Hardie Siding Efficiency

Square feet of siding installed per man-hour on Hardie jobs, and what moves it: job size, return trips, crews, builders, product and division. Cascade Build. Jobs with a Siding task completed Jan 2023 to Sep 18, 2026.

built Sep 18, 20262,947 Hardie jobs · 5.5M sq ft · 97K crew-hourssource: TrackVia beta MCP, views 3045 · 3046 · 114

Where Hardie stands

all Hardie jobs, 2023 to date
Sq ft per man-hour · median job
12.9
middle half of jobs: 7.5 to 22.3
crew hours × current crew headcount
Sq ft per crew-hour · median job
48
2,947 jobs · 4.7-person crews
headcount-free; all crews included
Time on site · median job
2.5
work days · 1,008 sq ft
29% of jobs need a second siding visit
Labor pay per sq ft
$1.58
Task Pay ÷ net sq ft
nearly flat across cuts: footage and pay agree
Two things set the pace on a Hardie job: how big it is and whether the crew has to come back. Efficiency more than triples from small accent jobs to whole-building jobs because mobilization, scaffold access and layout are paid once per job. Jobs that need a second siding task run at two thirds the pace of jobs done in one visit. Everything else in this report is measured after removing the job-size effect.

Job size · Hardie jobs

Job sizeJobsSq ft / crew-hrSq ft / man-hrCrewDays on sitePay / sq ft
< 1,000 sq ft1,45228.57.04.22.0$1.75
1,000 – 2,00042339.79.74.42.7$1.66
2,000 – 4,00075570.616.25.24.0$1.55
4,000 +31796.718.86.05.0$1.51

Half of Hardie jobs are under 1,000 sq ft: siding accents on stucco homes. Those jobs cost 16% more per sq ft in labor and install at a third of the pace of a full-siding building. For reference, LP jobs run 20 sq ft per man-hour overall, but they are three times larger; within the same size band LP is within 5 to 10 percent of Hardie on small jobs and up to 29 percent ahead on 2,000 to 4,000 sq ft jobs.

Stack ranks · Hardie jobs

size-adjusted index · 1.00 = typical for that job size · cells under 8 jobs omitted

The index divides each job's sq ft per crew-hour by the median for its brand and size band, then takes the group median. It removes the job-size effect so a crew that only gets small accent jobs is not penalized.

Crews · headcount known

TeamHardie jobsIndexSq ft / crew-hrSq ft / man-hrCrewDays on siteMedian job sq ftPay / sq ft
Mario H Ortiz-Guevara1631.8415016.792.03,577$1.61
Hilton Medina941.789932.832.02,802$1.63
Innacio Portio1671.6312117.372.53,586$1.53
Adan Tiburcio241.467913.162.01,708$1.48
Nollan Sierra1141.3611027.343.03,198$1.51
Olman Sierra1081.167314.753.02,971$1.54
Virgilio Cabrera1191.14618.772.01,036$1.54
Eveli Solis1191.097017.543.02,585$1.56
Alex Salinas1391.085217.532.0948$1.59
Kevin Hernandez1040.98405.972.5912$1.64
Mario Herrera1270.953812.532.0776$1.57
Luis Chavarria1360.93348.542.0860$1.65
Agustin Ramirez1070.904310.043.0979$1.56
Armando Segundo-Garcia1250.72283.682.0610$2.07
Joaquin Feresin1340.68225.443.0796$1.63
Efrain Diaz-Lopez840.682323.113.0794$1.62
Alberto Bernabe160.613712.234.71,214$1.46
Roberto Cruz1360.582210.822.0338$2.09
Ismael Soto100.43237.834.51,084$1.55

32 crews qualify; the middle of the table is in the CSV. Two now-inactive crews rank above everyone on crew-hours but have no headcount on file: Amilcar Sosa (102 jobs, index 2.01, one-day jobs) and Rigoberto Sierra-Arias (30 jobs, 2.27). Per person, Hilton Medina's three-man crew is the standout at 33 sq ft per man-hour, roughly 2.5× the Hardie median. Armando Segundo-Garcia's 8-person headcount and 3.6 sq ft per man-hour look like a roster problem rather than a crew problem.

Builders

BuilderHardie jobsIndexSq ft / crew-hrSq ft / man-hrDays on siteMedian job sq ftPay / sq ft
Cottonwood Cove HOA212.407020.21.01,438$1.63
Century261.4012224.92.83,006$1.39
McArthur401.194313.02.01,106$1.55
Woodside3711.165413.22.0888$1.57
Hamlet911.047418.03.32,772$1.50
DR Horton (baseline)1,5241.026313.82.51,048$1.57
Richmond1551.01337.92.0750$1.64
Element Homes1200.98347.91.0364$1.62
Pulte Homes290.82349.82.0417$1.55
Toll Brothers1090.806015.54.02,673$1.66
Visionary1190.68296.53.0728$1.86
Meritage Homes1020.635014.26.03,082$1.42
Fieldstone Homes140.54489.86.83,286$1.60

Meritage and Fieldstone homes sit open six to seven days against a 2.5-day norm; Toll Brothers four. Those are the builders where sequencing with other trades, not crew speed, is most likely eating the hours. Visionary combines slow jobs with the highest pay per sq ft.

Division and area

CutHardie jobsIndexSq ft / crew-hrSq ft / man-hrMedian job sq ftPay / sq ft
Salt Lake division6041.215914.6948$1.61
Orem division1,8181.006113.61,111$1.55
Ogden division1750.855212.51,281$1.48
St. George division3330.67266.1362$2.02
By the crew's home division: Salt Lake crews 1.35 · Orem 0.97 · Ogden 0.83 · St. George 0.66. Top areas: North Salt Lake County 1.26, South Salt Lake County 1.24, NE Utah County 1.15. Bottom: Wasatch County 0.73, Southern Utah 0.68, Iron County 0.58.

Material and product

CutHardie jobsIndexSq ft / crew-hrSq ft / man-hrDays on siteMedian job sq ft
Board & batten dominant1,0171.034911.32.0885
Lap 8¼" dominant1,4101.005713.73.01,084
Mixed profiles4250.947115.33.02,861
V-Groove dominant160.663810.34.01,566
Lap 12" dominant170.57487.13.22,685
ColorPlus (prefinished)1580.605013.56.03,156
Primed2,2381.025913.42.5981
Smooth texture180.61357.52.0458
Hardie trim1,6761.006013.53.01,200
Miratec trim1,2501.015112.42.0873
Single-family2,2780.994510.92.0859
Building / multifamily6691.028317.14.03,614

Board and batten and 8¼" lap install at the same pace once size is accounted for. ColorPlus jobs sit open six days against 2.5, the clearest product effect in the data, though 158 jobs is a modest cell. Trim brand makes no difference. Buildings look faster only because they are big.

Crew size, year and return trips

CutHardie jobsIndexSq ft / crew-hrSq ft / man-hrDays on siteMedian job sq ft
3-person crews5520.965016.52.0930
4-person crews6470.955212.73.01,014
5-person crews1221.086713.33.02,932
7-person crews3921.298011.52.52,422
9-person crews1631.8415016.72.03,577
Hardie 20238451.125412.32.51,012
Hardie 20247040.975913.02.7942
Hardie 20256231.056213.22.0897
Hardie 2026 YTD7750.865414.03.01,243
One siding task on the job2,0831.166114.92.0887
Two or more siding tasks (return trips)8640.685111.45.02,708

Big crews move the most wall per day; small crews are the most productive per person. LP held an index near 1.00 in every year while Hardie drifted from 1.12 in 2023 to 0.86 so far in 2026. Return trips cost the most of anything measured: 29% of Hardie jobs carry a second siding task, and those jobs run at two thirds the pace.

What this suggests

internal read
The envelope gets more efficient by cutting return trips and grouping small jobs, not by hanging board faster. 29% of Hardie jobs carry a second siding task and run at two thirds the pace. Small accent jobs cost 16% more labor per sq ft than full-siding jobs; sequencing several accent lots for one crew in one mobilization is where the hours are.
Three crews set the pace on Hardie: Ortiz-Guevara, Medina and Portio. Medina's three-man crew at 33 sq ft per man-hour is the model for small crews; Ortiz-Guevara's nine-man crew for buildings. Segundo-Garcia's numbers need a roster check before anyone reads them as performance.
Meritage, Fieldstone and Toll jobs sit open two to three times longer than the norm. That is a scheduling and sequencing question for those builders more than a crew question.
ColorPlus needs its own plan. Six days on site versus 2.5 for primed board. If prefinished volume grows, staging, handling and touch-up protocol is where the hours are.
Watch the 2026 slide. Hardie efficiency is down about 20% from 2023 on a size-adjusted basis while LP is flat. Worth a look at whether it is crew mix, more return trips, or open-task hygiene.

Method and caveats

read before quoting