaDec 31, 2025 3:59 PMPassIker Hernandez$60.00
Soffit/FasciaDec 31, 2025 3:59 PMPassKelvin Flores$102.00
Return/FixFeb 26, 2026 1:42 PMPassManolo Najarro-Garcia$0.00
GuttersJan 17, 2026 2:48 PMPassManolo Najarro-Garcia$200.00
SidingJan 23, 2026 7:01 AMPassIker Hernandez$60.00
SidingJan 23, 2026 7:01 AMPassIker Hernandez$36.00
Remove ScaffJan 8, 2026 12:00 AMPassPedro Aguillar$677.85
Misc. WorkMar 17, 2026 12:16 PMPassAlberto Bernabe$30.00
Misc. WorkMar 3, 2026 3:57 PMPassWillson Garcia$820.91
Misc. WorkMar 4, 2026 11:34 AMPassAlberto Bernabe$264.95
QC WalkMar 4, 2026 7:44 PMPassAlex Saldana$432.00

101-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 04, 2026
$21,303.00
Open balance (QB)
$35,869
Total revenue billed
$720
Labor costs (burdened)
$18,247
Material POs w/ tax
$18,967
Total hard costs
$16,903 (47.1%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77581Nov 25, 2025Dec 25, 2025216d overdue$34,595.00$21,303.00
Total open$34,595.00$21,303.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Rock$0.00$6,060.73$12,620.00
Siding$0.00$9,801.89$16,796.00
Soffit/Fascia$0.00$675.28$3,837.00
Gutters$0.00$539.76$1,342.00
Insulation$0.00$539.76

Tasks — TrackVia (17)

TaskCompletedInspectionTeamTask pay
Soffit/FasciaDec 05, 2025 6:00 PMPassJavier Perez$745.00
SidingDec 05, 2025 7:00 PMPassJavier Perez$0.00
Set TarpsDec 26, 2025 3:21 PMPassOffice Staff - Orem$60.00
GuttersDec 26, 2025 3:21 PMPassManolo Najarro-Garcia$382.25
Remove TarpsDec 26, 2025 3:22 PMPassOffice Staff - Orem$100.00
Scratch CoatDec 26, 2025 3:22 PMPassOffice Staff - Orem$546.90
Misc. WorkFeb 27, 2026 5:01 PMPassJavier Perez$409.53
RockJan 5, 2026 4:00 PMPassOffice Staff - Orem$0.00
QC WalkMar 04, 2026 7:47 PMPassAlex Saldana$183.06
Scaff PickupMar 3, 2026 12:24 PMPassOscar Villegas$0.00
Misc. WorkMar 9, 2026 6:29 PMPassWillson Garcia$148.20
Set ScaffNov 21, 2025 12:00 PMPassOffice Staff - Orem$1,592.00
Paper/WireNov 21, 2025 7:30 PMPassOffice Staff - Orem$1,655.38
4-Way PassNov 25, 2025 11:34 AMPassOffice Staff - Orem$107.94
HousewrapNov 25, 2025 12:02 PMPassOffice Staff - Orem$106.00
HW: Weather Barrier InspectionNov 25, 2025 1:00 PMPassCity Inspections$65.00
PW: Lath InspectionNov 25, 2025 1:00 PMPassCity Inspections$54.83

Bldg 3-Midtown Village-DR Horton

Midtown Village · Ogden Division · Status: 12. Archive · Cascade final: May 21, 2026
$17,165.00
Open balance (QB)
$67,700
Total revenue billed
$31,520
Labor costs (burdened)
$34,101
Material POs w/ tax
$65,622
Total hard costs
$2,078 (3.1%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
79829Feb 24, 2026Apr 25, 202695d overdue$2,222.00$1,132.00
79831Feb 24, 2026Apr 25, 202695d overdue$23,955.00$15,833.00
83030May 11, 2026Jun 10, 202649d overdue$200.00$200.00
Total open$26,377.00$17,165.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$7,274.19$6,383.34$16,444.00
Rock$922.24$11,503.65$23,955.00
Brick$11,763.23$0.00
Siding$5,917.13$11,286.04$16,444.00
Soffit/Fascia$956.52$1,915.98$5,900.00
Gutters$890.40$2,917.81$2,222.00
Insulation$0.00$2,917.81

Tasks — TrackVia (25)

TaskCompletedInspectionTeamTask pay
4-Way PassFeb 24, 2026 5:09 PMPassOffice Staff - Orem$120.00
WRB PassMar 10, 2026 12:06 PMPassOffice Staff - Orem$245.00
Stucco BrownMar 11, 2026 6:17 PMPassIsaac Arzate Rosas$120.00
Scratch CoatMar 11, 2026 7:11 PMPassIsaac Arzate Rosas$180.00
Set TarpsMar 12, 2026 10:26 AMPassIsaac Arzate Rosas$530.00
VPO WorkMar 12, 2026 6:48 PMPassSergio Aguilar$60.00
BrickMar 14, 2026 7:40 PMPassJuan Robles$75.00
Stucco ColorMar 16, 2026 7:57 PMPassIsaac Arzate Rosas$650.00
Base Install CompleteMar 18, 2026 7:55 PMPassOffice Staff - Orem$1,339.19
SidingMar 18, 2026 7:55 PMPassAlberto Bernabe$95.00
Hardie Soffit/FasciaMar 19, 2026 12:22 PMPassAlberto Bernabe$300.00
Soffit/FasciaMar 20, 2026 2:03 PMPassAriel Ramirez$781.86
Soffit/FasciaMar 20, 2026 2:03 PMPassAriel Ramirez$80.00
Woodtone PaintMar 22, 2026 2:21 PMPassDiego Priego$30.00
PaintMar 22, 2026 4:16 PMPassDiego Priego$90.00
Paint Hardie Soffit/FasciaMar 24, 2026 3:10 PMPassDiego Priego$100.00
Remove ScaffMar 25, 2026 1:02 PMPassSergio Aguilar$0.00
GuttersMar 26, 2026 9:00 AMPassEnrique Godinez$140.00
Set ScaffMar 5, 2026 1:55 PMPassSergio Aguilar$257.54
HousewrapMar 6, 2026 12:40 PMPassSergio Aguilar$135.00
Paper/WireMar 6, 2026 3:41 PMPassSergio Aguilar$250.00
HW: Weather Barrier InspectionMar 9, 2026 1:00 PMPassCity Inspections$210.00
Brick Lath InspectionMar 9, 2026 1:00 PMPassCity Inspections$0.00
PW: Lath InspectionMar 9, 2026 1:00 PMPassCity Inspections$80.00
QC WalkMay 21, 2026 6:35 AMPassGeorge Contreras$550.00

204-Cherry Wood-DR Horton

Cherry Wood · Ogden Division · Status: 12. Archive · Cascade final: Mar 4, 2026
$17,094.00
Open balance (QB)
$33,216
Total revenue billed
$13,813
Labor costs (burdened)
$13,099
Material POs w/ tax
$26,912
Total hard costs
$6,304 (19.0%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77580Nov 21, 2025Dec 21, 2025220d overdue$30,889.00$17,094.00
Total open$30,889.00$17,094.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,154.29$4,956.96$13,922.00
Siding$4,187.32$5,686.95$11,480.00
Soffit/Fascia$1,146.54$1,806.52$3,932.00
Gutters$363.60$639.68$1,555.00
Insulation$0.00$639.68

Tasks — TrackVia (21)

TaskCompletedInspectionTeamTask pay
PW: Lath InspectionDec 01, 2025 8:00 AMPassCity Inspections$100.00
SidingDec 02, 2025 5:00 PMPassEric Hernandez$874.72
HW: Weather Barrier InspectionDec 1, 2025 8:00 AMPassCity Inspections$1,530.90
VPO WorkDec 13, 2025 10:42 AMPassAndres Dominguez$4,068.00
Stucco ColorDec 16, 2025 3:22 PMPassMelissa Camacho$603.04
Fix ScaffDec 18, 2025 10:54 AMPassHector Moreta$0.00
Soffit/FasciaDec 19, 2025 6:29 PMPassAlexander Aguirre$720.00
Remove TarpsDec 22, 2025 9:08 PMPassErnesto Ramirez$0.00
Remove ScaffDec 22, 2025 9:10 PMPassErnesto Ramirez$2,295.00
GuttersDec 25, 2025 7:26 PMPassManolo Najarro-Garcia$1,221.00
Stucco BrownDec 5, 2025 2:43 PMPassAndres Dominguez$957.00
Set TarpsDec 5, 2025 8:41 AMPassAndres Dominguez$1,287.51
Stucco BrownDec 5, 2025 8:56 AMPassAndres Dominguez$0.00
Set TarpsDec 6, 2025 10:38 AMPassAndres Dominguez$1,250.00
PaintDec 9, 2025 10:26 AMPassKeren Avila Herrera$0.00
Fix ScaffJan 13, 2026 2:16 PMPassJuan Pablo Moreno$72.00
Misc. WorkJan 15, 2026 4:56 PMPassFredi Chuncho$0.00
4-Way PassNov 21, 2025 4:08 PMPassOffice Staff - Orem$300.00
Set ScaffNov 27, 2025 3:34 PMPassSergio Aguilar$0.00
HousewrapNov 27, 2025 3:36 PMPassSergio Aguilar$0.00
Paper/WireNov 27, 2025 3:41 PMPassSergio Aguilar$1,085.70

Bldg 43-Pointe West-DR Horton

Pointe West · St. George Division · Status: 12. Archive · Cascade final: Feb 8, 2026
$11,022.00
Open balance (QB)
$18,322
Total revenue billed
$7,409
Labor costs (burdened)
$3,925
Material POs w/ tax
$11,334
Total hard costs
$6,988 (38.1%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77613Dec 23, 2025Jan 22, 2026188d overdue$8,811.00$2,211.00
78513Dec 23, 2025Jan 22, 2026188d overdue$6,522.00$6,522.00
78514Dec 23, 2025Jan 22, 2026188d overdue$1,492.00$1,492.00
78515Dec 23, 2025Jan 22, 2026188d overdue$797.00$797.00
Total open$17,622.00$11,022.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$540.00$0.00
Siding$5,942.70$2,895.42$13,044.00
Soffit/Fascia$692.76$0.00$2,984.00
Gutters$234.00$0.00$1,594.00

Tasks — TrackVia (9)

TaskCompletedInspectionTeamTask pay
HousewrapDec 29, 2025 4:05 PMPassKevin Hernandez$164.00
QC WalkFeb 03, 2026 10:32 AMPassDaniel Cid$0.00
Foundation PlasterFeb 07, 2026 11:50 AMPassDiego Martin$120.00
HW: Weather Barrier InspectionJan 1, 2026 8:30 AMPassCity Inspections$18.00
VinylJan 11, 2026 9:41 PMPassArmando Segundo-Garcia$0.00
VinylJan 11, 2026 9:41 PMPassArmando Segundo-Garcia$720.00
GuttersJan 17, 2026 5:55 PMPassManolo Najarro-Garcia$27.00
Soffit/FasciaJan 8, 2026 11:29 PMPassArmando Segundo-Garcia$720.00
SidingJan 8, 2026 11:31 PMPassArmando Segundo-Garcia$36.00

234-Cherry Wood-DR Horton

Cherry Wood · Ogden Division · Status: 12. Archive · Cascade final: Feb 16, 2026
$8,788.00
Open balance (QB)
$28,622
Total revenue billed
$12,945
Labor costs (burdened)
$13,483
Material POs w/ tax
$26,428
Total hard costs
$2,194 (7.7%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77579Nov 21, 2025Dec 21, 2025220d overdue$27,151.00$8,788.00
Total open$27,151.00$8,788.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,067.80$5,688.61$13,626.00
Rock$0.00$82.31
Siding$3,449.26$4,786.30$8,789.00
Soffit/Fascia$1,144.77$1,820.13$3,570.00
Gutters$302.40$582.16$1,166.00
Insulation$0.00$582.16

Tasks — TrackVia (20)

TaskCompletedInspectionTeamTask pay
Set TarpsDec 06, 2025 12:00 PMPassAngela Prudente$390.65
PaintDec 09, 2025 10:11 AMPassKeren Avila Herrera$60.00
HW: Weather Barrier InspectionDec 1, 2025 8:00 AMPassCity Inspections$80.00
PW: Lath InspectionDec 1, 2025 8:00 AMPassCity Inspections$3,342.64
Stucco ColorDec 15, 2025 2:09 PMPassChristian Evangelista$989.44
Fix ScaffDec 18, 2025 1:24 PMPassHector Moreta$646.00
Soffit/FasciaDec 21, 2025 12:07 PMPassRoger Guzman$50.00
GuttersDec 22, 2025 6:37 PMPassManolo Najarro-Garcia$80.00
Remove TarpsDec 22, 2025 9:11 PMPassErnesto Ramirez$3,021.47
Remove ScaffDec 22, 2025 9:12 PMPassErnesto Ramirez$0.00
SidingDec 3, 2025 9:16 PMPassMisael Santos$120.00
Set TarpsDec 5, 2025 1:11 PMPassAngela Prudente$7,926.94
Stucco BrownDec 6, 2025 11:59 AMPassAngela Prudente$1,149.67
Stucco BrownDecember 5, 2025 9:01 AMPassAngela Prudente$1,233.58
Misc. WorkJan 15, 2026 2:33 PMPassFredi Chuncho$232.77
VPO WorkJan 15, 2026 8:50 AMPassEuddy Enrique Rodriguez-Chima$945.69
Set ScaffNov 25, 2025 8:29 PMPassSergio Aguilar$3,709.00
Set ScaffNov 25, 2025 8:29 PMPassSergio Aguilar$882.11
Paper/WireNov 27, 2025 3:39 PMPassSergio Aguilar$4,644.00
HousewrapNovember 27, 2025 3:35 PMPassSergio Aguilar$182.00

Bldg 33-Old Sorrel Ranch-DR Horton

Old Sorrel Ranch · St. George Division · Status: 12. Archive · Cascade final: Jun 22, 2026
$8,764.38
Open balance (QB)
$29,564
Total revenue billed
$22,905
Labor costs (burdened)
$279
Material POs w/ tax
$23,184
Total hard costs
$6,381 (21.6%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
76493Nov 19, 2025Dec 19, 2025222d overdue$27,764.38$8,764.38
Total open$27,764.38$8,764.38

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$540.00$0.00
Siding$20,102.42$0.00
Soffit/Fascia$2,262.18$0.00

Tasks — TrackVia (10)

TaskCompletedInspectionTeamTask pay
QC WalkJun 22, 2026 10:23 PMPassJuan Gracia Acero$55.00
HousewrapNov 10, 2025 6:23 AMPassKevin Hernandez$0.00
SidingNov 10, 2025 6:25 AMPassKevin Hernandez$80.00
VinylNov 10, 2025 6:26 AMPassKevin Hernandez$0.00
Soffit/FasciaNov 10, 2025 6:30 AMPassKevin Hernandez$130.00
VinylNov 7, 2025 2:06 PMPassKevin Hernandez$55.00
HousewrapNov 7, 2025 2:06 PMPassKevin Hernandez$55.00
Foundation PlasterNovember 12, 2025 12:27 PMPassDiego Martin$0.00
Soffit/FasciaNovember 7, 2025 1:58 PMPassKevin Hernandez$179.00
4-Way PassOct 31, 2025 4:22 PMPassOffice Staff - Orem$160.00

253-Long Valley-DR Horton

Long Valley · St. George Division · Status: 12. Archive · Cascade final: Mar 6, 2026
$4,721.72
Open balance (QB)
$27,461
Total revenue billed
$10,253
Labor costs (burdened)
$12,850
Material POs w/ tax
$23,103
Total hard costs
$4,358 (15.9%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77003Dec 11, 2025Feb 9, 2026170d overdue$4,721.72$4,721.72
Total open$4,721.72$4,721.72

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$6,256.10$7,111.63$18,819.91
Rock$1,055.57$1,840.70$2,556.77
Siding$1,129.95$3,186.41$4,721.72
Gutters$273.60$0.00$1,362.82

Tasks — TrackVia (17)

TaskCompletedInspectionTeamTask pay
4-Way PassDec 11, 2025 3:03 PMPassOffice Staff - Orem$50.00
Set ScaffDec 16, 2025 11:32 AMPassMarcos Mata$160.00
HousewrapDec 23, 2025 9:31 AMPassNahum Jaurez Jimenez$713.59
Paper/WireDec 23, 2025 9:34 AMPassNahum Jaurez Jimenez$50.00
Porch OSBDec 23, 2025 9:38 AMPassNahum Jaurez Jimenez$0.00
HW: Weather Barrier InspectionDec 29, 2025 10:30 AMPassCity Inspections$306.00
PW: Lath InspectionDec 29, 2025 10:30 AMPassCity Inspections$825.00
SidingDec 31, 2025 11:34 PMPassArmando Segundo-Garcia$404.60
Stucco ColorJan 13, 2026 3:53 PMPassJorge Castro$178.23
Remove ScaffJan 13, 2026 3:54 PMPassJorge Castro$811.03
PaintJan 14, 2026 5:43 PMPassCarlos Guzman$129.00
GuttersJan 15, 2026 2:34 PMPassManolo Najarro-Garcia$50.00
Scratch CoatJan 2, 2026 5:49 PMPassJorge Castro$788.03
QC WalkJan 23, 2026 9:43 AMPassDaniel Cid$100.00
Stucco BrownJan 6, 2026 2:09 PMPassJorge Castro$330.35
RockJan 7, 2026 3:14 PMPassMinor Escobar Rodriguez$0.00
WateringJan 7, 2026 6:08 PMPassJorge Castro$6,211.32

4077-Long Valley Rambler-DR Horton

Long Valley Rambler · St. George Division · Status: 12. Archive · Cascade final: September 2, 2025
$3,159.64
Open balance (QB)
$19,483
Total revenue billed
$6,739
Labor costs (burdened)
$7,284
Material POs w/ tax
$14,023
Total hard costs
$5,460 (28.0%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
73601Jul 16, 2025Aug 15, 2025348d overdue$3,159.64$3,159.64
Total open$3,159.64$3,159.64

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,088.06$3,609.31$14,539.06
Rock$1,200.65$2,006.72
Gutters$343.20$0.00$1,784.58

Tasks — TrackVia (10)

TaskCompletedInspectionTeamTask pay
GuttersAug 02, 2025 6:43 PMPassManolo Najarro-Garcia$154.00
QC WalkAug 15, 2025 11:33 AMPassDaniel Cid$0.00
Porch OSBJul 22, 2025 4:09 PMPassLuis Gomez Hernandez$914.00
Paper/WireJul 22, 2025 4:11 PMPassLuis Gomez Hernandez$772.07
PW: Lath InspectionJul 23, 2025 11:00 AMPassCity Inspections$241.24
Scratch CoatJul 23, 2025 7:02 PMPassCarmen Corona Salazar$0.00
Stucco BrownJul 24, 2025 4:09 PMPassJorge Castro$1,202.31
RockJul 25, 2025 11:44 AMPassCarmen Corona Salazar$486.95
WateringJul 27, 2025 1:03 PMPassJorge Castro$904.96
Stucco ColorJul 30, 2025 10:41 AMPassJorge Castro$537.62

Metal Shade Structures-Western Acres Townhomes-DR Horton

Western Acres Townhomes · Ogden Division · Status: 12. Archive · Cascade final: Dec 30, 2025
$3,141.60
Open balance (QB)
$3,927
Total revenue billed
$360
Labor costs (burdened)
$158
Material POs w/ tax
$518
Total hard costs
$3,409 (86.8%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
76457Nov 17, 2025Dec 17, 2025224d overdue$3,141.60$3,141.60
Total open$3,141.60$3,141.60

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Siding$0.00$183.95
No task records found for this job in TrackVia.

263-Long Valley-DR Horton

Long Valley · St. George Division · Status: 12. Archive · Cascade final: Apr 6, 2026
$2,556.77
Open balance (QB)
$30,018
Total revenue billed
$10,322
Labor costs (burdened)
$12,596
Material POs w/ tax
$22,917
Total hard costs
$7,101 (23.7%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
79105Feb 11, 2026Apr 12, 2026108d overdue$2,556.77$2,556.77
Total open$2,556.77$2,556.77

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$6,340.10$6,066.20$18,819.91
Rock$1,004.04$1,830.04$5,113.54
Siding$1,165.95$3,008.94$4,721.72
Gutters$273.60$4,911.29$1,362.82
Insulation$0.00$4,911.29

Tasks — TrackVia (18)

TaskCompletedInspectionTeamTask pay
4-Way PassFeb 11, 2026 11:13 AMPassOffice Staff - Orem$537.03
Set ScaffFeb 17, 2026 8:40 AMPassMarcos Mata$794.09
Porch OSBFeb 21, 2026 7:43 AMPassNahum Jaurez Jimenez$196.95
HousewrapFeb 21, 2026 7:44 AMPassNahum Jaurez Jimenez$40.00
Paper/WireFeb 21, 2026 7:46 AMPassNahum Jaurez Jimenez$0.00
Paper/WireFeb 21, 2026 7:46 AMPassNahum Jaurez Jimenez$144.95
HW: Weather Barrier InspectionFeb 24, 2026 10:30 AMPassCity Inspections$0.00
PW: Lath InspectionFeb 24, 2026 10:30 AMPassCity Inspections$3,450.20
Stucco BrownFeb 26, 2026 5:43 PMPassFrancisco Juarez$573.99
Scratch CoatFeb 26, 2026 5:58 PMPassFrancisco Juarez$160.00
SidingFeb 28, 2026 1:38 PMPassRoberto Cruz$642.58
WateringMar 02, 2026 7:32 AMPassFrancisco Juarez$3,476.00
Remove ScaffMar 04, 2026 1:12 PMPassFrancisco Juarez$0.00
QC WalkMar 25, 2026 12:26 PMPassDaniel Cid$178.00
PaintMar 3, 2026 11:00 AMPassFernando Caal$353.42
Stucco ColorMar 4, 2026 12:10 PMPassFrancisco Juarez$311.00
RockMar 4, 2026 9:19 AMPassMinor Escobar Rodriguez$90.00
GuttersMar 5, 2026 5:01 PMPassWalter Najarro$592.27

Bldg 4-Midtown Village-DR Horton

Midtown Village · Ogden Division · Status: 12. Archive · Cascade final: May 21, 2026
$2,474.85
Open balance (QB)
$67,440
Total revenue billed
$30,793
Labor costs (burdened)
$34,248
Material POs w/ tax
$65,041
Total hard costs
$2,399 (3.6%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77645Dec 18, 2025Apr 19, 2026101d overdue$2,474.85$2,474.85
Total open$2,474.85$2,474.85

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$7,394.19$7,780.33$16,444.00
Rock$922.24$13,504.56$23,955.00
Brick$8,940.05$0.00
Siding$5,873.33$7,256.55$16,444.00
Soffit/Fascia$956.52$2,052.90$5,900.00
Gutters$890.40$2,707.19$2,222.00
Insulation$0.00$2,707.19

Tasks — TrackVia (28)

TaskCompletedInspectionTeamTask pay
4-Way PassDec 18, 2025 10:01 AMPassOffice Staff - Orem$0.00
Set ScaffDec 22, 2025 5:11 PMPassJuan Pablo Moreno$60.00
Paper/WireDec 26, 2025 6:44 PMPassSergio Aguilar$1,621.65
HousewrapDec 26, 2025 7:57 PMPassSergio Aguilar$0.00
HW: Weather Barrier InspectionDec 30, 2025 10:00 AMPassCity Inspections$50.00
Brick Lath InspectionDec 30, 2025 10:00 AMPassCity Inspections$1,379.08
PW: Lath InspectionDec 30, 2025 10:00 AMPassCity Inspections$557.60
Misc. WorkFeb 06, 2026 12:42 PMPassAdan Tiburcio$0.00
Stucco BrownJan 06, 2026 8:14 AMPassAngela Prudente$90.00
SidingJan 07, 2026 5:20 PMPassEveli Solis$1,582.00
Woodtone PaintJan 10, 2026 1:00 AMPassDiego Priego$346.25
BrickJan 12, 2026 7:04 PMPassLincoln Valencia$2,470.00
Stucco ColorJan 14, 2026 5:49 PMPassOmar Perez Padilla$60.00
PaintJan 14, 2026 8:59 AMPassDiego Priego$1,952.00
BrickJan 15, 2026 4:45 PMPassLincoln Valencia$1,386.28
Brick WashJan 20, 2026 4:00 PMPassEnemecio Fonseca$0.00
Soffit/FasciaJan 21, 2026 9:17 AMPassIsmael Soto$90.00
Remove TarpsJan 23, 2026 4:25 PMPassJuan Pablo Moreno$0.00
Remove ScaffJan 23, 2026 4:48 PMPassJuan Pablo Moreno$0.00
Scaff PickupJan 24, 2026 12:05 PMPassAgustin Lamas-Rico$50.00
GuttersJan 26, 2026 12:39 PMPassMaria Estrada Olivarez$164.00
Hardie Soffit/FasciaJan 27, 2026 2:26 PMPassEveli Solis$50.00
Paint Hardie Soffit/FasciaJan 30, 2026 10:00 AMPassDiego Priego$1,274.00
Set TarpsJan 6, 2026 6:22 PMPassAngela Prudente$1,804.01
Scratch CoatJan 6, 2026 8:13 AMPassAngela Prudente$202.00
Scratch CoatJan 8, 2026 10:16 AMPassAngela Prudente$884.80
Stucco BrownJan 8, 2026 8:32 PMPassAngela Prudente$486.64
QC WalkMar 3, 2026 7:20 AMPassGeorge Contreras$150.00

Bldg 41-Pointe West-DR Horton

Pointe West · St. George Division · Status: 12. Archive · Cascade final: Dec 14, 2025
$2,211.00
Open balance (QB)
$8,811
Total revenue billed
$8,377
Labor costs (burdened)
$1,181
Material POs w/ tax
$9,558
Total hard costs
$-747 (-8.5%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77631Jan 6, 2026Feb 5, 2026174d overdue$8,811.00$2,211.00
Total open$8,811.00$2,211.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$540.00$0.00
Siding$7,030.56$1,117.40$6,522.00
Soffit/Fascia$626.16$0.00$1,492.00
Gutters$0.00$0.00$797.00

Tasks — TrackVia (12)

TaskCompletedInspectionTeamTask pay
Soffit/FasciaDec 04, 2025 9:19 PMPassArmando Segundo-Garcia$864.00
GuttersDec 05, 2025 9:00 AMPassOffice Staff - Orem$92.00
Soffit/FasciaDec 1, 2025 1:14 PMPassArmando Segundo-Garcia$531.00
VinylDec 1, 2025 1:33 PMPassArmando Segundo-Garcia$120.00
Foundation PlasterDec 13, 2025 5:27 PMPassDiego Martin$100.00
Misc. WorkDec 22, 2025 5:12 PMPassArmando Segundo-Garcia$356.00
VinylDec 4, 2025 9:22 PMPassArmando Segundo-Garcia$100.00
SidingDec 6, 2025 8:27 AMPassArmando Segundo-Garcia$250.00
HW: Weather Barrier InspectionNov 18, 2025 10:30 AMPassCity Inspections$80.00
HousewrapNov 18, 2025 4:00 PMPassFernando Caal$196.00
Soffit/FasciaNov 21, 2025 11:49 AMPassKevin Hernandez$0.00
VinylNov 21, 2025 8:34 AMPassKevin Hernandez$480.00

Bldg 42-Pointe West-DR Horton

Pointe West · St. George Division · Status: 12. Archive · Cascade final: Jan 18, 2026
$2,211.00
Open balance (QB)
$9,511
Total revenue billed
$7,518
Labor costs (burdened)
$901
Material POs w/ tax
$8,419
Total hard costs
$1,092 (11.5%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77588Dec 8, 2025Jan 7, 2026203d overdue$8,811.00$2,211.00
Total open$8,811.00$2,211.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$540.00$0.00
Siding$6,053.38$0.00$6,522.00
Soffit/Fascia$692.76$0.00$1,492.00
Gutters$231.60$730.47$797.00
Insulation$0.00$730.47

Tasks — TrackVia (10)

TaskCompletedInspectionTeamTask pay
HousewrapDec 11, 2025 7:25 AMPassArmando Segundo-Garcia$323.00
HW: Weather Barrier InspectionDec 15, 2025 8:00 AMPassCity Inspections$55.00
SidingDec 20, 2025 5:30 PMPassArmando Segundo-Garcia$0.00
Soffit/FasciaDec 22, 2025 11:57 AMPassArmando Segundo-Garcia$150.00
VinylDec 22, 2025 2:45 PMPassArmando Segundo-Garcia$0.00
VinylDec 22, 2025 5:05 PMPassArmando Segundo-Garcia$0.00
Soffit/FasciaDec 22, 2025 5:07 PMPassArmando Segundo-Garcia$0.00
QC WalkFeb 3, 2026 10:25 AMPassDaniel Cid$1,311.00
Foundation PlasterJan 17, 2026 10:37 AMPassDiego Martin$0.00
GuttersJan 7, 2026 1:48 PMPassManolo Najarro-Garcia$55.00

47-Mountainside Estates-DR Horton

Mountainside Estates · Ogden Division · Status: 12. Archive · Cascade final: Feb 26, 2026
$2,115.61
Open balance (QB)
$26,560
Total revenue billed
$11,626
Labor costs (burdened)
$14,146
Material POs w/ tax
$25,772
Total hard costs
$787 (3.0%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
78972Feb 5, 2026Apr 6, 2026114d overdue$747.61$747.61
79995Mar 2, 2026May 1, 202689d overdue$1,368.00$1,368.00
Total open$2,115.61$2,115.61

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$4,408.67$4,637.42$11,235.00
Siding$3,663.74$4,960.71$8,586.00
Soffit/Fascia$860.61$1,512.21$3,376.00
Gutters$350.40$897.71$1,246.00
Insulation$0.00$897.71

Tasks — TrackVia (19)

TaskCompletedInspectionTeamTask pay
4-Way PassDec 11, 2025 7:31 PMPassOffice Staff - Orem$343.10
Set ScaffDec 18, 2025 1:27 PMPassSergio Aguilar$0.00
Paper/WireDec 18, 2025 8:24 PMPassSergio Aguilar$40.00
HousewrapDec 18, 2025 8:25 PMPassSergio Aguilar$300.00
HW: Weather Barrier InspectionDec 22, 2025 10:15 AMPassCity Inspections$550.00
PW: Lath InspectionDec 22, 2025 10:15 AMPassCity Inspections$0.00
Set TarpsDec 26, 2025 5:00 PMPassIsaac Arzate Rosas$1,165.00
Stucco BrownDec 26, 2025 5:00 PMPassIsaac Arzate Rosas$0.00
Hardie Soffit/FasciaDec 29, 2025 4:40 PMPassAlberto Bernabe$266.74
SidingDec 31, 2025 6:51 PMPassAlberto Bernabe$250.00
QC WalkFeb 04, 2026 7:45 AMPassJose Renteria$1,800.00
Paint Hardie Soffit/FasciaJan 06, 2026 1:40 PMPassKeren Avila Herrera$0.00
Stucco ColorJan 08, 2026 3:02 PMPassJuan Valentine$250.00
VPO WorkJan 12, 2026 10:41 AMPassAlberto Bernabe$866.00
Soffit/FasciaJan 13, 2026 7:02 PMPassLucio Hernandez$135.00
Remove TarpsJan 14, 2026 4:41 PMPassJuan Pablo Moreno$1,156.93
Remove ScaffJan 14, 2026 4:43 PMPassJuan Pablo Moreno$97.00
GuttersJan 15, 2026 3:55 AMPassEnrique Godinez$450.00
PaintJan 3, 2026 2:13 PMPassKeren Avila Herrera$320.00

Bldg 13-Dixon Creek-DR Horton

Dixon Creek · Ogden Division · Status: 12. Archive · Cascade final: Jul 2, 2026
$2,003.92
Open balance (QB)
$45,031
Total revenue billed
$16,105
Labor costs (burdened)
$19,556
Material POs w/ tax
$35,661
Total hard costs
$9,370 (20.8%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
81120Feb 10, 2026Apr 11, 2026109d overdue$1,730.75$1,730.75
80661Mar 16, 2026May 15, 202675d overdue$273.17$273.17
Total open$2,003.92$2,003.92

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$2,794.71$3,130.37$7,766.20
Rock$0.00$1,202.14$3,691.17
Brick$1,056.13$983.04
Siding$7,941.01$11,363.49$24,217.04
Soffit/Fascia$1,241.79$2,010.52$5,381.65
Gutters$490.80$1,519.78$1,969.28
Insulation$0.00$1,519.78

Tasks — TrackVia (26)

TaskCompletedInspectionTeamTask pay
Base Install CompletePassOffice Staff - Ogden$268.00
WRB PassApr 5, 2026 8:15 PMPass$870.52
4-Way PassFeb 10, 2026 3:50 PMPassOffice Staff - Orem$120.00
Set Brick ScaffFeb 12, 2026 5:33 PMPassJuan Pablo Moreno$139.75
Set ScaffFeb 12, 2026 5:35 PMPassJuan Pablo Moreno$0.00
HousewrapFeb 13, 2026 1:50 PMPassAdan Tiburcio$579.20
Paper/WireFeb 20, 2026 5:23 PMPassGenaro Miramontes$1,132.00
PW: Lath InspectionFeb 23, 2026 8:05 AMPassCity Inspections$866.97
HW: Weather Barrier InspectionFeb 23, 2026 8:06 AMPassCity Inspections$226.00
Stucco BrownFeb 25, 2026 10:07 AMPassErnesto Salcedo$1,211.00
Set TarpsFeb 25, 2026 11:46 AMPassErnesto Salcedo$50.00
SidingFeb 26, 2026 4:21 PMPassEveli Solis$125.38
Remove ScaffMar 04, 2026 4:30 PMPassGenaro Miramontes$89.42
Remove TarpsMar 04, 2026 8:40 AMPassGenaro Miramontes$288.00
BrickMar 10, 2026 8:36 AMPassMoises Ramos$0.00
GuttersMar 11, 2026 10:55 AMPassMaria Estrada Olivarez$145.00
Paint Hardie Soffit/FasciaMar 13, 2026 2:05 PMPassDiego Priego$0.00
Brick WashMar 13, 2026 3:10 PMPassJuan Robles$342.94
Hardie Soffit/FasciaMar 13, 2026 4:49 PMPassEveli Solis$1,083.50
Return/FixMar 18, 2026 11:48 AMPassEveli Solis$847.80
QC WalkMar 19, 2026 9:21 AMPassGeorge Contreras$250.00
Misc. WorkMar 22, 2026 12:00 PMPassDiego Priego$2,000.00
PaintMar 3, 2026 2:30 PMPassDiego Priego$116.00
Misc. WorkMar 30, 2026 7:58 PMPassJose Medardo Rivera Ayala$3,317.00
Stucco ColorMar 4, 2026 8:32 AMPassGenaro Miramontes$50.00
Soffit/FasciaMar 9, 2026 1:11 PMPassJavier Buitimea$140.00

Bldg 2-Midtown Village-DR Horton

Midtown Village · Ogden Division · Status: 12. Archive · Cascade final: May 21, 2026
$1,931.49
Open balance (QB)
$54,840
Total revenue billed
$26,300
Labor costs (burdened)
$24,621
Material POs w/ tax
$50,921
Total hard costs
$3,919 (7.1%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
78166Jan 16, 2026Apr 9, 2026111d overdue$1,931.49$1,931.49
Total open$1,931.49$1,931.49

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$6,644.56$6,868.71$14,678.00
Rock$784.53$10,957.41$20,200.00
Brick$7,605.17$0.00
Siding$3,879.12$4,271.31$11,837.00
Soffit/Fascia$863.91$2,174.20$4,468.00
Gutters$709.20$1,380.59$1,726.00
Insulation$0.00$1,380.59

Tasks — TrackVia (25)

TaskCompletedInspectionTeamTask pay
Set ScaffDec 10, 2025 5:17 PMPassJuan Pablo Moreno$1,186.39
Paper/WireDec 12, 2025 4:20 PMPassSergio Aguilar$0.00
HousewrapDec 12, 2025 4:24 PMPassSergio Aguilar$70.00
HW: Weather Barrier InspectionDec 15, 2025 8:00 AMPassCity Inspections$130.00
Brick Lath InspectionDec 15, 2025 8:00 AMPassCity Inspections$60.00
PW: Lath InspectionDec 15, 2025 8:00 AMPassCity Inspections$827.40
SidingDec 17, 2025 8:31 AMPassCristobal Tellez$40.00
Stucco BrownDec 18, 2025 5:45 PMPassOmar Perez Padilla$411.07
Set TarpsDec 18, 2025 7:00 PMPassOmar Perez Padilla$840.00
PaintDec 19, 2025 5:03 PMPassJuan Rivera$900.00
Scratch CoatDec 22, 2025 12:49 PMPassOmar Perez Padilla$76.00
Woodtone PaintDec 23, 2025 6:25 PMPassJuan Rivera$320.00
BrickDec 25, 2025 8:08 AMPassLincoln Valencia$90.00
Stucco ColorDec 28, 2025 2:00 PMPassOmar Perez Padilla$0.00
Brick WashDec 31, 2025 2:23 PMPassViridiana Nazario$70.00
Fix ScaffDec 31, 2025 4:12 PMPassJuan Pablo Moreno$60.00
4-Way PassDec 8, 2025 2:07 PMPassOffice Staff - Orem$50.00
Misc. WorkFeb 19, 2026 1:33 PMPassAdan Tiburcio$373.84
GuttersJan 04, 2026 2:43 PMPassManolo Najarro-Garcia$125.00
Misc. WorkJan 21, 2026 4:55 AMPassEuddy Enrique Rodriguez-Chima$384.50
Misc. WorkJan 23, 2026 9:46 AMPassManolo Najarro-Garcia$0.00
Remove TarpsJan 3, 2026 3:27 PMPassJuan Pablo Moreno$119.00
Remove ScaffJan 3, 2026 3:29 PMPassJuan Pablo Moreno$0.00
Soffit/FasciaJan 4, 2026 10:43 PMPassAlexis Gaibor$0.00
QC WalkMay 21, 2026 6:30 AMPassGeorge Contreras$3,373.00

Bldg 14-Dixon Creek-DR Horton

Dixon Creek · Ogden Division · Status: 12. Archive · Cascade final: May 16, 2026
$1,730.40
Open balance (QB)
$44,754
Total revenue billed
$15,552
Labor costs (burdened)
$15,591
Material POs w/ tax
$31,143
Total hard costs
$13,612 (30.4%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
81341Feb 20, 2026Apr 21, 202699d overdue$1,730.40$1,730.40
Total open$1,730.40$1,730.40

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$2,814.90$3,022.28$7,766.20
Rock$60.00$554.22$3,691.17
Brick$433.49$0.00
Siding$8,041.26$12,017.86$24,217.04
Soffit/Fascia$1,238.76$2,088.82$5,381.65
Gutters$459.60$886.13$1,969.28
Insulation$0.00$886.13

Tasks — TrackVia (23)

TaskCompletedInspectionTeamTask pay
4-Way PassFeb 20, 2026 8:17 PMPassOffice Staff - Orem$2,430.10
Set ScaffFeb 24, 2026 6:49 PMPassJuan Pablo Moreno$0.00
Set Brick ScaffFeb 24, 2026 6:51 PMPassJuan Pablo Moreno$0.00
HousewrapFeb 26, 2026 10:01 AMPassPedro Aguillar$1,520.77
Paper/WireFeb 27, 2026 9:49 AMPassPedro Aguillar$80.00
Stucco BrownMar 03, 2026 3:59 PMPassArmando Barajas$0.00
Scratch CoatMar 07, 2026 12:06 PMPassLincoln Valencia$866.16
Paint Hardie Soffit/FasciaMar 10, 2026 2:07 PMPassJuan Rivera$91.00
PaintMar 10, 2026 2:40 PMPassJuan Rivera$4,075.75
Soffit/FasciaMar 12, 2026 3:30 PMPassAngel Hernandez Reyez$0.00
Remove TarpsMar 13, 2026 12:10 PMPassIsaac Arzate Rosas$153.00
Remove ScaffMar 13, 2026 4:55 PMPassIsaac Arzate Rosas$219.93
Brick WashMar 16, 2026 3:56 PMPassJuan Robles$257.81
GuttersMar 17, 2026 10:13 AMPassManolo Najarro-Garcia$0.00
QC WalkMar 19, 2026 9:22 AMPassGeorge Contreras$850.00
PW: Lath InspectionMar 2, 2026 2:42 PMPassCity Inspections$0.00
HW: Weather Barrier InspectionMar 2, 2026 2:50 PMPassCity Inspections$704.41
Set TarpsMar 3, 2026 4:00 PMPassArmando Barajas$4.20
Misc. WorkMar 31, 2026 1:55 PMPassJose Medardo Rivera Ayala$0.00
SidingMar 7, 2026 2:49 PMPassJose Fuente$0.00
Hardie Soffit/FasciaMar 8, 2026 12:55 PMPassJose Fuente$400.00
BrickMar 9, 2026 1:13 PMPassLincoln Valencia$50.00
Stucco ColorMar 9, 2026 5:04 PMPassIsaac Arzate Rosas$643.09

124-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 14, 2026
$1,469.00
Open balance (QB)
$28,622
Total revenue billed
$8,670
Labor costs (burdened)
$15,983
Material POs w/ tax
$24,653
Total hard costs
$3,969 (13.9%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
79827Feb 25, 2026Apr 26, 202694d overdue$5,683.00$1,469.00
Total open$5,683.00$1,469.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Siding$7,259.37$8,889.48$21,626.00
Soffit/Fascia$836.24$1,551.86$5,683.00
Gutters$274.80$521.62$1,313.00
Insulation$0.00$521.62

Tasks — TrackVia (9)

TaskCompletedInspectionTeamTask pay
HousewrapFeb 12, 2026 10:06 AMPassIsmael Martinez$394.59
HW: Weather Barrier InspectionFeb 18, 2026 10:30 AMPassCity Inspections$231.25
4-Way PassFeb 25, 2026 1:40 AMPassOffice Staff - Orem$0.00
QC WalkMar 12, 2026 11:13 AMPassAlex Saldana$60.00
SidingMar 4, 2026 3:11 PMPassJavier Perez$692.08
Soffit/FasciaMar 4, 2026 3:21 PMPassJavier Perez$260.00
Hardie Soffit/FasciaMar 4, 2026 3:31 PMPassJavier Perez$0.00
GuttersMar 6, 2026 11:59 AMPassManolo Najarro-Garcia$30.00
Misc. WorkMar 9, 2026 3:59 PMPassWillson Garcia$0.00

Bldg 28-Old Sorrel Ranch-DR Horton

Old Sorrel Ranch · St. George Division · Status: 12. Archive · Cascade final: Oct 14, 2025
$1,300.00
Open balance (QB)
$1,300
Total revenue billed
$540
Labor costs (burdened)
$115
Material POs w/ tax
$655
Total hard costs
$645 (49.6%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
75541Oct 8, 2025Nov 7, 2025264d overdue$1,300.00$1,300.00
Total open$1,300.00$1,300.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$540.00$0.00

Tasks — TrackVia (1)

TaskCompletedInspectionTeamTask pay
Foundation PlasterOctober 13, 2025 1:14 PMPassDiego Martin$0.00

46-Mountainside Estates-DR Horton

Mountainside Estates · Ogden Division · Status: 12. Archive · Cascade final: Mar 27, 2026
$1,150.45
Open balance (QB)
$24,633
Total revenue billed
$9,054
Labor costs (burdened)
$10,693
Material POs w/ tax
$19,747
Total hard costs
$4,886 (19.8%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
81121Feb 10, 2026Apr 11, 2026109d overdue$1,150.45$1,150.45
Total open$1,150.45$1,150.45

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$4,666.39$5,030.48$14,564.00
Rock$714.08$970.83$1,432.00
Siding$692.82$648.53$2,677.00
Soffit/Fascia$1,020.44$1,327.59$3,301.00
Gutters$330.00$1,017.19$1,510.00
Insulation$0.00$1,017.19

Tasks — TrackVia (22)

TaskCompletedInspectionTeamTask pay
4-Way PassFeb 10, 2026 4:53 PMPassOffice Staff - Orem$60.00
Set ScaffFeb 19, 2026 8:00 AMPassMiguel Adame Alvis$59.50
Paper/WireFeb 20, 2026 2:50 PMPassIsmael Martinez$1,081.50
HousewrapFeb 20, 2026 2:52 PMPassIsmael Martinez$481.00
HW: Weather Barrier InspectionFeb 23, 2026 3:30 PMPassCity Inspections$1,052.41
PW: Lath InspectionFeb 23, 2026 3:30 PMPassCity Inspections$761.03
Stucco BrownFeb 26, 2026 7:33 PMPassOmar Perez Padilla$3,805.71
Scratch CoatFeb 26, 2026 7:34 PMPassOmar Perez Padilla$0.00
Set TarpsFeb 26, 2026 7:36 PMPassOmar Perez Padilla$2,335.00
VPO WorkJun 5, 2026 1:33 PMPassMaria Estrada Olivarez$174.00
RockMar 03, 2026 5:19 PMPassRamon Jabalera$241.00
Remove ScaffMar 10, 2026 4:39 PMPassLeonardo Martin San Juan$569.65
Remove TarpsMar 10, 2026 4:42 PMPassLeonardo Martin San Juan$2,333.00
PaintMar 12, 2026 10:26 PMPassDavid Merino$85.45
Paint Hardie Soffit/FasciaMar 12, 2026 10:32 PMPassDavid Merino$0.00
GuttersMar 17, 2026 11:08 AMPassMaria Estrada Olivarez$2,297.28
QC WalkMar 27, 2026 2:16 PMPassJose Renteria$0.00
SidingMar 3, 2026 2:54 PMPassAdan Tiburcio$0.00
Hardie Soffit/FasciaMar 3, 2026 4:20 PMPassAdan Tiburcio$761.03
RockMar 3, 2026 5:19 PMPassRamon Jabalera$843.96
Stucco ColorMar 6, 2026 6:30 PMPassLeonardo Martin San Juan$1,364.67
Soffit/FasciaMar 7, 2026 2:55 PMPassAriel Ramirez$2,095.00

117-Palomino-DR Horton

Palomino · Ogden Division · Status: 12. Archive · Cascade final: Apr 18, 2026
$1,019.90
Open balance (QB)
$21,957
Total revenue billed
$8,202
Labor costs (burdened)
$10,825
Material POs w/ tax
$19,028
Total hard costs
$2,930 (13.3%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
81342Feb 17, 2026Apr 18, 2026102d overdue$1,019.90$1,019.90
Total open$1,019.90$1,019.90

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$3,328.95$3,031.04$9,494.00
Siding$2,542.60$4,551.09$7,118.00
Soffit/Fascia$752.31$1,345.23$3,122.00
Gutters$207.60$717.62$979.00
Insulation$0.00$717.62

Tasks — TrackVia (19)

TaskCompletedInspectionTeamTask pay
QC WalkApr 13, 2026 5:44 PMPassGeorge Contreras$120.00
4-Way PassFeb 17, 2026 5:48 PMPassOffice Staff - Orem$329.20
Set ScaffFeb 24, 2026 7:19 AMPassGuillermo Gonzalez$0.00
HousewrapFeb 27, 2026 10:44 AMPassGuillermo Gonzalez$350.00
Paper/WireFeb 27, 2026 11:06 AMPassGuillermo Gonzalez$0.00
HW: Weather Barrier InspectionFeb 27, 2026 6:45 PMPassCity Inspections$0.00
PW: Lath InspectionFeb 27, 2026 6:45 PMPassCity Inspections$300.00
Set TarpsMar 02, 2026 3:49 PMPassArmando Barajas$315.00
SidingMar 04, 2026 10:14 AMPassAlejandro Rodriguez$779.40
Remove ScaffMar 10, 2026 11:01 AMPassAngel Agustin Benitez$272.40
Remove TarpsMar 10, 2026 11:02 AMPassAngel Agustin Benitez$0.00
PaintMar 10, 2026 12:36 PMPassDiego Priego$428.67
Hardie Soffit/FasciaMar 11, 2026 1:12 PMPassAlejandro Rodriguez$1,498.89
Paint Hardie Soffit/FasciaMar 11, 2026 1:14 PMPassDiego Priego$0.00
Soffit/FasciaMar 12, 2026 6:36 PMPassKelvin Flores$1,008.00
ShuttersMar 13, 2026 2:01 PMPassErnesto Holguin$1,167.00
GuttersMar 16, 2026 1:48 PMPassMaria Estrada Olivarez$308.69
Stucco BrownMar 2, 2026 3:50 PMPassArmando Barajas$450.00
Stucco ColorMar 9, 2026 12:53 PMPassAngel Agustin Benitez$90.00

129-Old Sorrel Ranch-DR Horton

Old Sorrel Ranch · St. George Division · Status: 12. Archive · Cascade final: Jul 9, 2025
$930.00
Open balance (QB)
$1,930
Total revenue billed
$1,248
Labor costs (burdened)
$68
Material POs w/ tax
$1,316
Total hard costs
$614 (31.8%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
79080Feb 9, 2026Apr 10, 2026110d overdue$930.00$930.00
Total open$930.00$930.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$576.00$0.00

Tasks — TrackVia (3)

TaskCompletedInspectionTeamTask pay
VPO WorkDec 2, 2025 12:27 PMPassJorge flores $613.00
Foundation PlasterJul 18, 2025 5:35 PMPassDiego Martin$328.35
VPO WorkNov 19, 2025 6:21 PMPassArmando Segundo-Garcia$140.00

106-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 5, 2026
$238.00
Open balance (QB)
$30,030
Total revenue billed
$10,260
Labor costs (burdened)
$17,576
Material POs w/ tax
$27,835
Total hard costs
$2,195 (7.3%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
78594Jan 27, 2026Mar 28, 2026123d overdue$1,111.00$238.00
Total open$1,111.00$238.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$136.29$275.53
Rock$1,603.19$2,819.91$2,939.00
Siding$6,540.03$6,904.99$21,925.00
Soffit/Fascia$789.85$1,396.17$4,055.00
Gutters$350.40$635.29$1,111.00
Insulation$0.00$635.29

Tasks — TrackVia (20)

TaskCompletedInspectionTeamTask pay
HousewrapFeb 02, 2026 1:28 PMPassRoberto Lamas-Arellano$1,250.00
HW: Weather Barrier InspectionFeb 05, 2026 11:00 AMPassCity Inspections$7,000.00
Scratch CoatFeb 12, 2026 1:29 PMPassErnesto Velasquez$490.39
RockFeb 17, 2026 11:09 AMPassErnesto Velasquez$170.00
Hardie Soffit/FasciaFeb 19, 2026 3:20 PMPassEddie Fuentes$500.00
Soffit/FasciaFeb 19, 2026 5:00 PMPassEddie Fuentes$105.00
SidingFeb 19, 2026 6:00 PMPassEddie Fuentes$86.00
Paper/WireFeb 2, 2026 4:15 PMPassErnesto Velasquez$1,126.62
GuttersFeb 26, 2026 1:47 PMPassManolo Najarro-Garcia$1,875.00
Misc. WorkFeb 26, 2026 4:27 PMPassJuan Rivera$0.00
Return/FixFeb 28, 2026 3:08 PMPassErnesto Velasquez$0.00
PW: Lath InspectionFeb 5, 2026 11:00 AMPassCity Inspections$507.73
Return/FixFeb 5, 2026 4:59 PMPassRoberto Lamas-Arellano$0.00
4-Way PassJan 27, 2026 1:10 PMPassOffice Staff - Orem$970.00
Misc. WorkMar 05, 2026 10:59 AMPassMarcelo Moreta$569.00
Custom WorkMar 1, 2026 4:25 PMPassCristobal Tellez$214.00
Misc. WorkMar 17, 2026 1:48 PMPassCarlos Rodondo$375.00
Misc. WorkMar 19, 2026 2:00 PMPassCarlos Rodondo$553.40
Custom WorkMar 3, 2026 5:00 PMPassWillson Garcia$418.00
QC WalkMar 4, 2026 4:44 PMPassAlex Saldana$1,087.97

123-Montreux-DR Horton

Montreux · Orem Division · Status: 12. Archive · Cascade final: Mar 16, 2026
$209.00
Open balance (QB)
$34,595
Total revenue billed
$10,410
Labor costs (burdened)
$24,052
Material POs w/ tax
$34,462
Total hard costs
$133 (0.4%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
77987Jan 14, 2026Feb 13, 2026166d overdue$34,595.00$209.00
Total open$34,595.00$209.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$256.34$538.85
Rock$3,195.32$5,051.86$12,620.00
Siding$5,449.89$8,781.60$16,796.00
Soffit/Fascia$697.70$1,269.49$3,837.00
Gutters$295.20$543.04$1,342.00
Insulation$0.00$543.04

Tasks — TrackVia (20)

TaskCompletedInspectionTeamTask pay
Scratch CoatFeb 13, 2026 1:48 PMPassZeferino Mendoza$0.00
Return/FixFeb 23, 2026 11:54 AMPassAdan Tiburcio$222.74
RockFeb 23, 2026 2:40 PMPassZeferino Mendoza$50.00
Return/FixFeb 25, 2026 9:49 AMPassZeferino Mendoza$0.00
Return/FixFeb 4, 2026 4:00 PMPassAdan Tiburcio$0.00
HW: Weather Barrier InspectionFeb 5, 2026 10:30 AMPassCity Inspections$1,161.00
PW: Lath InspectionFeb 5, 2026 10:30 AMPassCity Inspections$1,356.26
4-Way PassJan 13, 2026 6:20 PMPassOffice Staff - Orem$27.00
HousewrapJan 17, 2026 3:35 PMPassAdan Tiburcio$1,345.00
Paper/WireJan 28, 2026 5:38 PMPassSergio Saligan$0.00
Soffit/FasciaMar 05, 2026 2:00 PMPassEddie Fuentes$924.42
Fix ScaffMar 1, 2026 11:43 AMPassAlan Gonzalez$3,476.00
Return/FixMar 11, 2026 12:36 PMPassEddie Fuentes$752.85
QC WalkMar 12, 2026 10:59 AMPassAlex Saldana$54.00
Misc. WorkMar 13, 2026 7:15 AMPassJavier Perez$30.00
Soffit/FasciaMar 3, 2026 7:58 PMPassEddie Fuentes$100.00
SidingMar 3, 2026 7:59 PMPassEddie Fuentes$279.50
SidingMar 5, 2026 4:30 PMPassEddie Fuentes$278.00
GuttersMar 6, 2026 11:58 AMPassManolo Najarro-Garcia$0.00
Misc. WorkMar 9, 2026 3:57 PMPassWillson Garcia$395.33

113-Old Sorrel Ranch-DR Horton

Old Sorrel Ranch · St. George Division · Status: 12. Archive · Cascade final: Feb 11, 2026
$200.00
Open balance (QB)
$24,863
Total revenue billed
$14,077
Labor costs (burdened)
$14,152
Material POs w/ tax
$28,229
Total hard costs
$-3,366 (-13.5%)
Gross profit

Open invoices — QuickBooks

Invoice #Invoice dateDue dateAgingAmountOpen balance
79079Dec 12, 2025Feb 10, 2026169d overdue$200.00$200.00
Total open$200.00$200.00

Cost & PO breakdown by trade — TrackVia

TradeLabor costMaterial costBuilder PO amount
Stucco$5,564.91$5,731.25
Siding$3,723.43$4,210.36
Soffit/Fascia$1,146.95$1,748.12
Gutters$284.40$0.00

Tasks — TrackVia (19)

TaskCompletedInspectionTeamTask pay
Set ScaffDec 22, 2025 6:43 PMPassDiego Martin$1,514.01
Paper/WireDec 28, 2025 9:31 AMPassNahum Jaurez Jimenez$135.25
Paper/WireDec 29, 2025 5:43 PMPassNahum Jaurez Jimenez$30.00
HousewrapDec 29, 2025 5:48 PMPassNahum Jaurez Jimenez$90.00
Foundation PlasterFeb 10, 2026 5:22 PMPassDiego Martin$0.00
QC WalkFeb 13, 2026 1:33 PMPassJuan Gracia Acero$2,339.00
PW: Lath InspectionJan 02, 2026 9:00 AMPassCity Inspections$1,275.00
PaintJan 14, 2026 5:15 PMPassRoberto Carlos Bibiano Vargas$0.00
Stucco BrownJan 14, 2026 5:44 PMPassDiego Martin$1,906.45
Set TarpsJan 15, 2026 11:25 AMPassDiego Martin$0.00
Return/FixJan 19, 2026 9:03 AMPassJuan Melendez$105.00
HW: Weather Barrier InspectionJan 2, 2026 9:00 AMPassCity Inspections$0.00
Stucco ColorJan 20, 2026 2:19 PMPassDiego Martin$1,212.05
Soffit/FasciaJan 22, 2026 8:47 PMPassArmando Segundo-Garcia$194.54
Misc. WorkJan 29, 2026 7:24 PMPassDiego Martin$0.00
Remove TarpsJan 29, 2026 7:30 PMPassDiego Martin$60.00
Remove ScaffJan 29, 2026 7:33 PMPassDiego Martin$0.00
GuttersJan 30, 2026 4:37 PMPassManolo Najarro-Garcia$714.16
SidingJan 7, 2026 9:11 PMPassJuan Melendez$50.00
Sources: QuickBooks Online A/R Aging Detail (accrual basis, as of July 29, 2026); TrackVia full exports — Tasks General (65,295 records), Job Revenue & Profitability (7,132 records), exported Jul 29, 2026. Jobs included: every DR Horton sub-customer with at least one open invoice 91+ days past due. All open invoices for those jobs are listed, including ones not yet 91 days old.