Every division. Tasks with an assignment date set but no team assigned and not yet completed.
Generated Sep 3, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 13,941 task records pulled, 231 matched the filter · assignment dates Feb 25, 2026 to Nov 3, 2026
past assignment date due today or upcoming
| Division | Overdue 30+ days | Overdue 8-30 days | Overdue 1-7 days | Due today | Next 7 days | Beyond 7 days | Total |
|---|---|---|---|---|---|---|---|
| Orem | 3 | 4 | 28 | 19 | 18 | 17 | 89 |
| Ogden | · | 12 | 49 | 18 | 3 | · | 82 |
| Salt Lake | · | · | 10 | 2 | 6 | 13 | 31 |
| St. George | 1 | 1 | 9 | · | 6 | · | 17 |
| Commercial | 2 | 3 | 6 | · | · | · | 11 |
| Corporate | · | 1 | · | · | · | · | 1 |
| All divisions | 6 | 21 | 102 | 39 | 33 | 30 | 231 |
Which trades the backlog is sitting in. Scroll sideways for all 28 task types.
| Division | Set Scaff | Stucco Color | Rock | Siding | Scratch Coat | Paper/Wire | Gutters | Housewrap | Insl Attic | Stucco Brown | Remove Scaff | Soffit/Fascia | Paint | Watering | Set Brick Scaff | Brown & Mesh | Misc. Work | Window Pre Wrap | Brick | Special Corbels | Penetration Sealing | Insl Walls | Insl Foam 1 | Shutters | VPO Work | Faux Concrete | Foundation Plaster | QC Walk | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Orem | 29 | 13 | 9 | 3 | 5 | 4 | 1 | 2 | 1 | 3 | 3 | 3 | 4 | 4 | · | · | 1 | · | · | 1 | · | · | · | · | 1 | 1 | 1 | · | 89 |
| Ogden | · | 16 | 7 | 14 | 9 | 4 | 11 | 3 | · | 3 | 3 | 3 | · | · | 4 | 3 | · | · | 2 | · | · | · | · | · | · | · | · | · | 82 |
| Salt Lake | 9 | 4 | 1 | · | · | 1 | · | 2 | 8 | 1 | 1 | 1 | · | · | · | · | · | · | · | · | · | 1 | 1 | 1 | · | · | · | · | 31 |
| St. George | 1 | 6 | 1 | · | 1 | · | · | 2 | · | 1 | · | · | 1 | 1 | · | · | · | 2 | · | · | · | · | · | · | · | · | · | 1 | 17 |
| Commercial | 2 | 1 | 1 | · | 1 | 3 | · | · | · | · | 1 | · | 1 | · | · | · | · | · | · | · | 1 | · | · | · | · | · | · | · | 11 |
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | 1 | · | · | · | · | · | · | · | · | · | · | · | 1 |
| All divisions | 41 | 40 | 19 | 17 | 16 | 12 | 12 | 9 | 9 | 8 | 8 | 7 | 6 | 5 | 4 | 3 | 2 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 231 |
Click a division to see the underlying tasks, oldest assignment date first.
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 813-Heron Hills-Richmond | VPO Work | Jul 10, 2026 | 55d overdue | Unassigned | $60 | Necesitan cambiar dos hojas de sofito, el que instaló las cámaras dejó el agujero muy grande y lo quieren exacto para que no se vea el agujero. El supervisor Mike Bash lo está auto | |
| 708-Highridge-Edge | Watering | Jul 29, 2026 | 36d overdue | Unassigned | $94 | ✅ 2026-07-23: 4 Days - Stucco delay - framers are gonna have to fix a porch column for being twisted - Jonathan 2026-07-29 ✅ 2026-07-14: Scaff Delay - Scaff delay - it hasn’t pass | |
| Bldg 70-Ridgehorne-Edge | Watering | Aug 1, 2026 | 33d overdue | Unassigned | $50 | ||
| 37-Lakeview Fields-Keystone Construction | Watering | Aug 5, 2026 | 29d overdue | Unassigned | $92 | ||
| 117-Vista at Harmony Place-Woodside | Watering | Aug 5, 2026 | 29d overdue | Unassigned | $59 | ||
| 2014-Wildflower-Toll Brothers | Faux Concrete | Aug 10, 2026 | 24d overdue | Unassigned | $1,182 | ⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-04 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l | |
| 47-Lakeview Fields-Keystone Construction | Misc. Work | Aug 25, 2026 | 9d overdue | Unassigned | $60 | Gutter was damaged during scaffolding removal and needs to be replaced. | |
| 2014-Wildflower-Toll Brothers | Foundation Plaster | Aug 27, 2026 | 7d overdue | Unassigned | $450 | ⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-04 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l | |
| 434-Viridian-DR Horton | Rock | Aug 28, 2026 | 6d overdue | Unassigned | $388 | ✅ | |
| 346-Mountain Vista at Sunset Flats-Pulte Homes | Paper/Wire | Aug 29, 2026 | 5d overdue | Unassigned | 2026-08-21 | $1,410 | ⭕ 2026-08-31: We need to wait to lath we need to pass Housewrap inspections before we can lath thanks ?? - Victor Est End: 2026-09-08 |
| 232-Viridian Plus-DR Horton | Set Scaff | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-03 | $779 | |
| Units 136-140-Regency at Harmony Place-Woodside | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | $2,545 | ||
| 16119-Harmony-Meritage Homes | Housewrap | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-02 | $489 | |
| Bldg 21-Silver Oaks-Lennar | Housewrap | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-02 | $1,733 | |
| 105 (FP)-Auburn Springs-Edge | Rock | Sep 1, 2026 | 2d overdue | Unassigned | $130 | ||
| 143-Montreux-DR Horton | Siding | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-27 | $4,764 | ⭕ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex Est End: 2026-09-03 ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - |
| 130-Montreux-DR Horton | Siding | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-27 | $4,655 | ⭕ 2026-08-28: Material Delay - Missing all the siding - Alex Est End: 2026-09-02 |
| 143-Montreux-DR Horton | Soffit/Fascia | Sep 1, 2026 | 2d overdue | Unassigned | $748 | ⭕ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex Est End: 2026-09-03 ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - | |
| 130-Montreux-DR Horton | Soffit/Fascia | Sep 1, 2026 | 2d overdue | Unassigned | $608 | ⭕ 2026-08-28: Material Delay - Missing all the siding - Alex Est End: 2026-09-02 | |
| 102-Canton Ridge-Richmond | Special Corbels | Sep 1, 2026 | 2d overdue | Unassigned | $50 | ||
| 1029-Harmony Ridge-Edge | Paint | Sep 2, 2026 | 1d overdue | Unassigned | $404 | ||
| 826-Broadview Shores-Ivory | Paint | Sep 2, 2026 | 1d overdue | Unassigned | $320 | ✅ 2026-08-24: Material Delay - Missing all the lath and stucco orders - Alex 2026-08-28 | |
| Roundabout Wall Phase 4-Viridian Townhomes-DR Horton | Paper/Wire | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-04 | $260 | |
| 26-Tanner Flats-Ivory | Paper/Wire | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-21 | $1,006 | |
| 814-Broadview Shores-Ivory | Paper/Wire | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-18 | $162 | |
| 120-Vista at Harmony Place-Woodside | Remove Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $258 | ||
| 111-Auburn Springs-Edge | Remove Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $432 | ||
| 143-Montreux-DR Horton | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $706 | ⭕ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex Est End: 2026-09-03 ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - | |
| 131-Montreux-DR Horton | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $1,431 | ||
| 826-Broadview Shores-Ivory | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $2,299 | ✅ 2026-08-24: Material Delay - Missing all the lath and stucco orders - Alex 2026-08-28 | |
| 143-Montreux-DR Horton | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $83 | ⭕ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex Est End: 2026-09-03 ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - | |
| 131-Montreux-DR Horton | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $168 | ||
| 247-Viridian Plus-DR Horton | Set Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $817 | ||
| 313-Viridian-DR Horton | Set Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $639 | ||
| 131-Montreux-DR Horton | Soffit/Fascia | Sep 2, 2026 | 1d overdue | Unassigned | $704 | ||
| Park Restroom 1-Viridian Townhomes-DR Horton | Gutters | Sep 3, 2026 | today | Unassigned | $108 | ||
| 49-Tanner Flats-Ivory | Paint | Sep 3, 2026 | today | Unassigned | $335 | ||
| 913-Harmony Ridge-Edge | Paint | Sep 3, 2026 | today | Unassigned | $101 | ✅ 2026-08-21: Missing window also columns - Jorge 2026-08-25 | |
| 243-Canton Ridge-Richmond | Remove Scaff | Sep 3, 2026 | today | Unassigned | $562 | ||
| 103-Auburn Springs-Edge | Rock | Sep 3, 2026 | today | Unassigned | $970 | ✅ 2026-08-24: 2 Days - Waiting for Columns to be done.it’s been sense last Tuesday - Harrison 2026-08-26 | |
| 243-Viridian Plus-DR Horton | Rock | Sep 3, 2026 | today | Unassigned | $1,380 | ||
| 531-River Point-Edge | Rock | Sep 3, 2026 | today | Unassigned | $187 | ||
| 723-Highridge-Edge | Rock | Sep 3, 2026 | today | Unassigned | $527 | ||
| 243-Viridian Plus-DR Horton | Scratch Coat | Sep 3, 2026 | today | Unassigned | $162 | ||
| 531-River Point-Edge | Scratch Coat | Sep 3, 2026 | today | Unassigned | $50 | ||
| 723-Highridge-Edge | Scratch Coat | Sep 3, 2026 | today | Unassigned | $76 | ||
| 2168-Wildflower-Edge | Set Scaff | Sep 3, 2026 | today | Unassigned | $559 | ||
| Bldg 49-Viridian Townhomes-DR Horton | Set Scaff | Sep 3, 2026 | today | Unassigned | $1,312 | ||
| 107-Auburn Springs-Edge | Set Scaff | Sep 3, 2026 | today | Unassigned | 2026-09-04 | $840 | |
| Units 279-284-Highline-Century | Siding | Sep 3, 2026 | today | Unassigned | 2026-09-02 | $8,640 | |
| 243-Viridian Plus-DR Horton | Stucco Brown | Sep 3, 2026 | today | Unassigned | 2026-08-24 | $1,413 | |
| 723-Highridge-Edge | Stucco Brown | Sep 3, 2026 | today | Unassigned | 2026-08-24 | $1,274 | |
| Units 279-284-Highline-Century | Stucco Brown | Sep 3, 2026 | today | Unassigned | 2026-08-24 | $2,453 | |
| 423-Viridian-DR Horton | Stucco Color | Sep 3, 2026 | today | Unassigned | $981 | ||
| 233-Viridian Plus-DR Horton | Set Scaff | Sep 4, 2026 | in 1d | Unassigned | $978 | ||
| 421-Viridian-DR Horton | Set Scaff | Sep 4, 2026 | in 1d | Unassigned | $644 | ||
| 517-River Point-Edge | Set Scaff | Sep 4, 2026 | in 1d | Unassigned | $625 | ||
| 1028-Harmony Ridge-Edge | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | $1,021 | ||
| 1029-Harmony Ridge-Edge | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | $793 | ||
| 49-Tanner Flats-Ivory | Stucco Color | Sep 6, 2026 | in 3d | Unassigned | $949 | ||
| 913-Harmony Ridge-Edge | Stucco Color | Sep 6, 2026 | in 3d | Unassigned | $1,336 | ✅ 2026-08-21: Missing window also columns - Jorge 2026-08-25 | |
| 36-Lakeview Fields-Keystone Construction | Stucco Color | Sep 6, 2026 | in 3d | Unassigned | $1,256 | ||
| Wellspring Park Restroom-Viridian Townhomes-DR Horton | Set Scaff | Sep 7, 2026 | in 4d | Unassigned | $15 | ||
| 110-Vista at Harmony Place-Woodside | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $787 | ||
| 341-Viridian-DR Horton | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $957 | ||
| 45-Tanner Flats-Ivory | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $949 | ||
| 338-Mountain Vista at Sunset Flats-Pulte Homes | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $1,527 | ✅ 2026-08-18: 4 Days - We need to wait to lath we need to pass the Housewrap inspection before we can continue with lath please don’t send any ath crews thanks - Victor 2026-08-24 | |
| 826-Broadview Shores-Ivory | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $1,001 | ✅ 2026-08-24: Material Delay - Missing all the lath and stucco orders - Alex 2026-08-28 | |
| 2024-Wildflower-Toll Brothers | Stucco Color | Sep 8, 2026 | in 5d | Unassigned | $130 | ✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-08-31 | |
| 234-Viridian Plus-DR Horton | Set Scaff | Sep 10, 2026 | in 7d | Unassigned | $763 | ||
| 2181-Wildflower-Edge | Set Scaff | Sep 10, 2026 | in 7d | Unassigned | $652 | ||
| 340-Viridian-DR Horton | Set Scaff | Sep 10, 2026 | in 7d | Unassigned | $606 | ||
| 314-Viridian-DR Horton | Set Scaff | Sep 11, 2026 | in 8d | Unassigned | $627 | ||
| 2227-Wildflower-Edge | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | $744 | ||
| 420-Viridian-DR Horton | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | $681 | ||
| 711-Ridgehorne-Edge | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | $740 | ||
| 1021-Harmony Ridge-Edge | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | 2026-09-14 | $777 | |
| 718-Highridge-Edge | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | $831 | ||
| 108-Auburn Springs-Edge | Set Scaff | Sep 14, 2026 | in 11d | Unassigned | $930 | ||
| 523-River Point-Edge | Set Scaff | Sep 15, 2026 | in 12d | Unassigned | $742 | ||
| Bldg 56-Harmony Ridge-Edge | Set Scaff | Sep 15, 2026 | in 12d | Unassigned | $1,891 | ||
| 339-Viridian-DR Horton | Set Scaff | Sep 16, 2026 | in 13d | Unassigned | $574 | ||
| 133-Auburn Springs-Edge | Set Scaff | Sep 17, 2026 | in 14d | Unassigned | $985 | ||
| 147-Auburn Springs-Edge | Set Scaff | Sep 17, 2026 | in 14d | Unassigned | $723 | ||
| 711-Highridge-Edge | Set Scaff | Sep 17, 2026 | in 14d | Unassigned | $557 | ||
| 353-Viridian Emerald-DR Horton | Set Scaff | Sep 22, 2026 | in 19d | Unassigned | $835 | ||
| 1031-Harmony Ridge-Edge | Set Scaff | Sep 22, 2026 | in 19d | Unassigned | $709 | ||
| Bldg 59-Harmony Ridge-Edge | Set Scaff | Sep 29, 2026 | in 26d | Unassigned | $1,480 | ||
| Bldg 39-Highridge-Edge | Insl Attic | Oct 9, 2026 | in 36d | Unassigned | $80 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 17-Sunset Ridges-Sierra Homes | Siding | Aug 6, 2026 | 28d overdue | Unassigned | 2026-07-30 | $261 | ✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24 |
| 108-Red Hill-Ivory | Set Brick Scaff | Aug 12, 2026 | 22d overdue | Unassigned | $40 | ||
| 206-Fremont Meadows-Sterling Homes | Scratch Coat | Aug 13, 2026 | 21d overdue | Unassigned | $50 | ||
| 7-Heritage Parkway-Sierra Homes | Siding | Aug 18, 2026 | 16d overdue | Unassigned | $158 | ✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-04 | |
| 71-Brookfield-Lennar | Gutters | Aug 24, 2026 | 10d overdue | Unassigned | $167 | ||
| 63-Brookfield-Lennar | Gutters | Aug 24, 2026 | 10d overdue | Unassigned | $236 | ||
| 106-Red Hill-Ivory | Set Brick Scaff | Aug 24, 2026 | 10d overdue | Unassigned | $36 | ||
| Bldg 25-Railrunner-DAI Construction | Gutters | Aug 25, 2026 | 9d overdue | Unassigned | $806 | ||
| 108-Red Hill-Ivory | Scratch Coat | Aug 25, 2026 | 9d overdue | Unassigned | $50 | ||
| Bldg K-Sugar Creek Townhomes-Visionary | Remove Scaff | Aug 26, 2026 | 8d overdue | Unassigned | $408 | ||
| Bldg 6-Midtown Village-DR Horton | Set Brick Scaff | Aug 26, 2026 | 8d overdue | Unassigned | $0 | ||
| 1523-Cranefield Estates-Ivory | Set Brick Scaff | Aug 26, 2026 | 8d overdue | Unassigned | $134 | ||
| 176-Mountain Gate-Sierra Homes | Siding | Aug 27, 2026 | 7d overdue | Unassigned | 2026-08-27 | $220 | |
| 116-Meadows at Hyde Park-Visionary | Siding | Aug 27, 2026 | 7d overdue | Unassigned | 2026-08-21 | $1,704 | |
| 106-Red Hill-Ivory | Brick | Aug 28, 2026 | 6d overdue | Unassigned | $1,042 | ||
| 62-Brookfield-Lennar | Housewrap | Aug 28, 2026 | 6d overdue | Unassigned | 2026-08-29 | $632 | |
| Bldg 2-Railrunner-DAI Construction | Siding | Aug 28, 2026 | 6d overdue | Unassigned | 2026-08-14 | $782 | ✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0 |
| 106-Three Farms Jenkins Fields-Ivory | Gutters | Aug 29, 2026 | 5d overdue | Unassigned | $146 | ||
| Bldg K-Sugar Creek Townhomes-Visionary | Gutters | Aug 29, 2026 | 5d overdue | Unassigned | $874 | ||
| 114-Meadows at Hyde Park-Visionary | Stucco Color | Aug 29, 2026 | 5d overdue | Unassigned | 2026-08-26 | $838 | |
| 701-Ridgeline Park-Visionary | Stucco Color | Aug 30, 2026 | 4d overdue | Unassigned | 2026-09-02 | $806 | |
| Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction Group | Rock | Aug 31, 2026 | 3d overdue | Unassigned | $635 | ⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15 | |
| 102-Meadows at Hyde Park-Visionary | Siding | Aug 31, 2026 | 3d overdue | Unassigned | $1,261 | ||
| 314-Stagecoach Estates-McArthur | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-07 | $809 | |
| 323-Stagecoach Estates-McArthur | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-04 | $791 | |
| 55-Cardamine-Sierra Homes | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-04 | $331 | ✅ 2026-08-12: Material Delay - We don’t have vinyl materials - Jose 2026-08-31 |
| 501-Legacy Park-Ivory | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-07 | $1,004 | |
| 1708-Cranefield Estates-Ivory | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-02 | $928 | |
| 227-Bristol Farms-Regal Homes | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-03 | $1,246 | |
| 229-Bristol Farms-Regal Homes | Stucco Color | Aug 31, 2026 | 3d overdue | Unassigned | 2026-09-07 | $1,210 | |
| 113-Meadows at Hyde Park-Visionary | Gutters | Sep 1, 2026 | 2d overdue | Unassigned | $352 | ✅ 2026-07-23: 11 Days - They missing the front porch cap - Jose 2026-08-07 ✅ 2026-07-22: Material Delay - We still don’t have material - Jose 2026-08-07 | |
| Bldg AC-North Point Townhomes-Visionary | Paper/Wire | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-19 | $107 | |
| 1523-Cranefield Estates-Ivory | Paper/Wire | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-28 | $667 | |
| 125-Palomino-DR Horton | Scratch Coat | Sep 1, 2026 | 2d overdue | Unassigned | $95 | ||
| 338-Sugar Creek-Visionary | Siding | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-28 | $489 | |
| Bldg AC-North Point Townhomes-Visionary | Siding | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-19 | $6,469 | |
| 1709-Cranefield Estates-Ivory | Stucco Brown | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-26 | $914 | |
| 313-Stagecoach Estates-McArthur | Stucco Color | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-02 | $951 | |
| 112-Three Farms Jenkins Fields-Ivory | Stucco Color | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-02 | $873 | |
| 603-Vineyard-Visionary | Brown & Mesh | Sep 2, 2026 | 1d overdue | Unassigned | $1,618 | ||
| 520-Vineyard-Visionary | Brown & Mesh | Sep 2, 2026 | 1d overdue | Unassigned | $736 | ✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24 | |
| 108-Meadows at Hyde Park-Visionary | Gutters | Sep 2, 2026 | 1d overdue | Unassigned | $461 | ||
| 108-Stagecoach Estates-McArthur | Housewrap | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-26 | $617 | |
| 5-Brynlee Acres-Hamlet | Housewrap | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-27 | $173 | ✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02 |
| 96-Seasons at Taylor Landing-Richmond | Remove Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $0 | ||
| 4-Heritage Parkway-Sierra Homes | Remove Scaff | Sep 2, 2026 | 1d overdue | Unassigned | $13 | ✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04 | |
| 603-Vineyard-Visionary | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $695 | ||
| 2-Brynlee Acres-Hamlet | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $1,609 | ||
| SF 6-Flint Acres-Henry Walker Homes | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $1,290 | ||
| 520-Vineyard-Visionary | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $402 | ✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24 | |
| 603-Vineyard-Visionary | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $74 | ||
| 2-Brynlee Acres-Hamlet | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $166 | ||
| SF 6-Flint Acres-Henry Walker Homes | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $187 | ||
| 520-Vineyard-Visionary | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $50 | ✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24 | |
| 723-Ridgeline Park-Visionary | Siding | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-19 | $1,603 | ⭕ 2026-09-02: Can’t start siding because front porch cap is not poured - Ronnie Est End: 2026-09-09 |
| 821-Ridgeline Park-Visionary | Siding | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-13 | $941 | |
| 521-Vineyard-Visionary | Siding | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-27 | $714 | |
| 314-Stagecoach Estates-McArthur | Soffit/Fascia | Sep 2, 2026 | 1d overdue | Unassigned | $635 | ||
| 3-Brynlee Acres-Hamlet | Stucco Color | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-08 | $901 | |
| Bldg 12-Midtown Village-DR Horton | Stucco Color | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-04 | $1,751 | |
| 17-Sunset Ridges-Sierra Homes | Stucco Color | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-04 | $301 | ✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24 |
| 311-Legacy Park-Ivory | Brick | Sep 3, 2026 | today | Unassigned | 2026-08-21 | $2,826 | |
| 609-Village at Fox Meadows-Visionary | Brown & Mesh | Sep 3, 2026 | today | Unassigned | $1,117 | ||
| 229-Westwood Estates-Meritage Homes | Gutters | Sep 3, 2026 | today | Unassigned | $280 | ||
| 111-Stagecoach Estates-McArthur | Gutters | Sep 3, 2026 | today | Unassigned | $293 | ||
| Bldg 18-Dixon Creek-DR Horton | Gutters | Sep 3, 2026 | today | Unassigned | $602 | ||
| 330-Riverside Estates-Fieldstone Homes | Gutters | Sep 3, 2026 | today | Unassigned | $321 | ||
| 102-Meadows at Hyde Park-Visionary | Paper/Wire | Sep 3, 2026 | today | Unassigned | 2026-09-01 | $1,075 | |
| 5-Brynlee Acres-Hamlet | Paper/Wire | Sep 3, 2026 | today | Unassigned | 2026-08-27 | $1,064 | ✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02 |
| 4-Brynlee Acres-Hamlet | Rock | Sep 3, 2026 | today | Unassigned | $2,207 | ||
| 609-Village at Fox Meadows-Visionary | Rock | Sep 3, 2026 | today | Unassigned | $434 | ||
| 4-Brynlee Acres-Hamlet | Scratch Coat | Sep 3, 2026 | today | Unassigned | $228 | ||
| 609-Village at Fox Meadows-Visionary | Scratch Coat | Sep 3, 2026 | today | Unassigned | $50 | ||
| 254-Westwood Estates-Meritage Homes | Siding | Sep 3, 2026 | today | Unassigned | 2026-08-28 | $4,627 | |
| 4-Brynlee Acres-Hamlet | Siding | Sep 3, 2026 | today | Unassigned | 2026-08-19 | $888 | |
| 311-Legacy Park-Ivory | Siding | Sep 3, 2026 | today | Unassigned | 2026-08-17 | $766 | |
| 254-Westwood Estates-Meritage Homes | Soffit/Fascia | Sep 3, 2026 | today | Unassigned | $527 | ||
| 4-Brynlee Acres-Hamlet | Stucco Brown | Sep 3, 2026 | today | Unassigned | 2026-08-19 | $933 | |
| 311-Legacy Park-Ivory | Stucco Brown | Sep 3, 2026 | today | Unassigned | 2026-08-13 | $989 | |
| 12-Mountainside Estates-DR Horton | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | 2026-09-07 | $1,034 | |
| 11-Mountainside Estates-DR Horton | Stucco Color | Sep 6, 2026 | in 3d | Unassigned | $1,115 | ||
| 253-Westwood Estates-Meritage Homes | Soffit/Fascia | Sep 7, 2026 | in 4d | Unassigned | $545 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Bldg 20-Solari-Edge | Rock | Aug 29, 2026 | 5d overdue | Unassigned | $1,183 | ✅ 2026-08-19: 4 Days - Delayed for drywall windows and gas line - Dustin 2026-08-25 | |
| 1005-Northstar Ranch-Destination Homes | Soffit/Fascia | Aug 29, 2026 | 5d overdue | Unassigned | $587 | ✅ 2026-08-17: 4 Days - Need to wait for gas to set up scaff - Alexander 2026-08-21 ✅ 2026-08-14: 2 Days - No available scaffolding waiting for scaffolding - Alexander 2026-08-18 | |
| Units 440-445-Legacy at Sky Ranch-Woodside | Stucco Color | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-04 | $1,754 | |
| 1004-Northstar Ranch-Destination Homes | Housewrap | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-04 | $217 | |
| 254-Boulder at Sky Ranch-Woodside | Housewrap | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-03 | $222 | |
| 254-Boulder at Sky Ranch-Woodside | Paper/Wire | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-03 | $1,013 | |
| 441-Daybreak Cottage Courts-Destination Homes | Set Scaff | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-02 | $526 | |
| 2909-Mountain Ridge-Edge | Set Scaff | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-04 | $494 | |
| 328-Pagoda Grove-McArthur | Stucco Brown | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-26 | $1,071 | |
| 11-Riley Park-DR Horton | Stucco Color | Sep 2, 2026 | 1d overdue | Unassigned | $1,100 | ✅ 2026-08-19: 2 Days - Waiting on initial order - Alexander 2026-08-21 | |
| 422-Daybreak Cottage Courts-Destination Homes | Remove Scaff | Sep 3, 2026 | today | Unassigned | $392 | ||
| 422-Daybreak Cottage Courts-Destination Homes | Shutters | Sep 3, 2026 | today | Unassigned | $350 | ||
| 442-Daybreak Cottage Courts-Destination Homes | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | 2026-09-02 | $674 | |
| Bldg 20-Solari-Edge | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | $2,876 | ✅ 2026-08-19: 4 Days - Delayed for drywall windows and gas line - Dustin 2026-08-25 | |
| 2912-Mountain Ridge-Edge | Set Scaff | Sep 8, 2026 | in 5d | Unassigned | 2026-09-04 | $759 | |
| Bldg 21-Solari-Edge | Set Scaff | Sep 9, 2026 | in 6d | Unassigned | $1,778 | ||
| 120-Capitol Reef-Edge | Set Scaff | Sep 9, 2026 | in 6d | Unassigned | 2026-09-02 | $671 | |
| Bldg 22-Solari-Edge | Set Scaff | Sep 10, 2026 | in 7d | Unassigned | $1,543 | ||
| Bldg 211-Mountain Ridge-Edge | Insl Attic | Sep 14, 2026 | in 11d | Unassigned | $144 | ||
| Bldg 19-Solari-Edge | Insl Foam 1 | Sep 15, 2026 | in 12d | Unassigned | $116 | ||
| Bldg 19-Solari-Edge | Insl Walls | Sep 15, 2026 | in 12d | Unassigned | $1,517 | ||
| 2929-Mountain Ridge-Edge | Set Scaff | Sep 15, 2026 | in 12d | Unassigned | $577 | ||
| 2916-Mountain Ridge-Edge | Set Scaff | Sep 17, 2026 | in 14d | Unassigned | $752 | ||
| Bldg 19-Solari-Edge | Set Scaff | Sep 18, 2026 | in 15d | Unassigned | $1,570 | ||
| Bldg 22-Mt. Rainier-Edge | Insl Attic | Sep 23, 2026 | in 20d | Unassigned | $159 | ✅ 2026-08-12: 3 Days - Don’t start stucco brown until drywall windows are installed correctly - Arturo 2026-08-17 | |
| Bldg 9-Taylor Villas-Edge | Insl Attic | Sep 29, 2026 | in 26d | Unassigned | $179 | ✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18 | |
| Bldg 1-Solari-Edge | Insl Attic | Oct 1, 2026 | in 28d | Unassigned | $143 | ✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19 | |
| Bldg 208-Mountain Ridge-Edge | Insl Attic | Oct 14, 2026 | in 41d | Unassigned | $144 | ||
| Bldg 202-Mountain Ridge-Edge | Insl Attic | Oct 20, 2026 | in 47d | Unassigned | $143 | ||
| Bldg 22-Solari-Edge | Insl Attic | Oct 26, 2026 | in 53d | Unassigned | $160 | ||
| Bldg 19-Solari-Edge | Insl Attic | Nov 3, 2026 | in 61d | Unassigned | $192 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 10-Black Desert North Village-VGI | QC Walk | Feb 25, 2026 | 190d overdue | Unassigned | $0 | ✅ 2025-12-08: 11 Days - Tendremos que posponer el papel y el alambre, porque el Super me habló que si lo podemos empezar hasta el siguiente lunes - Francisco 2025-12-23 | |
| Bldg Y-Sage Haven Townhomes-Visionary | Paint | Aug 21, 2026 | 13d overdue | Unassigned | $1,551 | ||
| 75-Divario-Visionary | Window Pre Wrap | Aug 31, 2026 | 3d overdue | Unassigned | $100 | ||
| 52-Zion Shores-Split Rock | Housewrap | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-03 | $1,438 | |
| 4271-Long Valley-DR Horton | Housewrap | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-01 | $50 | |
| Bldg 133-Long Valley Townhomes-DR Horton | Watering | Sep 1, 2026 | 2d overdue | Unassigned | $189 | ||
| 24-Legacy at Sand Hollow-Visionary | Window Pre Wrap | Sep 1, 2026 | 2d overdue | Unassigned | $100 | ||
| 4156-Long Valley Rambler-DR Horton | Rock | Sep 2, 2026 | 1d overdue | Unassigned | $406 | ||
| 4156-Long Valley Rambler-DR Horton | Scratch Coat | Sep 2, 2026 | 1d overdue | Unassigned | $50 | ||
| Bldg 124-Long Valley Townhomes-DR Horton | Set Scaff | Sep 2, 2026 | 1d overdue | Unassigned | 2026-09-02 | $1,478 | |
| 4156-Long Valley Rambler-DR Horton | Stucco Brown | Sep 2, 2026 | 1d overdue | Unassigned | 2026-08-25 | $1,053 | |
| 4164-Long Valley Rambler-DR Horton | Stucco Color | Sep 5, 2026 | in 2d | Unassigned | 2026-09-04 | $865 | |
| 4272-Long Valley-DR Horton | Stucco Color | Sep 6, 2026 | in 3d | Unassigned | $1,465 | ||
| 4290-Long Valley-DR Horton | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $2,064 | ||
| 35-Legacy at Sand Hollow-Visionary | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $2,523 | ||
| 4305-Long Valley-DR Horton | Stucco Color | Sep 7, 2026 | in 4d | Unassigned | $1,592 | ✅ 2026-08-21: 6 Days - Cannot finish lath. Missing window - Daniel 2026-08-31 | |
| 16-Desert Cove-Richmond | Stucco Color | Sep 8, 2026 | in 5d | Unassigned | $1,687 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Bldg C-Residence at Millcreek-Rimrock | Rock | Jul 16, 2026 | 49d overdue | Unassigned | $15,704 | ||
| Bldg C-Residence at Millcreek-Rimrock | Scratch Coat | Jul 16, 2026 | 49d overdue | Unassigned | $1,811 | ||
| Bldg D-Residence at Millcreek-Rimrock | Remove Scaff | Aug 6, 2026 | 28d overdue | Unassigned | $2,133 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | Penetration Sealing | Aug 15, 2026 | 19d overdue | Unassigned | $0 | ||
| Bldg C-Residence at Millcreek-Rimrock | Paint | Aug 24, 2026 | 10d overdue | Unassigned | $1,838 | ||
| White Dome Chapel-St George-Grass Creek | Set Scaff | Aug 27, 2026 | 7d overdue | Unassigned | 2026-08-27 | $57 | |
| 206-Fort Pierce-Dawson Development | Paper/Wire | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-03 | $50 | |
| 205-Fort Pierce-Dawson Development | Paper/Wire | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-03 | $50 | |
| 203-Fort Pierce-Dawson Development | Paper/Wire | Sep 1, 2026 | 2d overdue | Unassigned | 2026-09-03 | $50 | |
| Garage 4-Residence at Millcreek-Rimrock | Set Scaff | Sep 1, 2026 | 2d overdue | Unassigned | 2026-08-31 | $644 | |
| Bldg C-Residence at Millcreek-Rimrock | Stucco Color | Sep 2, 2026 | 1d overdue | Unassigned | $6,354 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Cascade West Haven Warehouse-Overhead Projects (Ogden)-Unknown | Misc. Work | Aug 17, 2026 | 17d overdue | Unassigned | $0 | Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP |
Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):
Assigned Task Date is not blankTeam (Task Team) is blankCompleted Date/Time is blankTeam and Team Name agree on every record
(0 disagreements), so "no team assigned" is unambiguous.