Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Sep 9, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Nov 3, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Sep 9, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 14,022 task records pulled, 214 matched the filter · assignment dates Jul 16, 2026 to Nov 3, 2026

214
Ready for assignment
103
Past assignment date
6
Divisions affected
$213,969
Unassigned task pay
55d
Oldest overdue

Ready tasks by division

021426485Orem8531 odOgden7754 odSalt Lake282 odSt. George126 odCommercial119 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Orem·
Ogden··
Salt Lake··
St. George···
Commercial···
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 27 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionInsl Foam 1Insl WallsPenetration SealingWindow Pre WrapSet ScaffHousewrapSet Brick ScaffSpecial CorbelsPaper/WireEIFS Weather BarrierStucco BrownScratch CoatPaintSidingWateringRockBrickVinylSoffit/FasciaGuttersRemove ScaffShuttersVPO WorkStucco ColorInsl AtticMisc. WorkFoundation PlasterTotal
Orem···········
Ogden········
Salt Lake··················
St. George·························
Commercial···················
Corporate··························
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 147 of 214 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorRockSidingGuttersSoffitInsulationStucco BrownPaper/WirePaintBrickHousewrapField OpsWarrantyAny tradeTotal
Orem····
Ogden··
Salt Lake······
St. George·············
Commercial········
Corporate··············
All divisions·

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorRockSidingGuttersSoffitInsulationStucco BrownPaper/WirePaintBrickHousewrapField OpsWarrantyAny tradeTotal
Orem·······
Ogden············
Salt Lake···········
St. George··········
Commercial················
Corporate················
All divisions·····

31 crews company-wide have a hand up, counted once per division they cover (39 crew-division slots, of which 8 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Orem — 85 tasks ready for assignment · 31 overdue · $88,802
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
47-Lakeview Fields-Keystone ConstructionMisc. WorkAug 25, 202615d overdueUnassigned$60Gutter was damaged during scaffolding removal and needs to be replaced.
2014-Wildflower-Toll BrothersFoundation PlasterAug 27, 202613d overdueUnassigned$450⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-08 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l
106-Canyon Park-Tri Pointe HomesPaper/WireAug 29, 202611d overdueUnassigned2026-08-13$117⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-14 ✅ 2026-08-20:
143-Montreux-DR HortonSidingSep 1, 20268d overdueUnassigned2026-08-27$6,281⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-09 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
143-Montreux-DR HortonSoffit/FasciaSep 1, 20268d overdueUnassigned$937⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-09 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
130-Montreux-DR HortonSoffit/FasciaSep 1, 20268d overdueUnassigned$747✅ 2026-08-28: Material Delay - Missing all the siding - Alex 2026-09-03
102-Canton Ridge-RichmondSpecial CorbelsSep 1, 20268d overdueUnassigned$50
143-Montreux-DR HortonRockSep 2, 20267d overdueUnassigned$706⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-09 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
826-Broadview Shores-IvoryRockSep 2, 20267d overdueUnassigned$2,299✅ 2026-08-24: Material Delay - Missing all the lath and stucco orders - Alex 2026-08-28
143-Montreux-DR HortonScratch CoatSep 2, 20267d overdueUnassigned$83⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-09 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
531-River Point-EdgeRockSep 3, 20266d overdueUnassigned$187
531-River Point-EdgeScratch CoatSep 3, 20266d overdueUnassigned$50
352 (FP)-Viridian Emerald-DR HortonRockSep 4, 20265d overdueUnassigned$351
919-Broadview Shores-IvoryRockSep 4, 20265d overdueUnassigned$1,459
248-Canton Ridge-RichmondRockSep 4, 20265d overdueUnassigned$933
717-Highridge-EdgeRockSep 4, 20265d overdueUnassigned$129
517-River Point-EdgeSet ScaffSep 4, 20265d overdueUnassigned2026-09-11$625
16122-Harmony-Meritage HomesSoffit/FasciaSep 4, 20265d overdueUnassigned$582
Bldg 10-Montreux Townhomes-DR HortonSoffit/FasciaSep 4, 20265d overdueUnassigned$1,579✅ 2026-08-12: 4 Days - Do not send teams yet. Waiting on columns to be fully wrapped before commencing. - Alex 2026-08-18
2021-Wildflower-Toll BrothersRockSep 5, 20264d overdueUnassigned$1,893⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan Est End: 2026-09-10 ✅ 2026-08-21: 1 Days - Tyvek delay - there is a front section of Sca
1027-Harmony Ridge-EdgeRockSep 5, 20264d overdueUnassigned$187
1027-Harmony Ridge-EdgeScratch CoatSep 5, 20264d overdueUnassigned$50
233-Viridian Plus-DR HortonSet ScaffSep 5, 20264d overdueUnassigned2026-09-10$978
2021-Wildflower-Toll BrothersStucco BrownSep 5, 20264d overdueUnassigned2026-08-21$129⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan Est End: 2026-09-10 ✅ 2026-08-21: 1 Days - Tyvek delay - there is a front section of Sca
1027-Harmony Ridge-EdgeStucco BrownSep 5, 20264d overdueUnassigned2026-08-24$1,117
36-Lakeview Fields-Keystone ConstructionStucco ColorSep 6, 20263d overdueUnassigned$1,256
Wellspring Park Restroom-Viridian Townhomes-DR HortonSet ScaffSep 7, 20262d overdueUnassigned$15
346-Mountain Vista at Sunset Flats-Pulte HomesPaintSep 8, 20261d overdueUnassigned$310✅ 2026-08-31: 6 Days - We need to wait to lath we need to pass Housewrap inspections before we can lath thanks ?? - Victor 2026-09-08
2024-Wildflower-Toll BrothersStucco ColorSep 8, 20261d overdueUnassigned$130✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-08-31
741-Broadview Shores-IvoryStucco ColorSep 8, 20261d overdueUnassigned$846
723-Highridge-EdgeStucco ColorSep 8, 20261d overdueUnassigned2026-09-08$1,100
Units 975-979-Anderson Farms Townhomes-IvoryBrickSep 9, 2026todayUnassigned$14,239
254-Canton Ridge-RichmondBrickSep 9, 2026todayUnassigned$1,441
102-Canton Ridge-RichmondRockSep 9, 2026todayUnassigned$1,094
135-Auburn Springs-EdgeRockSep 9, 2026todayUnassigned$1,036⭕ 2026-09-08: Columns are twisted - Harrison Est End: 2026-09-11
102-Canton Ridge-RichmondScratch CoatSep 9, 2026todayUnassigned$99
135-Auburn Springs-EdgeScratch CoatSep 9, 2026todayUnassigned$150⭕ 2026-09-08: Columns are twisted - Harrison Est End: 2026-09-11
107-Auburn Springs-EdgeSet ScaffSep 9, 2026todayUnassigned2026-09-09$840
135-Auburn Springs-EdgeSidingSep 9, 2026todayUnassigned2026-09-09$5,360⭕ 2026-09-08: Columns are twisted - Harrison Est End: 2026-09-11
16121-Harmony-Meritage HomesSoffit/FasciaSep 9, 2026todayUnassigned$602
16121-Harmony-Meritage HomesStucco BrownSep 9, 2026todayUnassigned2026-08-31$172
102-Canton Ridge-RichmondStucco BrownSep 9, 2026todayUnassigned2026-09-02$1,210
Bldg 57-Harmony Ridge-EdgeStucco ColorSep 9, 2026todayUnassigned$2,382
919-Broadview Shores-IvoryStucco ColorSep 9, 2026todayUnassigned$902
234-Viridian Plus-DR HortonSet ScaffSep 10, 2026in 1dUnassigned$763
2181-Wildflower-EdgeSet ScaffSep 10, 2026in 1dUnassigned$652
340-Viridian-DR HortonSet ScaffSep 10, 2026in 1dUnassigned$606
725-Highridge-EdgeStucco ColorSep 10, 2026in 1dUnassigned$1,284
Units 279-284-Highline-CenturyStucco ColorSep 11, 2026in 2dUnassigned$2,159
107-Vista at Harmony Place-WoodsideStucco ColorSep 12, 2026in 3dUnassigned$768
248-Canton Ridge-RichmondStucco ColorSep 12, 2026in 3dUnassigned$874
434-Viridian-DR HortonStucco ColorSep 13, 2026in 4dUnassigned$1,212✅
2227-Wildflower-EdgeSet ScaffSep 14, 2026in 5dUnassigned$758
420-Viridian-DR HortonSet ScaffSep 14, 2026in 5dUnassigned$681
711-Ridgehorne-EdgeSet ScaffSep 14, 2026in 5dUnassigned$747
1021-Harmony Ridge-EdgeSet ScaffSep 14, 2026in 5dUnassigned2026-09-14$786
718-Highridge-EdgeSet ScaffSep 14, 2026in 5dUnassigned$831
108-Auburn Springs-EdgeSet ScaffSep 14, 2026in 5dUnassigned$930
109-Vista at Harmony Place-WoodsideStucco ColorSep 14, 2026in 5dUnassigned$802
Bldg 56-Harmony Ridge-EdgeSet ScaffSep 15, 2026in 6dUnassigned$1,891
115-Auburn Springs-EdgeSet ScaffSep 15, 2026in 6dUnassigned$780
339-Viridian-DR HortonSet ScaffSep 16, 2026in 7dUnassigned$574
Bldg 37-Highridge-EdgeInsl Foam 1Sep 17, 2026in 8dUnassigned$115
Bldg 37-Highridge-EdgeInsl WallsSep 17, 2026in 8dUnassigned$912
523-River Point-EdgeSet ScaffSep 17, 2026in 8dUnassigned$745
147-Auburn Springs-EdgeSet ScaffSep 17, 2026in 8dUnassigned$723
711-Highridge-EdgeSet ScaffSep 17, 2026in 8dUnassigned$561
2212-Wildflower-EdgeSet ScaffSep 18, 2026in 9dUnassigned$660
133-Auburn Springs-EdgeSet ScaffSep 18, 2026in 9dUnassigned$991
2228-Wildflower-EdgeSet ScaffSep 18, 2026in 9dUnassigned$807
Bldg 37-Highridge-EdgeSet ScaffSep 18, 2026in 9dUnassigned$1,104
518-River Point-EdgeSet ScaffSep 21, 2026in 12dUnassigned$583
246-Viridian Plus-DR HortonSet ScaffSep 21, 2026in 12dUnassigned$784
525-River Point-EdgeSet ScaffSep 21, 2026in 12dUnassigned$671
1030-Harmony Ridge-EdgeSet ScaffSep 21, 2026in 12dUnassigned$753
353-Viridian Emerald-DR HortonSet ScaffSep 22, 2026in 13dUnassigned2026-09-08$841⭕
1031-Harmony Ridge-EdgeSet ScaffSep 22, 2026in 13dUnassigned$709
721-Ridgehorne-EdgeSet ScaffSep 22, 2026in 13dUnassigned$518
106-Auburn Springs-EdgeSet ScaffSep 23, 2026in 14dUnassigned$958
519-River Point-EdgeSet ScaffSep 23, 2026in 14dUnassigned$693
710-Highridge-EdgeSet ScaffSep 23, 2026in 14dUnassigned$668
Bldg 38-Highridge-EdgeSet ScaffSep 28, 2026in 19dUnassigned$1,104
Bldg 59-Harmony Ridge-EdgeSet ScaffSep 29, 2026in 20dUnassigned$1,480
Bldg 39-Highridge-EdgeInsl AtticOct 9, 2026in 30dUnassigned$80
Bldg 37-Highridge-EdgeInsl AtticNov 3, 2026in 55dUnassigned$80
Ogden — 77 tasks ready for assignment · 54 overdue · $48,052
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
108-Red Hill-IvorySet Brick ScaffAug 12, 202628d overdueUnassigned$40
206-Fremont Meadows-Sterling HomesScratch CoatAug 13, 202627d overdueUnassigned$50
71-Brookfield-LennarGuttersAug 24, 202616d overdueUnassigned$167
63-Brookfield-LennarGuttersAug 24, 202616d overdueUnassigned$236
106-Red Hill-IvorySet Brick ScaffAug 24, 202616d overdueUnassigned$0
Bldg 25-Railrunner-DAI ConstructionGuttersAug 25, 202615d overdueUnassigned$806
108-Red Hill-IvoryScratch CoatAug 25, 202615d overdueUnassigned$50
Bldg 6-Midtown Village-DR HortonSet Brick ScaffAug 26, 202614d overdueUnassigned$0⭕ 2026-09-08: not ready for lathe is missing the metal cap - George Est End: 2026-09-11
1523-Cranefield Estates-IvorySet Brick ScaffAug 26, 202614d overdueUnassigned$134
176-Mountain Gate-Sierra HomesSidingAug 27, 202613d overdueUnassigned2026-08-27$220
106-Red Hill-IvoryBrickAug 28, 202612d overdueUnassigned$50
Bldg 2-Railrunner-DAI ConstructionSidingAug 28, 202612d overdueUnassigned2026-08-14$782✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0
106-Three Farms Jenkins Fields-IvoryGuttersAug 29, 202611d overdueUnassigned$146
Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction GroupRockAug 31, 20269d overdueUnassigned$635⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15
102-Meadows at Hyde Park-VisionarySidingAug 31, 20269d overdueUnassigned2026-09-04$1,261
227-Bristol Farms-Regal HomesStucco ColorAug 31, 20269d overdueUnassigned2026-09-08$1,246
338-Sugar Creek-VisionarySidingSep 1, 20268d overdueUnassigned2026-08-28$489
Bldg AC-North Point Townhomes-VisionarySidingSep 1, 20268d overdueUnassigned2026-08-19$6,469
4-Heritage Parkway-Sierra HomesRemove ScaffSep 2, 20267d overdueUnassigned$13✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04
520-Vineyard-VisionaryRockSep 2, 20267d overdueUnassigned$402✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24
603-Vineyard-VisionaryScratch CoatSep 2, 20267d overdueUnassigned$74
SF 6-Flint Acres-Henry Walker HomesScratch CoatSep 2, 20267d overdueUnassigned$187
520-Vineyard-VisionaryScratch CoatSep 2, 20267d overdueUnassigned$50✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24
723-Ridgeline Park-VisionarySidingSep 2, 20267d overdueUnassigned2026-08-19$1,603✅ 2026-09-02: -1 Days - Can’t start siding because front porch cap is not poured - Ronnie 2026-09-01
821-Ridgeline Park-VisionarySidingSep 2, 20267d overdueUnassigned2026-08-13$941
17-Sunset Ridges-Sierra HomesStucco ColorSep 2, 20267d overdueUnassigned2026-09-04$301✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
311-Legacy Park-IvoryBrickSep 3, 20266d overdueUnassigned2026-08-21$2,826
Bldg G-Legends Crossing Townhomes-VisionaryPaintSep 3, 20266d overdueUnassigned$187
102-Village at Fox Meadows-VisionarySet ScaffSep 3, 20266d overdueUnassigned2026-09-03$446✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
102-Village at Fox Meadows-VisionarySidingSep 3, 20266d overdueUnassigned2026-08-27$1,217✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
107-Stagecoach Estates-McArthurWindow Pre WrapSep 3, 20266d overdueUnassigned$100
711-Ridgeline Park-VisionaryRemove ScaffSep 4, 20265d overdueUnassigned$0
TH 6-Flint Acres-Henry Walker HomesSet ScaffSep 4, 20265d overdueUnassigned2026-09-04$772
11-Mountainside Estates-DR HortonVPO WorkSep 4, 20265d overdueUnassigned$60We need to do the wrap beams post and the gable
TH 6-Flint Acres-Henry Walker HomesHousewrapSep 5, 20264d overdueUnassigned2026-08-18$667
103-Legends Crossing-VisionaryPaper/WireSep 5, 20264d overdueUnassigned2026-09-03$50
SF 7-Flint Acres-Henry Walker HomesScratch CoatSep 5, 20264d overdueUnassigned$331
505-Legacy Park-IvoryScratch CoatSep 5, 20264d overdueUnassigned$182✅ 2026-09-02: 1 Days - Inspection delayed. - Erik 2026-09-03
227-Bristol Farms-Regal HomesShuttersSep 5, 20264d overdueUnassigned$50
12-Mountainside Estates-DR HortonStucco ColorSep 5, 20264d overdueUnassigned2026-09-07$1,034
11-Mountainside Estates-DR HortonStucco ColorSep 6, 20263d overdueUnassigned2026-09-07$1,115
115-Three Farms Jenkins Fields-IvoryWateringSep 6, 20263d overdueUnassigned$85
2-Brynlee Acres-HamletPaintSep 7, 20262d overdueUnassigned$284
17-Sunset Ridges-Sierra HomesSidingSep 7, 20262d overdueUnassigned2026-07-30$261✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
17-Sunset Ridges-Sierra HomesVinylSep 7, 20262d overdueUnassigned$1,819✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
1707-Cranefield Estates-IvoryGuttersSep 8, 20261d overdueUnassigned$360
112-Three Farms Jenkins Fields-IvoryGuttersSep 8, 20261d overdueUnassigned$366
330-Riverside Estates-Fieldstone HomesGuttersSep 8, 20261d overdueUnassigned$321
12-Mountainside Estates-DR HortonPaintSep 8, 20261d overdueUnassigned$677
126-Palomino-DR HortonSoffit/FasciaSep 8, 20261d overdueUnassigned$643
125-Palomino-DR HortonSoffit/FasciaSep 8, 20261d overdueUnassigned$584
227-Bristol Farms-Regal HomesSoffit/FasciaSep 8, 20261d overdueUnassigned$893
2-Brynlee Acres-HamletStucco ColorSep 8, 20261d overdueUnassigned2026-09-09$692
176-Mountain Gate-Sierra HomesVinylSep 8, 20261d overdueUnassigned$1,439
253-Westwood Estates-Meritage HomesGuttersSep 9, 2026todayUnassigned$464
254-Westwood Estates-Meritage HomesGuttersSep 9, 2026todayUnassigned$287
3-Brynlee Acres-HamletGuttersSep 9, 2026todayUnassigned$248
125-Palomino-DR HortonGuttersSep 9, 2026todayUnassigned$321
111-Stagecoach Estates-McArthurGuttersSep 9, 2026todayUnassigned$293
314-Stagecoach Estates-McArthurGuttersSep 9, 2026todayUnassigned$255
501-Legacy Park-IvoryGuttersSep 9, 2026todayUnassigned$234
821-Ridgeline Park-VisionaryRockSep 9, 2026todayUnassigned$483
821-Ridgeline Park-VisionaryScratch CoatSep 9, 2026todayUnassigned$50
3-Brynlee Acres-HamletSoffit/FasciaSep 9, 2026todayUnassigned$796
17-Sunset Ridges-Sierra HomesSoffit/FasciaSep 9, 2026todayUnassigned$650✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
229-Bristol Farms-Regal HomesSoffit/FasciaSep 9, 2026todayUnassigned$720
1709-Cranefield Estates-IvoryStucco ColorSep 9, 2026todayUnassigned2026-09-10$790
336-Sugar Creek-VisionaryStucco ColorSep 9, 2026todayUnassigned2026-09-11$995✅ 2026-08-22: Material Delay - We still missing the initial order - Jose 2026-08-26
313-Stagecoach Estates-McArthurStucco ColorSep 9, 2026todayUnassigned2026-09-08$1,076
311-Legacy Park-IvoryStucco ColorSep 9, 2026todayUnassigned2026-09-09$855
505-Legacy Park-IvoryStucco ColorSep 9, 2026todayUnassigned2026-09-09$868✅ 2026-09-02: 1 Days - Inspection delayed. - Erik 2026-09-03
229-Bristol Farms-Regal HomesStucco ColorSep 9, 2026todayUnassigned2026-09-08$1,210
521-Vineyard-VisionarySidingSep 10, 2026in 1dUnassigned2026-08-27$714
4-Brynlee Acres-HamletStucco BrownSep 10, 2026in 1dUnassigned2026-08-19$933
115-Three Farms Jenkins Fields-IvoryStucco ColorSep 10, 2026in 1dUnassigned2026-09-09$1,080
609-Village at Fox Meadows-VisionaryScratch CoatSep 11, 2026in 2dUnassigned$50
115-Meadows at Hyde Park-VisionaryStucco ColorSep 14, 2026in 5dUnassigned$867
Salt Lake — 28 tasks ready for assignment · 2 overdue · $23,078
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg 20-Solari-EdgeStucco ColorSep 5, 20264d overdueUnassigned2026-09-10$2,876✅ 2026-08-19: 4 Days - Delayed for drywall windows and gas line - Dustin 2026-08-25
2909-Mountain Ridge-EdgePaper/WireSep 8, 20261d overdueUnassigned2026-09-10$134
22-Sky Ranch Cascade-WoodsideHousewrapSep 9, 2026todayUnassigned2026-09-10$690
153-Pierson Farms-McArthurRockSep 9, 2026todayUnassigned$871
111-Creek Ridge Cove-RichmondRockSep 9, 2026todayUnassigned$1,079✅ 2026-08-28: 3 Days - Can’t finish lath and housewrap until back sliding door gets installed - Arturo 2026-09-02
2919-Mountain Ridge-EdgeRockSep 9, 2026todayUnassigned$513✅ 2026-08-26: 3 Days - Don’t start paper and wire or housewrap until client CM gives us the go - Arturo 2026-08-31
2920-Mountain Ridge-EdgeRockSep 9, 2026todayUnassigned$211✅ 2026-08-26: 3 Days - Don’t start paper and wire or housewrap until client CM gives us the go - Arturo 2026-08-31
153-Pierson Farms-McArthurScratch CoatSep 9, 2026todayUnassigned$102
2919-Mountain Ridge-EdgeScratch CoatSep 9, 2026todayUnassigned$74✅ 2026-08-26: 3 Days - Don’t start paper and wire or housewrap until client CM gives us the go - Arturo 2026-08-31
2920-Mountain Ridge-EdgeScratch CoatSep 9, 2026todayUnassigned$50✅ 2026-08-26: 3 Days - Don’t start paper and wire or housewrap until client CM gives us the go - Arturo 2026-08-31
Units 508-509-Daybreak Duets-Destination HomesSidingSep 9, 2026todayUnassigned2026-08-30$513
153-Pierson Farms-McArthurSidingSep 9, 2026todayUnassigned2026-08-31$721
Units 508-509-Daybreak Duets-Destination HomesStucco BrownSep 9, 2026todayUnassigned2026-08-28$2,206
Bldg 9-Taylor Villas-EdgeStucco ColorSep 9, 2026todayUnassigned2026-09-10$1,948✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
Bldg 201-Mountain Ridge-EdgeStucco ColorSep 12, 2026in 3dUnassigned$1,854
Bldg 202-Mountain Ridge-EdgeStucco ColorSep 12, 2026in 3dUnassigned$1,620
2929-Mountain Ridge-EdgeSet ScaffSep 15, 2026in 6dUnassigned$577
2916-Mountain Ridge-EdgeSet ScaffSep 17, 2026in 8dUnassigned$752
Bldg 18-Solari-EdgeSet ScaffSep 18, 2026in 9dUnassigned$1,570
Bldg 19-Solari-EdgeSet ScaffSep 18, 2026in 9dUnassigned$1,570
Bldg 203-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 13dUnassigned$1,474
2931-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 13dUnassigned$712
Bldg 9-Taylor Villas-EdgeInsl AtticSep 29, 2026in 20dUnassigned$179✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
Bldg 1-Solari-EdgeInsl AtticOct 1, 2026in 22dUnassigned$143✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19
Bldg 208-Mountain Ridge-EdgeInsl AtticOct 14, 2026in 35dUnassigned$144
Bldg 202-Mountain Ridge-EdgeInsl AtticOct 20, 2026in 41dUnassigned$143
Bldg 22-Solari-EdgeInsl AtticOct 26, 2026in 47dUnassigned$160
Bldg 19-Solari-EdgeInsl AtticNov 3, 2026in 55dUnassigned$192
St. George — 12 tasks ready for assignment · 6 overdue · $23,202
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
4272-Long Valley-DR HortonStucco ColorSep 6, 20263d overdueUnassigned2026-09-04$1,711
4290-Long Valley-DR HortonStucco ColorSep 7, 20262d overdueUnassigned2026-09-08$2,327
35-Legacy at Sand Hollow-VisionaryStucco ColorSep 7, 20262d overdueUnassigned2026-09-08$2,523
16-Desert Cove-RichmondStucco ColorSep 8, 20261d overdueUnassigned2026-09-04$1,887
4202-Long Valley-DR HortonStucco ColorSep 8, 20261d overdueUnassigned2026-09-08$2,016
76-Divario-VisionaryStucco ColorSep 8, 20261d overdueUnassigned2026-09-08$2,195
323-Finley Farms-RichmondRockSep 9, 2026todayUnassigned$571
4156-Long Valley Rambler-DR HortonStucco ColorSep 9, 2026todayUnassigned$1,183
413-The Preserve at Alaia-VisionaryStucco ColorSep 10, 2026in 1dUnassigned2026-09-09$2,021
32-Legacy at Sand Hollow-VisionaryStucco ColorSep 12, 2026in 3dUnassigned2026-09-09$1,981
323-Finley Farms-RichmondStucco ColorSep 13, 2026in 4dUnassigned$2,963
104-La Spazio-LennarStucco ColorSep 13, 2026in 4dUnassigned$1,823
Commercial — 11 tasks ready for assignment · 9 overdue · $30,836
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-RimrockScratch CoatJul 16, 202655d overdueUnassigned$1,811
Bldg D-Residence at Millcreek-RimrockRemove ScaffAug 6, 202634d overdueUnassigned$7,542
Bldg RU-1-ARA Southwest-Campbell ConstructionPenetration SealingAug 15, 202625d overdueUnassigned$0
Bldg C-Residence at Millcreek-RimrockPaintAug 24, 202616d overdueUnassigned$1,838
White Dome Chapel-St George-Grass CreekSet ScaffAug 27, 202613d overdueUnassigned2026-08-27$57
Bldg RU-1-ARA Southwest-Campbell ConstructionEIFS Weather BarrierSep 1, 20268d overdueUnassigned$1,843
206-Fort Pierce-Dawson DevelopmentPaper/WireSep 1, 20268d overdueUnassigned2026-09-03$50
205-Fort Pierce-Dawson DevelopmentPaper/WireSep 1, 20268d overdueUnassigned2026-09-03$50
203-Fort Pierce-Dawson DevelopmentPaper/WireSep 1, 20268d overdueUnassigned2026-09-03$50
Bldg D-Residence at Millcreek-RimrockRockSep 9, 2026todayUnassigned$15,588
Bldg D-Residence at Millcreek-RimrockScratch CoatSep 9, 2026todayUnassigned$2,008
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-UnknownMisc. WorkAug 17, 202623d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 290 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: