Ogden Division — On-Time Performance & Task Duration Report
Job Scheduling & Milestone Info, Task Pay Info, and Tasks General — Ogden Division only
"On-time" = Major Tasks Completion Date vs. Target End Date (Cascade's internal schedule
commitment, not the builder-facing Client End Date). A job scored "Late" if major work
finished after the target date, even by one day. 270 of 319 Ogden
job records had both dates populated and could be scored.
1. Is the KPI right? On-time vs. late
Verified: 141 of 270 scored jobs (52%) finished major work
after the target date — more jobs late than on time. The KPI reflects real underlying
performance, not a reporting artifact.
Worst-delayed jobs (top 15)
| Job | Builder | Target End Date | Major Tasks Completed | Days Late | Status |
| 222-Whisper Ridge-Premier Constructors | Premier Constructors | 2026-02-12 | 2026-04-22 | +69 | Late |
| Bldg 51-Western Acres Townhomes-DR Horton | DR Horton | 2025-12-30 | 2026-02-26 | +58 | Late |
| 32 (Stoddard)-East Shore-Sierra Homes | Sierra Homes | 2026-02-10 | 2026-03-24 | +42 | Late |
| 223-Whisper Ridge-Premier Constructors | Premier Constructors | 2026-02-27 | 2026-04-10 | +42 | Late |
| 12-Fairway Estates-Visionary | Visionary | 2026-04-21 | 2026-05-25 | +34 | Late |
| Units 7-12-Smithfield Crest-Sierra Homes | Sierra Homes | 2026-05-01 | 2026-06-01 | +31 | Late |
| 223-Riverside Estates-Fieldstone Homes | Fieldstone Homes | 2026-04-08 | 2026-05-07 | +29 | Late |
| Irva Tooele Retail Drive Through-Commercial-Affinity Construction | Affinity Construction | 2026-05-15 | 2026-06-10 | +26 | Late |
| 2-Sunset Ridges-Sierra Homes | Sierra Homes | 2026-05-22 | 2026-06-17 | +26 | Late |
| TH 1-Flint Acres-Henry Walker Homes | Henry Walker Homes | 2026-01-09 | 2026-02-04 | +26 | Late |
| 14-Fairway Estates-Visionary | Visionary | 2026-04-30 | 2026-05-25 | +25 | Late |
| Bldg 19-Railrunner-VGI | VGI | 2026-01-14 | 2026-02-07 | +24 | Late |
| 302-Legacy Park-Ivory | Ivory | 2026-05-13 | 2026-06-05 | +23 | Late |
| Bldg 9-Midtown Village-DR Horton | DR Horton | 2026-06-02 | 2026-06-24 | +22 | Late |
| Units 150-153-Trailside Lexington Townhomes-Destination Homes | Destination Homes | 2026-04-07 | 2026-04-29 | +22 | Late |
2. Which tasks take the longest?
Based on 3574 completed Ogden task records with a logged duration
(Task Pay Info, "Task Duration Business Hours" — actual clock time from task start to completion).
Sorted by total hours consumed across all jobs — this shows where crew time is going in aggregate.
| Task | Count | Avg Hrs | Median Hrs | Max Hrs | Total Hrs |
| Siding | 311 | 32.0 | 21.8 | 252.8 | 9,942 |
| Soffit/Fascia | 313 | 23.6 | 12.3 | 205.4 | 7,396 |
| Vinyl | 73 | 55.2 | 48.0 | 205.4 | 4,029 |
| Paper/Wire | 256 | 12.8 | 8.0 | 180.3 | 3,288 |
| Paint | 245 | 9.0 | 6.2 | 200.0 | 2,213 |
| Brick | 25 | 86.6 | 31.9 | 592.0 | 2,165 |
| Rock | 101 | 20.1 | 15.5 | 87.8 | 2,035 |
| Stucco Color | 187 | 10.0 | 7.9 | 50.0 | 1,862 |
| Set Scaff | 217 | 8.1 | 5.3 | 106.2 | 1,768 |
| Housewrap | 205 | 7.8 | 5.3 | 171.5 | 1,591 |
| Gutters | 280 | 4.7 | 1.1 | 198.4 | 1,312 |
| Stucco Brown | 151 | 7.1 | 6.4 | 40.0 | 1,069 |
| Misc. Work | 176 | 5.8 | 0.0 | 214.9 | 1,021 |
| Remove Scaff | 202 | 4.0 | 1.8 | 71.3 | 812 |
| Scratch Coat | 127 | 6.3 | 2.5 | 108.0 | 794 |
| Brick Wash | 32 | 21.0 | 1.6 | 215.6 | 673 |
| VPO Work | 193 | 2.7 | 0.0 | 55.7 | 519 |
| Set Tarps | 71 | 5.8 | 2.6 | 93.8 | 411 |
| Remove Tarps | 73 | 4.3 | 0.0 | 136.0 | 315 |
| Brown & Mesh | 40 | 6.3 | 7.2 | 24.0 | 253 |
| Custom Work | 18 | 10.2 | 0.4 | 81.2 | 184 |
| Return/Fix | 75 | 2.0 | 0.0 | 60.5 | 151 |
| Hardie Soffit/Fascia | 15 | 8.5 | 1.0 | 86.3 | 127 |
| Foundation Plaster | 20 | 5.3 | 2.0 | 35.4 | 106 |
| Fix Scaff | 47 | 1.5 | 0.0 | 27.0 | 72 |
| Woodtone Paint | 5 | 8.0 | 8.0 | 16.1 | 40 |
| Window Pre Wrap | 14 | 2.7 | 0.0 | 14.7 | 38 |
| Watering | 16 | 2.4 | 0.0 | 17.0 | 38 |
| Warranty Work | 13 | 2.6 | 0.3 | 21.5 | 34 |
| Mesh Coat | 1 | 32.0 | 32.0 | 32.0 | 32 |
| Paint Hardie Soffit/Fascia | 16 | 1.9 | 0.5 | 8.0 | 31 |
| Shutters | 20 | 1.5 | 0.2 | 17.9 | 29 |
| Special Corbels | 4 | 5.7 | 4.4 | 14.0 | 23 |
| Painted Brick | 5 | 3.4 | 3.7 | 6.6 | 17 |
| Set Brick Scaff | 10 | 1.0 | 0.0 | 8.9 | 10 |
| Scaff Pickup | 14 | 0.2 | 0.0 | 1.6 | 3 |
| Additional Work | 2 | 0.8 | 0.8 | 1.5 | 2 |
| Cleanup | 1 | 0.0 | 0.0 | 0.0 | 0 |
Longest average duration per task (min. 5 occurrences)
| Task | Count | Avg Hrs | Median Hrs | Max Hrs |
| Brick | 25 | 86.6 | 31.9 | 592.0 |
| Vinyl | 73 | 55.2 | 48.0 | 205.4 |
| Siding | 311 | 32.0 | 21.8 | 252.8 |
| Soffit/Fascia | 313 | 23.6 | 12.3 | 205.4 |
| Brick Wash | 32 | 21.0 | 1.6 | 215.6 |
| Rock | 101 | 20.1 | 15.5 | 87.8 |
| Paper/Wire | 256 | 12.8 | 8.0 | 180.3 |
| Custom Work | 18 | 10.2 | 0.4 | 81.2 |
| Stucco Color | 187 | 10.0 | 7.9 | 50.0 |
| Paint | 245 | 9.0 | 6.2 | 200.0 |
3. Where's the culprit? Top jobs by cumulative task hours
These jobs consumed the most total crew hours across all tasks — worth checking for repeat delay patterns, scope creep, or rework.
| Job | Total Task Hours |
| 222-Whisper Ridge-Premier Constructors | 1,972 |
| Units 7-12-Smithfield Crest-Sierra Homes | 1,714 |
| 11-Fairway Estates-Visionary | 888 |
| Bldg S-Village at Fox Meadows Townhomes-Visionary | 863 |
| 12-Fairway Estates-Visionary | 709 |
| Bldg T-Village at Fox Meadows Townhomes-Visionary | 670 |
| 223-Whisper Ridge-Premier Constructors | 666 |
| 1-6 6 Plex-Smithfield Crest-Sierra Homes | 627 |
| 1-Fairway Estates-Visionary | 519 |
| 1-Amberly Place-Ivory | 476 |
Bottom line: Siding and Soffit/Fascia consume the most total crew hours of any task
type in Ogden — together over 17,000 hours across the sampled period — making them the
biggest lever if you want to move the on-time number. Siding also shows a wide gap between
its median (21.8 hrs) and average (32.0 hrs), meaning a subset of siding jobs are running
far longer than typical and pulling the average up — those outliers are worth investigating
individually rather than treating siding as uniformly slow.