Ogden Division — On-Time Performance & Task Duration Report

Job Scheduling & Milestone Info, Task Pay Info, and Tasks General — Ogden Division only
"On-time" = Major Tasks Completion Date vs. Target End Date (Cascade's internal schedule commitment, not the builder-facing Client End Date). A job scored "Late" if major work finished after the target date, even by one day. 270 of 319 Ogden job records had both dates populated and could be scored.

1. Is the KPI right? On-time vs. late

129
On time (48%)
141
Late (52%)
+0.6
Avg days vs. target
+1
Median days vs. target
Verified: 141 of 270 scored jobs (52%) finished major work after the target date — more jobs late than on time. The KPI reflects real underlying performance, not a reporting artifact.

Worst-delayed jobs (top 15)

JobBuilderTarget End DateMajor Tasks CompletedDays LateStatus
222-Whisper Ridge-Premier ConstructorsPremier Constructors2026-02-122026-04-22+69Late
Bldg 51-Western Acres Townhomes-DR HortonDR Horton2025-12-302026-02-26+58Late
32 (Stoddard)-East Shore-Sierra HomesSierra Homes2026-02-102026-03-24+42Late
223-Whisper Ridge-Premier ConstructorsPremier Constructors2026-02-272026-04-10+42Late
12-Fairway Estates-VisionaryVisionary2026-04-212026-05-25+34Late
Units 7-12-Smithfield Crest-Sierra HomesSierra Homes2026-05-012026-06-01+31Late
223-Riverside Estates-Fieldstone HomesFieldstone Homes2026-04-082026-05-07+29Late
Irva Tooele Retail Drive Through-Commercial-Affinity ConstructionAffinity Construction2026-05-152026-06-10+26Late
2-Sunset Ridges-Sierra HomesSierra Homes2026-05-222026-06-17+26Late
TH 1-Flint Acres-Henry Walker HomesHenry Walker Homes2026-01-092026-02-04+26Late
14-Fairway Estates-VisionaryVisionary2026-04-302026-05-25+25Late
Bldg 19-Railrunner-VGIVGI2026-01-142026-02-07+24Late
302-Legacy Park-IvoryIvory2026-05-132026-06-05+23Late
Bldg 9-Midtown Village-DR HortonDR Horton2026-06-022026-06-24+22Late
Units 150-153-Trailside Lexington Townhomes-Destination HomesDestination Homes2026-04-072026-04-29+22Late

2. Which tasks take the longest?

Based on 3574 completed Ogden task records with a logged duration (Task Pay Info, "Task Duration Business Hours" — actual clock time from task start to completion). Sorted by total hours consumed across all jobs — this shows where crew time is going in aggregate.
TaskCountAvg HrsMedian HrsMax HrsTotal Hrs
Siding31132.021.8252.89,942
Soffit/Fascia31323.612.3205.47,396
Vinyl7355.248.0205.44,029
Paper/Wire25612.88.0180.33,288
Paint2459.06.2200.02,213
Brick2586.631.9592.02,165
Rock10120.115.587.82,035
Stucco Color18710.07.950.01,862
Set Scaff2178.15.3106.21,768
Housewrap2057.85.3171.51,591
Gutters2804.71.1198.41,312
Stucco Brown1517.16.440.01,069
Misc. Work1765.80.0214.91,021
Remove Scaff2024.01.871.3812
Scratch Coat1276.32.5108.0794
Brick Wash3221.01.6215.6673
VPO Work1932.70.055.7519
Set Tarps715.82.693.8411
Remove Tarps734.30.0136.0315
Brown & Mesh406.37.224.0253
Custom Work1810.20.481.2184
Return/Fix752.00.060.5151
Hardie Soffit/Fascia158.51.086.3127
Foundation Plaster205.32.035.4106
Fix Scaff471.50.027.072
Woodtone Paint58.08.016.140
Window Pre Wrap142.70.014.738
Watering162.40.017.038
Warranty Work132.60.321.534
Mesh Coat132.032.032.032
Paint Hardie Soffit/Fascia161.90.58.031
Shutters201.50.217.929
Special Corbels45.74.414.023
Painted Brick53.43.76.617
Set Brick Scaff101.00.08.910
Scaff Pickup140.20.01.63
Additional Work20.80.81.52
Cleanup10.00.00.00

Longest average duration per task (min. 5 occurrences)

TaskCountAvg HrsMedian HrsMax Hrs
Brick2586.631.9592.0
Vinyl7355.248.0205.4
Siding31132.021.8252.8
Soffit/Fascia31323.612.3205.4
Brick Wash3221.01.6215.6
Rock10120.115.587.8
Paper/Wire25612.88.0180.3
Custom Work1810.20.481.2
Stucco Color18710.07.950.0
Paint2459.06.2200.0

3. Where's the culprit? Top jobs by cumulative task hours

These jobs consumed the most total crew hours across all tasks — worth checking for repeat delay patterns, scope creep, or rework.
JobTotal Task Hours
222-Whisper Ridge-Premier Constructors1,972
Units 7-12-Smithfield Crest-Sierra Homes1,714
11-Fairway Estates-Visionary888
Bldg S-Village at Fox Meadows Townhomes-Visionary863
12-Fairway Estates-Visionary709
Bldg T-Village at Fox Meadows Townhomes-Visionary670
223-Whisper Ridge-Premier Constructors666
1-6 6 Plex-Smithfield Crest-Sierra Homes627
1-Fairway Estates-Visionary519
1-Amberly Place-Ivory476
Bottom line: Siding and Soffit/Fascia consume the most total crew hours of any task type in Ogden — together over 17,000 hours across the sampled period — making them the biggest lever if you want to move the on-time number. Siding also shows a wide gap between its median (21.8 hrs) and average (32.0 hrs), meaning a subset of siding jobs are running far longer than typical and pulling the average up — those outliers are worth investigating individually rather than treating siding as uniformly slow.