Square feet of siding installed per man-hour on Hardie jobs, and what moves it: job size, return trips, crews, builders, product and division. Cascade Build. Jobs with a Siding task completed Jan 2023 to Sep 18, 2026.
| Job size | Jobs | Sq ft / crew-hr | Sq ft / man-hr | Crew | Days on site | Pay / sq ft |
|---|---|---|---|---|---|---|
| < 1,000 sq ft | 1,452 | 28.5 | 7.0 | 4.2 | 2.0 | $1.75 |
| 1,000 – 2,000 | 423 | 39.7 | 9.7 | 4.4 | 2.7 | $1.66 |
| 2,000 – 4,000 | 755 | 70.6 | 16.2 | 5.2 | 4.0 | $1.55 |
| 4,000 + | 317 | 96.7 | 18.8 | 6.0 | 5.0 | $1.51 |
Half of Hardie jobs are under 1,000 sq ft: siding accents on stucco homes. Those jobs cost 16% more per sq ft in labor and install at a third of the pace of a full-siding building. For reference, LP jobs run 20 sq ft per man-hour overall, but they are three times larger; within the same size band LP is within 5 to 10 percent of Hardie on small jobs and up to 29 percent ahead on 2,000 to 4,000 sq ft jobs.
The index divides each job's sq ft per crew-hour by the median for its brand and size band, then takes the group median. It removes the job-size effect so a crew that only gets small accent jobs is not penalized.
| Team | Hardie jobs | Index | Sq ft / crew-hr | Sq ft / man-hr | Crew | Days on site | Median job sq ft | Pay / sq ft |
|---|---|---|---|---|---|---|---|---|
| Mario H Ortiz-Guevara | 163 | 1.84 | 150 | 16.7 | 9 | 2.0 | 3,577 | $1.61 |
| Hilton Medina | 94 | 1.78 | 99 | 32.8 | 3 | 2.0 | 2,802 | $1.63 |
| Innacio Portio | 167 | 1.63 | 121 | 17.3 | 7 | 2.5 | 3,586 | $1.53 |
| Adan Tiburcio | 24 | 1.46 | 79 | 13.1 | 6 | 2.0 | 1,708 | $1.48 |
| Nollan Sierra | 114 | 1.36 | 110 | 27.3 | 4 | 3.0 | 3,198 | $1.51 |
| Olman Sierra | 108 | 1.16 | 73 | 14.7 | 5 | 3.0 | 2,971 | $1.54 |
| Virgilio Cabrera | 119 | 1.14 | 61 | 8.7 | 7 | 2.0 | 1,036 | $1.54 |
| Eveli Solis | 119 | 1.09 | 70 | 17.5 | 4 | 3.0 | 2,585 | $1.56 |
| Alex Salinas | 139 | 1.08 | 52 | 17.5 | 3 | 2.0 | 948 | $1.59 |
| Kevin Hernandez | 104 | 0.98 | 40 | 5.9 | 7 | 2.5 | 912 | $1.64 |
| Mario Herrera | 127 | 0.95 | 38 | 12.5 | 3 | 2.0 | 776 | $1.57 |
| Luis Chavarria | 136 | 0.93 | 34 | 8.5 | 4 | 2.0 | 860 | $1.65 |
| Agustin Ramirez | 107 | 0.90 | 43 | 10.0 | 4 | 3.0 | 979 | $1.56 |
| Armando Segundo-Garcia | 125 | 0.72 | 28 | 3.6 | 8 | 2.0 | 610 | $2.07 |
| Joaquin Feresin | 134 | 0.68 | 22 | 5.4 | 4 | 3.0 | 796 | $1.63 |
| Efrain Diaz-Lopez | 84 | 0.68 | 23 | 23.1 | 1 | 3.0 | 794 | $1.62 |
| Alberto Bernabe | 16 | 0.61 | 37 | 12.2 | 3 | 4.7 | 1,214 | $1.46 |
| Roberto Cruz | 136 | 0.58 | 22 | 10.8 | 2 | 2.0 | 338 | $2.09 |
| Ismael Soto | 10 | 0.43 | 23 | 7.8 | 3 | 4.5 | 1,084 | $1.55 |
32 crews qualify; the middle of the table is in the CSV. Two now-inactive crews rank above everyone on crew-hours but have no headcount on file: Amilcar Sosa (102 jobs, index 2.01, one-day jobs) and Rigoberto Sierra-Arias (30 jobs, 2.27). Per person, Hilton Medina's three-man crew is the standout at 33 sq ft per man-hour, roughly 2.5× the Hardie median. Armando Segundo-Garcia's 8-person headcount and 3.6 sq ft per man-hour look like a roster problem rather than a crew problem.
| Builder | Hardie jobs | Index | Sq ft / crew-hr | Sq ft / man-hr | Days on site | Median job sq ft | Pay / sq ft |
|---|---|---|---|---|---|---|---|
| Cottonwood Cove HOA | 21 | 2.40 | 70 | 20.2 | 1.0 | 1,438 | $1.63 |
| Century | 26 | 1.40 | 122 | 24.9 | 2.8 | 3,006 | $1.39 |
| McArthur | 40 | 1.19 | 43 | 13.0 | 2.0 | 1,106 | $1.55 |
| Woodside | 371 | 1.16 | 54 | 13.2 | 2.0 | 888 | $1.57 |
| Hamlet | 91 | 1.04 | 74 | 18.0 | 3.3 | 2,772 | $1.50 |
| DR Horton (baseline) | 1,524 | 1.02 | 63 | 13.8 | 2.5 | 1,048 | $1.57 |
| Richmond | 155 | 1.01 | 33 | 7.9 | 2.0 | 750 | $1.64 |
| Element Homes | 120 | 0.98 | 34 | 7.9 | 1.0 | 364 | $1.62 |
| Pulte Homes | 29 | 0.82 | 34 | 9.8 | 2.0 | 417 | $1.55 |
| Toll Brothers | 109 | 0.80 | 60 | 15.5 | 4.0 | 2,673 | $1.66 |
| Visionary | 119 | 0.68 | 29 | 6.5 | 3.0 | 728 | $1.86 |
| Meritage Homes | 102 | 0.63 | 50 | 14.2 | 6.0 | 3,082 | $1.42 |
| Fieldstone Homes | 14 | 0.54 | 48 | 9.8 | 6.8 | 3,286 | $1.60 |
Meritage and Fieldstone homes sit open six to seven days against a 2.5-day norm; Toll Brothers four. Those are the builders where sequencing with other trades, not crew speed, is most likely eating the hours. Visionary combines slow jobs with the highest pay per sq ft.
| Cut | Hardie jobs | Index | Sq ft / crew-hr | Sq ft / man-hr | Median job sq ft | Pay / sq ft |
|---|---|---|---|---|---|---|
| Salt Lake division | 604 | 1.21 | 59 | 14.6 | 948 | $1.61 |
| Orem division | 1,818 | 1.00 | 61 | 13.6 | 1,111 | $1.55 |
| Ogden division | 175 | 0.85 | 52 | 12.5 | 1,281 | $1.48 |
| St. George division | 333 | 0.67 | 26 | 6.1 | 362 | $2.02 |
| By the crew's home division: Salt Lake crews 1.35 · Orem 0.97 · Ogden 0.83 · St. George 0.66. Top areas: North Salt Lake County 1.26, South Salt Lake County 1.24, NE Utah County 1.15. Bottom: Wasatch County 0.73, Southern Utah 0.68, Iron County 0.58. | ||||||
| Cut | Hardie jobs | Index | Sq ft / crew-hr | Sq ft / man-hr | Days on site | Median job sq ft |
|---|---|---|---|---|---|---|
| Board & batten dominant | 1,017 | 1.03 | 49 | 11.3 | 2.0 | 885 |
| Lap 8¼" dominant | 1,410 | 1.00 | 57 | 13.7 | 3.0 | 1,084 |
| Mixed profiles | 425 | 0.94 | 71 | 15.3 | 3.0 | 2,861 |
| V-Groove dominant | 16 | 0.66 | 38 | 10.3 | 4.0 | 1,566 |
| Lap 12" dominant | 17 | 0.57 | 48 | 7.1 | 3.2 | 2,685 |
| ColorPlus (prefinished) | 158 | 0.60 | 50 | 13.5 | 6.0 | 3,156 |
| Primed | 2,238 | 1.02 | 59 | 13.4 | 2.5 | 981 |
| Smooth texture | 18 | 0.61 | 35 | 7.5 | 2.0 | 458 |
| Hardie trim | 1,676 | 1.00 | 60 | 13.5 | 3.0 | 1,200 |
| Miratec trim | 1,250 | 1.01 | 51 | 12.4 | 2.0 | 873 |
| Single-family | 2,278 | 0.99 | 45 | 10.9 | 2.0 | 859 |
| Building / multifamily | 669 | 1.02 | 83 | 17.1 | 4.0 | 3,614 |
Board and batten and 8¼" lap install at the same pace once size is accounted for. ColorPlus jobs sit open six days against 2.5, the clearest product effect in the data, though 158 jobs is a modest cell. Trim brand makes no difference. Buildings look faster only because they are big.
| Cut | Hardie jobs | Index | Sq ft / crew-hr | Sq ft / man-hr | Days on site | Median job sq ft |
|---|---|---|---|---|---|---|
| 3-person crews | 552 | 0.96 | 50 | 16.5 | 2.0 | 930 |
| 4-person crews | 647 | 0.95 | 52 | 12.7 | 3.0 | 1,014 |
| 5-person crews | 122 | 1.08 | 67 | 13.3 | 3.0 | 2,932 |
| 7-person crews | 392 | 1.29 | 80 | 11.5 | 2.5 | 2,422 |
| 9-person crews | 163 | 1.84 | 150 | 16.7 | 2.0 | 3,577 |
| Hardie 2023 | 845 | 1.12 | 54 | 12.3 | 2.5 | 1,012 |
| Hardie 2024 | 704 | 0.97 | 59 | 13.0 | 2.7 | 942 |
| Hardie 2025 | 623 | 1.05 | 62 | 13.2 | 2.0 | 897 |
| Hardie 2026 YTD | 775 | 0.86 | 54 | 14.0 | 3.0 | 1,243 |
| One siding task, one payroll week | 2,083 | 1.16 | 61 | 14.9 | 2.0 | 887 |
| Same crew, split across payroll weeks | 822 | 0.69 | — | — | 8 cal. | — |
| Two or more crews on the job | 42 | 0.53 | — | — | 11 cal. | — |
Big crews move the most wall per day; small crews are the most productive per person. LP held an index near 1.00 in every year while Hardie drifted from 1.12 in 2023 to 0.86 so far in 2026. Split jobs read slow because they are the jobs that ran long enough to cross a Thursday payroll close (first task closed Monday or Friday in 81% of them), so the split is a symptom of a long job, not a cause. The 42 two-crew jobs are the big, hard ones where a second crew was added for speed.
"Needed more" means Hardie board products (lap, panel, trim, corners, shake) ordered after the crew's Siding task had already started, from the 2026 PO line items. Staged deliveries are normal (85% of jobs receive material in more than one delivery), and paint and consumable orders costed to Siding are excluded, so this is the narrowest defensible test of a crew running short. 469 jobs. The lap ratio divides lap sq ft ordered (12' boards, exposure = width minus 1¼") by the job's net lap footage.
| Crew | Jobs | Jobs with a re-order | Re-order share of board $ | Will-call share | Lap ordered ÷ net | Board $ | Median job sq ft |
|---|---|---|---|---|---|---|---|
| Elias Prudente | 13 | 46% | 14.2% | 0.7% | 1.20 | $71K | 2,231 |
| Roberto Cruz | 26 | 12% | 13.1% | 9.7% | — | $26K | 326 |
| Eddie Fuentes | 14 | 64% | 11.7% | 0.2% | 1.12 | $71K | 2,491 |
| Adan Tiburcio | 21 | 43% | 10.1% | 0.0% | 1.08 | $96K | 1,131 |
| Armando Adame | 10 | 60% | 9.8% | 0.1% | 1.15 | $51K | 3,045 |
| Alex Salinas | 21 | 67% | 9.5% | 2.9% | 1.10 | $152K | 2,667 |
| Agustin Ramirez | 11 | 64% | 9.4% | 0.0% | 1.28 | $74K | 2,780 |
| Virgilio Cabrera | 17 | 41% | 8.6% | 0.8% | 1.07 | $72K | 2,189 |
| Alejandro Rodriguez | 13 | 69% | 7.1% | 2.5% | 1.11 | $79K | 2,661 |
| Fernando Abelino | 19 | 63% | 6.5% | 1.5% | 1.04 | $91K | 2,716 |
| Innacio Portio | 31 | 61% | 6.1% | 0.1% | 1.03 | $220K | 3,929 |
| Nollan Sierra | 12 | 50% | 5.9% | 0.1% | 1.01 | $27K | 2,638 |
| Gerardo Juarez | 12 | 75% | 5.8% | 1.0% | 1.18 | $139K | 3,366 |
| Jorge Danilo-Baquedano | 14 | 71% | 5.5% | 0.1% | 0.98 | $57K | 3,639 |
| Eveli Solis | 17 | 76% | 5.5% | 0.3% | 1.06 | $183K | 3,341 |
| Joaquin Feresin | 14 | 43% | 5.5% | 0.3% | 1.13 | $25K | 649 |
| Olman Sierra | 11 | 64% | 4.9% | 0.2% | 0.96 | $59K | 3,406 |
| Mario Herrera | 14 | 29% | 3.3% | 1.2% | 1.10 | $27K | 654 |
| Mario H Ortiz-Guevara | 18 | 44% | 3.0% | 0.1% | 1.04 | $78K | 3,404 |
| Armando Segundo-Garcia | 16 | 12% | 2.3% | 0.0% | 1.08 | $28K | 502 |
| Efrain Diaz-Lopez | 15 | 33% | 1.1% | 0.0% | 1.11 | $31K | 808 |
| Alfredo Barnica | 9 | 0% | 0.0% | 0.0% | — | $17K | 765 |
Prudente, Fuentes, Ramirez and Juarez both re-order more and order more lap than the footage calls for (ratios 1.12 to 1.28), the pattern waste or cut loss would leave. Ramirez's 1.28 is the largest in the data. Roberto Cruz's 13% sits on 326 sq ft accent jobs where one extra box swings the ratio, and most of it is will-call. Olman Sierra, Danilo-Baquedano and Nollan Sierra run low re-orders and order lap at or under net footage.
| Cut | Jobs | Jobs with a re-order | Re-order share of board $ | Will-call share | Lap ordered ÷ net | Median job sq ft |
|---|---|---|---|---|---|---|
| Pulte Homes | 21 | 57% | 18.9% | 0.1% | 1.02 | 479 |
| Visionary | 14 | 50% | 14.6% | 12.6% | 1.08 | 804 |
| Meritage Homes | 63 | 70% | 9.7% | 0.6% | 1.12 | 2,982 |
| Toll Brothers | 18 | 78% | 6.5% | 0.6% | 0.94 | 3,978 |
| DR Horton (baseline) | 181 | 46% | 5.8% | 0.9% | 1.05 | 1,034 |
| McArthur | 25 | 20% | 2.0% | 0.1% | 1.13 | 868 |
| Woodside | 34 | 32% | 1.1% | 0.7% | 1.10 | 912 |
| Keystone Construction | 13 | 15% | 0.3% | 0.0% | 1.14 | 347 |
| St. George division | 46 | 20% | 10.0% | 7.4% | 1.08 | 384 |
| Ogden division | 101 | 47% | 7.4% | 0.0% | 1.08 | 1,198 |
| Orem division | 255 | 57% | 6.8% | 0.9% | 1.06 | 2,780 |
| Salt Lake division | 63 | 38% | 3.5% | 0.4% | 1.12 | 909 |
Pulte, Visionary and Meritage lead by a wide margin, and Visionary alone accounts for most will-call pickups. That points at takeoffs and plan changes on those builders rather than at any one crew. The multi-year cost view agrees that crews are fairly uniform: siding material dollars per net sq ft on all 2,937 Hardie jobs since 2023, size-adjusted, puts nearly every crew between 0.92 and 1.05 of typical; the outliers above 1.2 are small St. George accent crews.
Caveats: ordering is done by the office from footage, so a re-order can mean a short takeoff, a plan change, damage or waste, and the PO data does not say which. Lap ratios assume 12-foot boards against estimated, not as-built, footage. Cells under 10 jobs are fragile. The leftover-material checkbox on the task would be the direct waste signal and is not in this pull.