Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Sep 11, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Nov 3, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Sep 11, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 14,186 task records pulled, 228 matched the filter · assignment dates Jul 16, 2026 to Nov 3, 2026

228
Ready for assignment
107
Past assignment date
6
Divisions affected
$242,200
Unassigned task pay
57d
Oldest overdue

Ready tasks by division

022446688Ogden8857 odOrem8430 odSalt Lake323 odSt. George147 odCommercial99 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Ogden·
Orem·
Salt Lake··
St. George···
Commercial···
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 29 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionInsl Foam 1Insl WallsPenetration SealingWindow Pre WrapSet ScaffHousewrapSet Brick ScaffSpecial CorbelsPaper/WireEIFS Weather BarrierStucco BrownScratch CoatPaintSidingWateringRockBrickVinylSoffit/FasciaBrown & MeshGuttersRemove ScaffShuttersStucco ColorScaff PickupVPO WorkMisc. WorkInsl AtticFoundation PlasterTotal
Ogden·········
Orem·············
Salt Lake····················
St. George························
Commercial·····················
Corporate····························
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 183 of 228 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorSidingRockSoffitInsulationGuttersStucco BrownPaintBrickPaper/WireHousewrapField OpsWarrantyAny tradeTotal
Ogden··
Orem·····
Salt Lake······
St. George···········
Commercial········
Corporate··············
All divisions·

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorSidingRockSoffitInsulationGuttersStucco BrownPaintBrickPaper/WireHousewrapField OpsWarrantyAny tradeTotal
Ogden··············
Orem·········
Salt Lake············
St. George············
Commercial················
Corporate················
All divisions········

20 crews company-wide have a hand up, counted once per division they cover (22 crew-division slots, of which 2 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Ogden — 88 tasks ready for assignment · 57 overdue · $68,623
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
108-Red Hill-IvorySet Brick ScaffAug 12, 202630d overdueUnassigned$40
206-Fremont Meadows-Sterling HomesScratch CoatAug 13, 202629d overdueUnassigned$50
71-Brookfield-LennarGuttersAug 24, 202618d overdueUnassigned$167
63-Brookfield-LennarGuttersAug 24, 202618d overdueUnassigned$236
106-Red Hill-IvorySet Brick ScaffAug 24, 202618d overdueUnassigned$0
108-Red Hill-IvoryScratch CoatAug 25, 202617d overdueUnassigned$50
Bldg 6-Midtown Village-DR HortonSet Brick ScaffAug 26, 202616d overdueUnassigned$0⭕ 2026-09-08: not ready for lathe is missing the metal cap - George Est End: 2026-09-11
1523-Cranefield Estates-IvorySet Brick ScaffAug 26, 202616d overdueUnassigned$134
176-Mountain Gate-Sierra HomesSidingAug 27, 202615d overdueUnassigned$50
106-Red Hill-IvoryBrickAug 28, 202614d overdueUnassigned2026-08-26$50
Bldg 2-Railrunner-DAI ConstructionSidingAug 28, 202614d overdueUnassigned2026-08-26$782✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0
Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction GroupRockAug 31, 202611d overdueUnassigned2026-08-26$635⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15
102-Meadows at Hyde Park-VisionarySidingAug 31, 202611d overdueUnassigned$1,261
338-Sugar Creek-VisionarySidingSep 1, 202610d overdueUnassigned$489
4-Heritage Parkway-Sierra HomesRemove ScaffSep 2, 20269d overdueUnassigned$13✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04
603-Vineyard-VisionaryScratch CoatSep 2, 20269d overdueUnassigned$74
723-Ridgeline Park-VisionarySidingSep 2, 20269d overdueUnassigned2026-08-26$1,603✅ 2026-09-02: -1 Days - Can’t start siding because front porch cap is not poured - Ronnie 2026-09-01
821-Ridgeline Park-VisionarySidingSep 2, 20269d overdueUnassigned2026-08-26$941
102-Village at Fox Meadows-VisionarySet ScaffSep 3, 20268d overdueUnassigned$446✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
102-Village at Fox Meadows-VisionarySidingSep 3, 20268d overdueUnassigned2026-09-04$1,217✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
49-Mountainside Estates-DR HortonVPO WorkSep 4, 20267d overdueUnassigned$60We need to fix the siding and add flashing on the font stoop
SF 7-Flint Acres-Henry Walker HomesScratch CoatSep 5, 20266d overdueUnassigned$331
227-Bristol Farms-Regal HomesShuttersSep 5, 20266d overdueUnassigned2026-09-05$50
17-Sunset Ridges-Sierra HomesSidingSep 7, 20264d overdueUnassigned2026-08-26$261✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
17-Sunset Ridges-Sierra HomesVinylSep 7, 20264d overdueUnassigned2026-07-15$1,819✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
1707-Cranefield Estates-IvoryGuttersSep 8, 20263d overdueUnassigned$360
2-Brynlee Acres-HamletStucco ColorSep 8, 20263d overdueUnassigned$692
176-Mountain Gate-Sierra HomesVinylSep 8, 20263d overdueUnassigned$671
SF 6-Flint Acres-Henry Walker HomesPaintSep 9, 20262d overdueUnassigned2026-09-05$1,166
11-Heritage Parkway-Sierra HomesPaintSep 9, 20262d overdueUnassigned$580✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07
821-Ridgeline Park-VisionaryRockSep 9, 20262d overdueUnassigned2026-09-01$483
229-Bristol Farms-Regal HomesShuttersSep 9, 20262d overdueUnassigned2026-09-05$100
339-Sugar Creek-VisionarySidingSep 9, 20262d overdueUnassigned$364
Bldg L-Sugar Creek Townhomes-VisionarySidingSep 9, 20262d overdueUnassigned2026-08-10$6,419
17-Sunset Ridges-Sierra HomesSoffit/FasciaSep 9, 20262d overdueUnassigned$650✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24
1709-Cranefield Estates-IvoryStucco ColorSep 9, 20262d overdueUnassigned$790
Bldg 2-Railrunner-DAI ConstructionVinylSep 9, 20262d overdueUnassigned$9,494✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0
116-Meadows at Hyde Park-VisionaryBrickSep 10, 20261d overdueUnassigned$1,723
116-Meadows at Hyde Park-VisionaryBrown & MeshSep 10, 20261d overdueUnassigned$1,000
102-Legends Crossing-VisionaryPaintSep 10, 20261d overdueUnassigned$102
103-Legends Crossing-VisionaryPaper/WireSep 10, 20261d overdueUnassigned$50
323-Stagecoach Estates-McArthurRemove ScaffSep 10, 20261d overdueUnassigned$351
332-Riverside Estates-Fieldstone HomesRemove ScaffSep 10, 20261d overdueUnassigned$401✅ 2026-08-03: Material Delay - - George 2026-08-17
9-Crested Peaks-IvoryRockSep 10, 20261d overdueUnassigned2026-08-26$4,768
116-Meadows at Hyde Park-VisionaryScratch CoatSep 10, 20261d overdueUnassigned$121
9-Crested Peaks-IvoryScratch CoatSep 10, 20261d overdueUnassigned$646
503-Vineyard-VisionarySet ScaffSep 10, 20261d overdueUnassigned$490
515-Vineyard-VisionarySet ScaffSep 10, 20261d overdueUnassigned$0
126-Red Hill-IvorySet ScaffSep 10, 20261d overdueUnassigned$36
515-Vineyard-VisionarySidingSep 10, 20261d overdueUnassigned$4,879
503-Vineyard-VisionarySidingSep 10, 20261d overdueUnassigned$1,338
4-Brynlee Acres-HamletSidingSep 10, 20261d overdueUnassigned2026-08-26$888
521-Vineyard-VisionarySidingSep 10, 20261d overdueUnassigned$714
12-Mountainside Estates-DR HortonSoffit/FasciaSep 10, 20261d overdueUnassigned$769
107-Red Hill-IvorySoffit/FasciaSep 10, 20261d overdueUnassigned$554
108-Red Hill-IvorySoffit/FasciaSep 10, 20261d overdueUnassigned$553
115-Three Farms Jenkins Fields-IvorySoffit/FasciaSep 10, 20261d overdueUnassigned$546
102-Meadows at Hyde Park-VisionaryBrickSep 11, 2026todayUnassigned$736
102-Meadows at Hyde Park-VisionaryBrown & MeshSep 11, 2026todayUnassigned$1,390
253-Westwood Estates-Meritage HomesGuttersSep 11, 2026todayUnassigned$464
254-Westwood Estates-Meritage HomesGuttersSep 11, 2026todayUnassigned$287
Bldg U-Village at Fox Meadows Townhomes-VisionaryGuttersSep 11, 2026todayUnassigned$1,001
3-Brynlee Acres-HamletGuttersSep 11, 2026todayUnassigned$248
12-Mountainside Estates-DR HortonGuttersSep 11, 2026todayUnassigned$262
1708-Cranefield Estates-IvoryGuttersSep 11, 2026todayUnassigned$266
330-Riverside Estates-Fieldstone HomesGuttersSep 11, 2026todayUnassigned$321
126-Red Hill-IvoryHousewrapSep 11, 2026todayUnassigned$473
2-Brynlee Acres-HamletPaintSep 11, 2026todayUnassigned$284
609-Village at Fox Meadows-VisionaryPaintSep 11, 2026todayUnassigned$583
Bldg G-Legends Crossing Townhomes-VisionaryPaintSep 11, 2026todayUnassigned$187
6-Heritage Parkway-Sierra HomesRemove ScaffSep 11, 2026todayUnassigned$9
108-Stagecoach Estates-McArthurRockSep 11, 2026todayUnassigned$906
501-Legacy Park-IvoryScaff PickupSep 11, 2026todayUnassigned$0Trailer ready for pick up
108-Stagecoach Estates-McArthurScratch CoatSep 11, 2026todayUnassigned$107
102-Meadows at Hyde Park-VisionaryScratch CoatSep 11, 2026todayUnassigned$77
609-Village at Fox Meadows-VisionaryScratch CoatSep 11, 2026todayUnassigned$50
108-Stagecoach Estates-McArthurSidingSep 11, 2026todayUnassigned2026-09-10$369
3-Brynlee Acres-HamletSoffit/FasciaSep 11, 2026todayUnassigned$796
108-Stagecoach Estates-McArthurStucco BrownSep 11, 2026todayUnassigned$1,069
11-Mountainside Estates-DR HortonStucco ColorSep 11, 2026todayUnassigned$1,115
4-Brynlee Acres-HamletWateringSep 11, 2026todayUnassigned$78
520-Vineyard-VisionaryStucco ColorSep 12, 2026in 1dUnassigned2026-09-08$518✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24
609-Village at Fox Meadows-VisionaryStucco ColorSep 14, 2026in 3dUnassigned$786
821-Ridgeline Park-VisionaryStucco ColorSep 14, 2026in 3dUnassigned$452
115-Meadows at Hyde Park-VisionaryStucco ColorSep 14, 2026in 3dUnassigned$867
4-Brynlee Acres-HamletStucco ColorSep 15, 2026in 4dUnassigned$806
603-Vineyard-VisionaryStucco ColorSep 15, 2026in 4dUnassigned2026-09-08$1,139
1523-Cranefield Estates-IvoryStucco ColorSep 15, 2026in 4dUnassigned$520
Orem — 84 tasks ready for assignment · 30 overdue · $79,022
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
47-Lakeview Fields-Keystone ConstructionMisc. WorkAug 25, 202617d overdueUnassigned$60Gutter was damaged during scaffolding removal and needs to be replaced.
2014-Wildflower-Toll BrothersFoundation PlasterAug 27, 202615d overdueUnassigned$450⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-11 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l
106-Canyon Park-Tri Pointe HomesPaper/WireAug 29, 202613d overdueUnassigned2026-09-03$117⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-14 ✅ 2026-08-20:
130-Montreux-DR HortonSoffit/FasciaSep 1, 202610d overdueUnassigned$608✅ 2026-08-28: Material Delay - Missing all the siding - Alex 2026-09-03
102-Canton Ridge-RichmondSpecial CorbelsSep 1, 202610d overdueUnassigned$50
143-Montreux-DR HortonRockSep 2, 20269d overdueUnassigned2026-08-27$706⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-11 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
143-Montreux-DR HortonScratch CoatSep 2, 20269d overdueUnassigned$83⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-11 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
16122-Harmony-Meritage HomesSoffit/FasciaSep 4, 20267d overdueUnassigned$438
2021-Wildflower-Toll BrothersRockSep 5, 20266d overdueUnassigned$1,893⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan
1027-Harmony Ridge-EdgeRockSep 5, 20266d overdueUnassigned2026-09-08$187
1027-Harmony Ridge-EdgeScratch CoatSep 5, 20266d overdueUnassigned$50
2021-Wildflower-Toll BrothersStucco BrownSep 5, 20266d overdueUnassigned$129⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan
1027-Harmony Ridge-EdgeStucco BrownSep 5, 20266d overdueUnassigned$1,117
Units 975-979-Anderson Farms Townhomes-IvoryBrickSep 9, 20262d overdueUnassigned2026-09-01$14,239
254-Canton Ridge-RichmondBrickSep 9, 20262d overdueUnassigned2026-09-09$1,441
102-Canton Ridge-RichmondRockSep 9, 20262d overdueUnassigned2026-09-01$1,094
135-Auburn Springs-EdgeRockSep 9, 20262d overdueUnassigned2026-09-04$1,036✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11
135-Auburn Springs-EdgeScratch CoatSep 9, 20262d overdueUnassigned$150✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11
234-Viridian Plus-DR HortonSet ScaffSep 9, 20262d overdueUnassigned$763
340-Viridian-DR HortonSet ScaffSep 9, 20262d overdueUnassigned$606
16121-Harmony-Meritage HomesSoffit/FasciaSep 9, 20262d overdueUnassigned$452
26-Lakeview Fields-Keystone ConstructionBrickSep 10, 20261d overdueUnassigned2026-08-11$934✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28
Roundabout Wall Phase 4-Viridian Townhomes-DR HortonPaper/WireSep 10, 20261d overdueUnassigned$260
110-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20261d overdueUnassigned2026-09-01$173
109-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20261d overdueUnassigned2026-09-02$117
2024-Wildflower-Toll BrothersRemove ScaffSep 10, 20261d overdueUnassigned$595✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-08-31
422-Viridian-DR HortonRockSep 10, 20261d overdueUnassigned2026-09-08$663
26-Lakeview Fields-Keystone ConstructionScratch CoatSep 10, 20261d overdueUnassigned$98✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28
814-Broadview Shores-IvorySidingSep 10, 20261d overdueUnassigned2026-09-10$3,491⭕ 2026-09-09: Failed inspection, hold on scratch coat. - Manuel Est End: 2026-09-11
26-Tanner Flats-IvoryStucco BrownSep 10, 20261d overdueUnassigned$1,136
25-Lakeview Fields-Keystone ConstructionBrickSep 11, 2026todayUnassigned2026-08-28$644
Units 136-140-Regency at Harmony Place-WoodsideRemove ScaffSep 11, 2026todayUnassigned$996
45-Tanner Flats-IvoryRemove ScaffSep 11, 2026todayUnassigned$386
527-River Point-EdgeRockSep 11, 2026todayUnassigned2026-09-10$1,290
726-Highridge-EdgeRockSep 11, 2026todayUnassigned2026-09-03$627
527-River Point-EdgeScratch CoatSep 11, 2026todayUnassigned$187
25-Lakeview Fields-Keystone ConstructionScratch CoatSep 11, 2026todayUnassigned$67
16118-Harmony-Meritage HomesSidingSep 11, 2026todayUnassigned$3,863
25-Lakeview Fields-Keystone ConstructionSidingSep 11, 2026todayUnassigned2026-09-02$1,264
16119-Harmony-Meritage HomesSoffit/FasciaSep 11, 2026todayUnassigned$418
16118-Harmony-Meritage HomesSoffit/FasciaSep 11, 2026todayUnassigned$418
107-Vista at Harmony Place-WoodsideStucco ColorSep 12, 2026in 1dUnassigned$768
248-Canton Ridge-RichmondStucco ColorSep 12, 2026in 1dUnassigned2026-09-10$874
434-Viridian-DR HortonStucco ColorSep 13, 2026in 2dUnassigned$1,212✅
314-Viridian-DR HortonSet ScaffSep 14, 2026in 3dUnassigned$627
2227-Wildflower-EdgeSet ScaffSep 14, 2026in 3dUnassigned$758
420-Viridian-DR HortonSet ScaffSep 14, 2026in 3dUnassigned$681
711-Ridgehorne-EdgeSet ScaffSep 14, 2026in 3dUnassigned$747
1021-Harmony Ridge-EdgeSet ScaffSep 14, 2026in 3dUnassigned$786
718-Highridge-EdgeSet ScaffSep 14, 2026in 3dUnassigned$831
108-Auburn Springs-EdgeSet ScaffSep 14, 2026in 3dUnassigned$930
Units 975-979-Anderson Farms Townhomes-IvoryStucco ColorSep 14, 2026in 3dUnassigned$1,760
254-Canton Ridge-RichmondStucco ColorSep 14, 2026in 3dUnassigned$1,165
102-Canton Ridge-RichmondStucco ColorSep 14, 2026in 3dUnassigned$1,045
109-Vista at Harmony Place-WoodsideStucco ColorSep 14, 2026in 3dUnassigned$802
717-Highridge-EdgeStucco ColorSep 14, 2026in 3dUnassigned$960
Bldg 56-Harmony Ridge-EdgeSet ScaffSep 15, 2026in 4dUnassigned$1,906
115-Auburn Springs-EdgeSet ScaffSep 15, 2026in 4dUnassigned$780
Bldg 49-Viridian Townhomes-DR HortonStucco ColorSep 15, 2026in 4dUnassigned$1,560
339-Viridian-DR HortonSet ScaffSep 16, 2026in 5dUnassigned$574
Bldg 37-Highridge-EdgeInsl Foam 1Sep 17, 2026in 6dUnassigned$115
Bldg 37-Highridge-EdgeInsl WallsSep 17, 2026in 6dUnassigned$912
523-River Point-EdgeSet ScaffSep 17, 2026in 6dUnassigned$745
147-Auburn Springs-EdgeSet ScaffSep 17, 2026in 6dUnassigned$723
711-Highridge-EdgeSet ScaffSep 17, 2026in 6dUnassigned$561
2212-Wildflower-EdgeSet ScaffSep 18, 2026in 7dUnassigned$660
133-Auburn Springs-EdgeSet ScaffSep 18, 2026in 7dUnassigned$991
246-Viridian Plus-DR HortonSet ScaffSep 18, 2026in 7dUnassigned$784
2228-Wildflower-EdgeSet ScaffSep 18, 2026in 7dUnassigned$807
Bldg 37-Highridge-EdgeSet ScaffSep 18, 2026in 7dUnassigned$1,104
518-River Point-EdgeSet ScaffSep 21, 2026in 10dUnassigned$583
525-River Point-EdgeSet ScaffSep 21, 2026in 10dUnassigned$671
1030-Harmony Ridge-EdgeSet ScaffSep 21, 2026in 10dUnassigned$756
721-Ridgehorne-EdgeSet ScaffSep 22, 2026in 11dUnassigned$530
1031-Harmony Ridge-EdgeSet ScaffSep 23, 2026in 12dUnassigned$712
519-River Point-EdgeSet ScaffSep 23, 2026in 12dUnassigned$693
710-Highridge-EdgeSet ScaffSep 23, 2026in 12dUnassigned$668
1008-Harmony Ridge-EdgeSet ScaffSep 24, 2026in 13dUnassigned$759
732-Ridgehorne-EdgeSet ScaffSep 24, 2026in 13dUnassigned$661
Bldg 38-Highridge-EdgeSet ScaffSep 28, 2026in 17dUnassigned$1,104
2234-Wildflower-EdgeSet ScaffSep 29, 2026in 18dUnassigned$782
Bldg 59-Harmony Ridge-EdgeSet ScaffSep 29, 2026in 18dUnassigned$1,480
Bldg 39-Highridge-EdgeInsl AtticOct 9, 2026in 28dUnassigned$80
Bldg 37-Highridge-EdgeInsl AtticNov 3, 2026in 53dUnassigned$80
Salt Lake — 32 tasks ready for assignment · 3 overdue · $31,644
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
153-Pierson Farms-McArthurRockSep 9, 20262d overdueUnassigned2026-09-01$871
Bldg 9-Taylor Villas-EdgeStucco ColorSep 9, 20262d overdueUnassigned$1,948✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
256-Boulder at Sky Ranch-WoodsidePaper/WireSep 10, 20261d overdueUnassigned$939
126-Capitol Reef-EdgeRockSep 11, 2026todayUnassigned2026-09-04$502
126-Capitol Reef-EdgeScratch CoatSep 11, 2026todayUnassigned$73
1004-Northstar Ranch-Destination HomesSidingSep 11, 2026todayUnassigned$1,265⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesSidingSep 11, 2026todayUnassigned$1,921⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
1004-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 2026todayUnassigned$597⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 2026todayUnassigned$686⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
Bldg 202-Mountain Ridge-EdgeSoffit/FasciaSep 11, 2026todayUnassigned$1,420
1004-Northstar Ranch-Destination HomesStucco BrownSep 11, 2026todayUnassigned$1,157⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesStucco BrownSep 11, 2026todayUnassigned2026-08-27$1,134⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
Bldg 201-Mountain Ridge-EdgeStucco ColorSep 12, 2026in 1dUnassigned$1,854
Bldg 202-Mountain Ridge-EdgeStucco ColorSep 12, 2026in 1dUnassigned$1,620
153-Pierson Farms-McArthurStucco ColorSep 14, 2026in 3dUnassigned$1,069
2929-Mountain Ridge-EdgeSet ScaffSep 15, 2026in 4dUnassigned$577
Units 508-509-Daybreak Duets-Destination HomesStucco ColorSep 15, 2026in 4dUnassigned$1,941
111-Creek Ridge Cove-RichmondStucco ColorSep 15, 2026in 4dUnassigned$1,251✅ 2026-08-28: 3 Days - Can’t finish lath and housewrap until back sliding door gets installed - Arturo 2026-09-02
Units 539-540-Daybreak Lexington Townhomes-Destination HomesStucco ColorSep 16, 2026in 5dUnassigned$1,571✅ 2026-08-25: 3 Days - Housewrap and paper and wire delay. Missing drywall windows and sheeting on beam - Facundo 2026-08-28
2916-Mountain Ridge-EdgeSet ScaffSep 17, 2026in 6dUnassigned$756
Bldg 18-Solari-EdgeSet ScaffSep 18, 2026in 7dUnassigned$1,570
Bldg 19-Solari-EdgeSet ScaffSep 18, 2026in 7dUnassigned$1,570
Bldg 203-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 11dUnassigned$1,474
2931-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 11dUnassigned$712
Bldg 204-Mountain Ridge-EdgeSet ScaffSep 24, 2026in 13dUnassigned$1,501
2927-Mountain Ridge-EdgeSet ScaffSep 25, 2026in 14dUnassigned$708
Bldg 9-Taylor Villas-EdgeInsl AtticSep 29, 2026in 18dUnassigned$179✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
Bldg 1-Solari-EdgeInsl AtticOct 1, 2026in 20dUnassigned$143✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19
Bldg 208-Mountain Ridge-EdgeInsl AtticOct 14, 2026in 33dUnassigned$144
Bldg 202-Mountain Ridge-EdgeInsl AtticOct 20, 2026in 39dUnassigned$143
Bldg 22-Solari-EdgeInsl AtticOct 26, 2026in 45dUnassigned$160
Bldg 19-Solari-EdgeInsl AtticNov 3, 2026in 53dUnassigned$192
St. George — 14 tasks ready for assignment · 7 overdue · $23,340
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
35-Legacy at Sand Hollow-VisionaryStucco ColorSep 7, 20264d overdueUnassigned2026-09-09$2,569
4156-Long Valley Rambler-DR HortonStucco ColorSep 9, 20262d overdueUnassigned$1,303
52-Zion Shores-Split RockRockSep 10, 20261d overdueUnassigned$7,062
7-Chelsey-DR HortonSet ScaffSep 10, 20261d overdueUnassigned$557
413-The Preserve at Alaia-VisionaryStucco ColorSep 10, 20261d overdueUnassigned$2,163
37-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20261d overdueUnassigned$100
33-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20261d overdueUnassigned$100
37-Legacy at Sand Hollow-VisionaryHousewrapSep 11, 2026todayUnassigned$181
4294-Long Valley-DR HortonHousewrapSep 11, 2026todayUnassigned$151
33-Legacy at Sand Hollow-VisionaryHousewrapSep 11, 2026todayUnassigned$50
32-Legacy at Sand Hollow-VisionaryStucco ColorSep 12, 2026in 1dUnassigned$2,126
323-Finley Farms-RichmondStucco ColorSep 13, 2026in 2dUnassigned$3,068
104-La Spazio-LennarStucco ColorSep 13, 2026in 2dUnassigned2026-09-08$2,146
105-La Spazio-LennarStucco ColorSep 14, 2026in 3dUnassigned$1,763
Commercial — 9 tasks ready for assignment · 9 overdue · $39,571
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-RimrockScratch CoatJul 16, 202657d overdueUnassigned$1,811
Bldg D-Residence at Millcreek-RimrockRemove ScaffAug 6, 202636d overdueUnassigned$7,542
Bldg RU-1-ARA Southwest-Campbell ConstructionPenetration SealingAug 15, 202627d overdueUnassigned$0
Bldg C-Residence at Millcreek-RimrockPaintAug 24, 202618d overdueUnassigned$1,838
White Dome Chapel-St George-Grass CreekSet ScaffAug 27, 202615d overdueUnassigned$57
Bldg RU-1-ARA Southwest-Campbell ConstructionEIFS Weather BarrierSep 1, 202610d overdueUnassigned$1,843
Bldg D-Residence at Millcreek-RimrockRockSep 9, 20262d overdueUnassigned$15,588
Bldg D-Residence at Millcreek-RimrockScratch CoatSep 9, 20262d overdueUnassigned$2,008
Bldg D-Residence at Millcreek-RimrockStucco BrownSep 9, 20262d overdueUnassigned$8,885
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-UnknownMisc. WorkAug 17, 202625d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 291 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: