Every division. Tasks with an assignment date set but no team assigned and not yet completed.
Generated Sep 11, 2026 · Go to the current version →
This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.
● All 6 divisions, not just yours — the
division scoping is removed.
● No 7-day cap. The division view only shows assignments due
inside a week; this carries the whole book — the overdue tail reaching back to
Jul 16, 2026 and forward assignments out to Nov 3, 2026.
● Delayed assignments are not excluded. The division view drops
tasks flagged Task Assignment Is Delayed; that field is not available to this
report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to
active jobs, so an unassigned task on a finaled job shows in your division view and
not here — the one direction where your view is larger than this
report.
Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.
Generated Sep 11, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 14,186 task records pulled, 228 matched the filter · assignment dates Jul 16, 2026 to Nov 3, 2026
past assignment date due today or upcoming
Click any number to see the tasks behind it. Esc closes.
| Division | Overdue 30+ days | Overdue 8-30 days | Overdue 1-7 days | Due today | Next 7 days | Beyond 7 days | Total |
|---|---|---|---|---|---|---|---|
| Ogden | · | ||||||
| Orem | · | ||||||
| Salt Lake | · | · | |||||
| St. George | · | · | · | ||||
| Commercial | · | · | · | ||||
| Corporate | · | · | · | · | · | ||
| All divisions |
Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 29 task types.
Click any number to see the tasks behind it. Esc closes.
| Division | Insl Foam 1 | Insl Walls | Penetration Sealing | Window Pre Wrap | Set Scaff | Housewrap | Set Brick Scaff | Special Corbels | Paper/Wire | EIFS Weather Barrier | Stucco Brown | Scratch Coat | Paint | Siding | Watering | Rock | Brick | Vinyl | Soffit/Fascia | Brown & Mesh | Gutters | Remove Scaff | Shutters | Stucco Color | Scaff Pickup | VPO Work | Misc. Work | Insl Attic | Foundation Plaster | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | · | · | · | · | · | · | · | |||||||||||||||||||||
| Orem | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||||||||||||
| Salt Lake | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||||||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||||||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions |
Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 183 of 228 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.
Click any number to see the tasks — or the crews — behind it. Esc closes.
Tasks needing assignment
| Division | Scaffolding | Stucco Color | Siding | Rock | Soffit | Insulation | Gutters | Stucco Brown | Paint | Brick | Paper/Wire | Housewrap | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | ||||||||||||||
| Orem | · | · | · | · | · | |||||||||||
| Salt Lake | · | · | · | · | · | · | ||||||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | |||||
| Commercial | · | · | · | · | · | · | · | · | ||||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions | · |
Crews with a hand up — available to that division
| Division | Scaffolding | Stucco Color | Siding | Rock | Soffit | Insulation | Gutters | Stucco Brown | Paint | Brick | Paper/Wire | Housewrap | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| Orem | · | · | · | · | · | · | · | · | · | |||||||
| Salt Lake | · | · | · | · | · | · | · | · | · | · | · | · | ||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | · | ||||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| All divisions | · | · | · | · | · | · | · | · |
20 crews company-wide have a hand up, counted once per division they cover (22 crew-division slots, of which 2 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.
Click a division to see the underlying tasks, oldest assignment date first.
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 108-Red Hill-Ivory | Set Brick Scaff | Aug 12, 2026 | 30d overdue | Unassigned | $40 | ||
| 206-Fremont Meadows-Sterling Homes | Scratch Coat | Aug 13, 2026 | 29d overdue | Unassigned | $50 | ||
| 71-Brookfield-Lennar | Gutters | Aug 24, 2026 | 18d overdue | Unassigned | $167 | ||
| 63-Brookfield-Lennar | Gutters | Aug 24, 2026 | 18d overdue | Unassigned | $236 | ||
| 106-Red Hill-Ivory | Set Brick Scaff | Aug 24, 2026 | 18d overdue | Unassigned | $0 | ||
| 108-Red Hill-Ivory | Scratch Coat | Aug 25, 2026 | 17d overdue | Unassigned | $50 | ||
| Bldg 6-Midtown Village-DR Horton | Set Brick Scaff | Aug 26, 2026 | 16d overdue | Unassigned | $0 | ⭕ 2026-09-08: not ready for lathe is missing the metal cap - George Est End: 2026-09-11 | |
| 1523-Cranefield Estates-Ivory | Set Brick Scaff | Aug 26, 2026 | 16d overdue | Unassigned | $134 | ||
| 176-Mountain Gate-Sierra Homes | Siding | Aug 27, 2026 | 15d overdue | Unassigned | $50 | ||
| 106-Red Hill-Ivory | Brick | Aug 28, 2026 | 14d overdue | Unassigned | 2026-08-26 | $50 | |
| Bldg 2-Railrunner-DAI Construction | Siding | Aug 28, 2026 | 14d overdue | Unassigned | 2026-08-26 | $782 | ✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0 |
| Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction Group | Rock | Aug 31, 2026 | 11d overdue | Unassigned | 2026-08-26 | $635 | ⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15 |
| 102-Meadows at Hyde Park-Visionary | Siding | Aug 31, 2026 | 11d overdue | Unassigned | $1,261 | ||
| 338-Sugar Creek-Visionary | Siding | Sep 1, 2026 | 10d overdue | Unassigned | $489 | ||
| 4-Heritage Parkway-Sierra Homes | Remove Scaff | Sep 2, 2026 | 9d overdue | Unassigned | $13 | ✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04 | |
| 603-Vineyard-Visionary | Scratch Coat | Sep 2, 2026 | 9d overdue | Unassigned | $74 | ||
| 723-Ridgeline Park-Visionary | Siding | Sep 2, 2026 | 9d overdue | Unassigned | 2026-08-26 | $1,603 | ✅ 2026-09-02: -1 Days - Can’t start siding because front porch cap is not poured - Ronnie 2026-09-01 |
| 821-Ridgeline Park-Visionary | Siding | Sep 2, 2026 | 9d overdue | Unassigned | 2026-08-26 | $941 | |
| 102-Village at Fox Meadows-Visionary | Set Scaff | Sep 3, 2026 | 8d overdue | Unassigned | $446 | ✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03 | |
| 102-Village at Fox Meadows-Visionary | Siding | Sep 3, 2026 | 8d overdue | Unassigned | 2026-09-04 | $1,217 | ✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03 |
| 49-Mountainside Estates-DR Horton | VPO Work | Sep 4, 2026 | 7d overdue | Unassigned | $60 | We need to fix the siding and add flashing on the font stoop | |
| SF 7-Flint Acres-Henry Walker Homes | Scratch Coat | Sep 5, 2026 | 6d overdue | Unassigned | $331 | ||
| 227-Bristol Farms-Regal Homes | Shutters | Sep 5, 2026 | 6d overdue | Unassigned | 2026-09-05 | $50 | |
| 17-Sunset Ridges-Sierra Homes | Siding | Sep 7, 2026 | 4d overdue | Unassigned | 2026-08-26 | $261 | ✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24 |
| 17-Sunset Ridges-Sierra Homes | Vinyl | Sep 7, 2026 | 4d overdue | Unassigned | 2026-07-15 | $1,819 | ✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24 |
| 1707-Cranefield Estates-Ivory | Gutters | Sep 8, 2026 | 3d overdue | Unassigned | $360 | ||
| 2-Brynlee Acres-Hamlet | Stucco Color | Sep 8, 2026 | 3d overdue | Unassigned | $692 | ||
| 176-Mountain Gate-Sierra Homes | Vinyl | Sep 8, 2026 | 3d overdue | Unassigned | $671 | ||
| SF 6-Flint Acres-Henry Walker Homes | Paint | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-05 | $1,166 | |
| 11-Heritage Parkway-Sierra Homes | Paint | Sep 9, 2026 | 2d overdue | Unassigned | $580 | ✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07 | |
| 821-Ridgeline Park-Visionary | Rock | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-01 | $483 | |
| 229-Bristol Farms-Regal Homes | Shutters | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-05 | $100 | |
| 339-Sugar Creek-Visionary | Siding | Sep 9, 2026 | 2d overdue | Unassigned | $364 | ||
| Bldg L-Sugar Creek Townhomes-Visionary | Siding | Sep 9, 2026 | 2d overdue | Unassigned | 2026-08-10 | $6,419 | |
| 17-Sunset Ridges-Sierra Homes | Soffit/Fascia | Sep 9, 2026 | 2d overdue | Unassigned | $650 | ✅ 2026-07-01: 17 Days - The it’s still don’t finished - Jose 2026-07-24 | |
| 1709-Cranefield Estates-Ivory | Stucco Color | Sep 9, 2026 | 2d overdue | Unassigned | $790 | ||
| Bldg 2-Railrunner-DAI Construction | Vinyl | Sep 9, 2026 | 2d overdue | Unassigned | $9,494 | ✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0 | |
| 116-Meadows at Hyde Park-Visionary | Brick | Sep 10, 2026 | 1d overdue | Unassigned | $1,723 | ||
| 116-Meadows at Hyde Park-Visionary | Brown & Mesh | Sep 10, 2026 | 1d overdue | Unassigned | $1,000 | ||
| 102-Legends Crossing-Visionary | Paint | Sep 10, 2026 | 1d overdue | Unassigned | $102 | ||
| 103-Legends Crossing-Visionary | Paper/Wire | Sep 10, 2026 | 1d overdue | Unassigned | $50 | ||
| 323-Stagecoach Estates-McArthur | Remove Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $351 | ||
| 332-Riverside Estates-Fieldstone Homes | Remove Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $401 | ✅ 2026-08-03: Material Delay - - George 2026-08-17 | |
| 9-Crested Peaks-Ivory | Rock | Sep 10, 2026 | 1d overdue | Unassigned | 2026-08-26 | $4,768 | |
| 116-Meadows at Hyde Park-Visionary | Scratch Coat | Sep 10, 2026 | 1d overdue | Unassigned | $121 | ||
| 9-Crested Peaks-Ivory | Scratch Coat | Sep 10, 2026 | 1d overdue | Unassigned | $646 | ||
| 503-Vineyard-Visionary | Set Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $490 | ||
| 515-Vineyard-Visionary | Set Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $0 | ||
| 126-Red Hill-Ivory | Set Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $36 | ||
| 515-Vineyard-Visionary | Siding | Sep 10, 2026 | 1d overdue | Unassigned | $4,879 | ||
| 503-Vineyard-Visionary | Siding | Sep 10, 2026 | 1d overdue | Unassigned | $1,338 | ||
| 4-Brynlee Acres-Hamlet | Siding | Sep 10, 2026 | 1d overdue | Unassigned | 2026-08-26 | $888 | |
| 521-Vineyard-Visionary | Siding | Sep 10, 2026 | 1d overdue | Unassigned | $714 | ||
| 12-Mountainside Estates-DR Horton | Soffit/Fascia | Sep 10, 2026 | 1d overdue | Unassigned | $769 | ||
| 107-Red Hill-Ivory | Soffit/Fascia | Sep 10, 2026 | 1d overdue | Unassigned | $554 | ||
| 108-Red Hill-Ivory | Soffit/Fascia | Sep 10, 2026 | 1d overdue | Unassigned | $553 | ||
| 115-Three Farms Jenkins Fields-Ivory | Soffit/Fascia | Sep 10, 2026 | 1d overdue | Unassigned | $546 | ||
| 102-Meadows at Hyde Park-Visionary | Brick | Sep 11, 2026 | today | Unassigned | $736 | ||
| 102-Meadows at Hyde Park-Visionary | Brown & Mesh | Sep 11, 2026 | today | Unassigned | $1,390 | ||
| 253-Westwood Estates-Meritage Homes | Gutters | Sep 11, 2026 | today | Unassigned | $464 | ||
| 254-Westwood Estates-Meritage Homes | Gutters | Sep 11, 2026 | today | Unassigned | $287 | ||
| Bldg U-Village at Fox Meadows Townhomes-Visionary | Gutters | Sep 11, 2026 | today | Unassigned | $1,001 | ||
| 3-Brynlee Acres-Hamlet | Gutters | Sep 11, 2026 | today | Unassigned | $248 | ||
| 12-Mountainside Estates-DR Horton | Gutters | Sep 11, 2026 | today | Unassigned | $262 | ||
| 1708-Cranefield Estates-Ivory | Gutters | Sep 11, 2026 | today | Unassigned | $266 | ||
| 330-Riverside Estates-Fieldstone Homes | Gutters | Sep 11, 2026 | today | Unassigned | $321 | ||
| 126-Red Hill-Ivory | Housewrap | Sep 11, 2026 | today | Unassigned | $473 | ||
| 2-Brynlee Acres-Hamlet | Paint | Sep 11, 2026 | today | Unassigned | $284 | ||
| 609-Village at Fox Meadows-Visionary | Paint | Sep 11, 2026 | today | Unassigned | $583 | ||
| Bldg G-Legends Crossing Townhomes-Visionary | Paint | Sep 11, 2026 | today | Unassigned | $187 | ||
| 6-Heritage Parkway-Sierra Homes | Remove Scaff | Sep 11, 2026 | today | Unassigned | $9 | ||
| 108-Stagecoach Estates-McArthur | Rock | Sep 11, 2026 | today | Unassigned | $906 | ||
| 501-Legacy Park-Ivory | Scaff Pickup | Sep 11, 2026 | today | Unassigned | $0 | Trailer ready for pick up | |
| 108-Stagecoach Estates-McArthur | Scratch Coat | Sep 11, 2026 | today | Unassigned | $107 | ||
| 102-Meadows at Hyde Park-Visionary | Scratch Coat | Sep 11, 2026 | today | Unassigned | $77 | ||
| 609-Village at Fox Meadows-Visionary | Scratch Coat | Sep 11, 2026 | today | Unassigned | $50 | ||
| 108-Stagecoach Estates-McArthur | Siding | Sep 11, 2026 | today | Unassigned | 2026-09-10 | $369 | |
| 3-Brynlee Acres-Hamlet | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $796 | ||
| 108-Stagecoach Estates-McArthur | Stucco Brown | Sep 11, 2026 | today | Unassigned | $1,069 | ||
| 11-Mountainside Estates-DR Horton | Stucco Color | Sep 11, 2026 | today | Unassigned | $1,115 | ||
| 4-Brynlee Acres-Hamlet | Watering | Sep 11, 2026 | today | Unassigned | $78 | ||
| 520-Vineyard-Visionary | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | 2026-09-08 | $518 | ✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24 |
| 609-Village at Fox Meadows-Visionary | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $786 | ||
| 821-Ridgeline Park-Visionary | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $452 | ||
| 115-Meadows at Hyde Park-Visionary | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $867 | ||
| 4-Brynlee Acres-Hamlet | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | $806 | ||
| 603-Vineyard-Visionary | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | 2026-09-08 | $1,139 | |
| 1523-Cranefield Estates-Ivory | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | $520 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 47-Lakeview Fields-Keystone Construction | Misc. Work | Aug 25, 2026 | 17d overdue | Unassigned | $60 | Gutter was damaged during scaffolding removal and needs to be replaced. | |
| 2014-Wildflower-Toll Brothers | Foundation Plaster | Aug 27, 2026 | 15d overdue | Unassigned | $450 | ⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-11 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l | |
| 106-Canyon Park-Tri Pointe Homes | Paper/Wire | Aug 29, 2026 | 13d overdue | Unassigned | 2026-09-03 | $117 | ⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-14 ✅ 2026-08-20: |
| 130-Montreux-DR Horton | Soffit/Fascia | Sep 1, 2026 | 10d overdue | Unassigned | $608 | ✅ 2026-08-28: Material Delay - Missing all the siding - Alex 2026-09-03 | |
| 102-Canton Ridge-Richmond | Special Corbels | Sep 1, 2026 | 10d overdue | Unassigned | $50 | ||
| 143-Montreux-DR Horton | Rock | Sep 2, 2026 | 9d overdue | Unassigned | 2026-08-27 | $706 | ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-11 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - |
| 143-Montreux-DR Horton | Scratch Coat | Sep 2, 2026 | 9d overdue | Unassigned | $83 | ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-11 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - | |
| 16122-Harmony-Meritage Homes | Soffit/Fascia | Sep 4, 2026 | 7d overdue | Unassigned | $438 | ||
| 2021-Wildflower-Toll Brothers | Rock | Sep 5, 2026 | 6d overdue | Unassigned | $1,893 | ⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan | |
| 1027-Harmony Ridge-Edge | Rock | Sep 5, 2026 | 6d overdue | Unassigned | 2026-09-08 | $187 | |
| 1027-Harmony Ridge-Edge | Scratch Coat | Sep 5, 2026 | 6d overdue | Unassigned | $50 | ||
| 2021-Wildflower-Toll Brothers | Stucco Brown | Sep 5, 2026 | 6d overdue | Unassigned | $129 | ⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan | |
| 1027-Harmony Ridge-Edge | Stucco Brown | Sep 5, 2026 | 6d overdue | Unassigned | $1,117 | ||
| Units 975-979-Anderson Farms Townhomes-Ivory | Brick | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-01 | $14,239 | |
| 254-Canton Ridge-Richmond | Brick | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-09 | $1,441 | |
| 102-Canton Ridge-Richmond | Rock | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-01 | $1,094 | |
| 135-Auburn Springs-Edge | Rock | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-04 | $1,036 | ✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11 |
| 135-Auburn Springs-Edge | Scratch Coat | Sep 9, 2026 | 2d overdue | Unassigned | $150 | ✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11 | |
| 234-Viridian Plus-DR Horton | Set Scaff | Sep 9, 2026 | 2d overdue | Unassigned | $763 | ||
| 340-Viridian-DR Horton | Set Scaff | Sep 9, 2026 | 2d overdue | Unassigned | $606 | ||
| 16121-Harmony-Meritage Homes | Soffit/Fascia | Sep 9, 2026 | 2d overdue | Unassigned | $452 | ||
| 26-Lakeview Fields-Keystone Construction | Brick | Sep 10, 2026 | 1d overdue | Unassigned | 2026-08-11 | $934 | ✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28 |
| Roundabout Wall Phase 4-Viridian Townhomes-DR Horton | Paper/Wire | Sep 10, 2026 | 1d overdue | Unassigned | $260 | ||
| 110-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 1d overdue | Unassigned | 2026-09-01 | $173 | |
| 109-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 1d overdue | Unassigned | 2026-09-02 | $117 | |
| 2024-Wildflower-Toll Brothers | Remove Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $595 | ✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-08-31 | |
| 422-Viridian-DR Horton | Rock | Sep 10, 2026 | 1d overdue | Unassigned | 2026-09-08 | $663 | |
| 26-Lakeview Fields-Keystone Construction | Scratch Coat | Sep 10, 2026 | 1d overdue | Unassigned | $98 | ✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28 | |
| 814-Broadview Shores-Ivory | Siding | Sep 10, 2026 | 1d overdue | Unassigned | 2026-09-10 | $3,491 | ⭕ 2026-09-09: Failed inspection, hold on scratch coat. - Manuel Est End: 2026-09-11 |
| 26-Tanner Flats-Ivory | Stucco Brown | Sep 10, 2026 | 1d overdue | Unassigned | $1,136 | ||
| 25-Lakeview Fields-Keystone Construction | Brick | Sep 11, 2026 | today | Unassigned | 2026-08-28 | $644 | |
| Units 136-140-Regency at Harmony Place-Woodside | Remove Scaff | Sep 11, 2026 | today | Unassigned | $996 | ||
| 45-Tanner Flats-Ivory | Remove Scaff | Sep 11, 2026 | today | Unassigned | $386 | ||
| 527-River Point-Edge | Rock | Sep 11, 2026 | today | Unassigned | 2026-09-10 | $1,290 | |
| 726-Highridge-Edge | Rock | Sep 11, 2026 | today | Unassigned | 2026-09-03 | $627 | |
| 527-River Point-Edge | Scratch Coat | Sep 11, 2026 | today | Unassigned | $187 | ||
| 25-Lakeview Fields-Keystone Construction | Scratch Coat | Sep 11, 2026 | today | Unassigned | $67 | ||
| 16118-Harmony-Meritage Homes | Siding | Sep 11, 2026 | today | Unassigned | $3,863 | ||
| 25-Lakeview Fields-Keystone Construction | Siding | Sep 11, 2026 | today | Unassigned | 2026-09-02 | $1,264 | |
| 16119-Harmony-Meritage Homes | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $418 | ||
| 16118-Harmony-Meritage Homes | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $418 | ||
| 107-Vista at Harmony Place-Woodside | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | $768 | ||
| 248-Canton Ridge-Richmond | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | 2026-09-10 | $874 | |
| 434-Viridian-DR Horton | Stucco Color | Sep 13, 2026 | in 2d | Unassigned | $1,212 | ✅ | |
| 314-Viridian-DR Horton | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $627 | ||
| 2227-Wildflower-Edge | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $758 | ||
| 420-Viridian-DR Horton | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $681 | ||
| 711-Ridgehorne-Edge | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $747 | ||
| 1021-Harmony Ridge-Edge | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $786 | ||
| 718-Highridge-Edge | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $831 | ||
| 108-Auburn Springs-Edge | Set Scaff | Sep 14, 2026 | in 3d | Unassigned | $930 | ||
| Units 975-979-Anderson Farms Townhomes-Ivory | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $1,760 | ||
| 254-Canton Ridge-Richmond | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $1,165 | ||
| 102-Canton Ridge-Richmond | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $1,045 | ||
| 109-Vista at Harmony Place-Woodside | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $802 | ||
| 717-Highridge-Edge | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $960 | ||
| Bldg 56-Harmony Ridge-Edge | Set Scaff | Sep 15, 2026 | in 4d | Unassigned | $1,906 | ||
| 115-Auburn Springs-Edge | Set Scaff | Sep 15, 2026 | in 4d | Unassigned | $780 | ||
| Bldg 49-Viridian Townhomes-DR Horton | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | $1,560 | ||
| 339-Viridian-DR Horton | Set Scaff | Sep 16, 2026 | in 5d | Unassigned | $574 | ||
| Bldg 37-Highridge-Edge | Insl Foam 1 | Sep 17, 2026 | in 6d | Unassigned | $115 | ||
| Bldg 37-Highridge-Edge | Insl Walls | Sep 17, 2026 | in 6d | Unassigned | $912 | ||
| 523-River Point-Edge | Set Scaff | Sep 17, 2026 | in 6d | Unassigned | $745 | ||
| 147-Auburn Springs-Edge | Set Scaff | Sep 17, 2026 | in 6d | Unassigned | $723 | ||
| 711-Highridge-Edge | Set Scaff | Sep 17, 2026 | in 6d | Unassigned | $561 | ||
| 2212-Wildflower-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $660 | ||
| 133-Auburn Springs-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $991 | ||
| 246-Viridian Plus-DR Horton | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $784 | ||
| 2228-Wildflower-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $807 | ||
| Bldg 37-Highridge-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $1,104 | ||
| 518-River Point-Edge | Set Scaff | Sep 21, 2026 | in 10d | Unassigned | $583 | ||
| 525-River Point-Edge | Set Scaff | Sep 21, 2026 | in 10d | Unassigned | $671 | ||
| 1030-Harmony Ridge-Edge | Set Scaff | Sep 21, 2026 | in 10d | Unassigned | $756 | ||
| 721-Ridgehorne-Edge | Set Scaff | Sep 22, 2026 | in 11d | Unassigned | $530 | ||
| 1031-Harmony Ridge-Edge | Set Scaff | Sep 23, 2026 | in 12d | Unassigned | $712 | ||
| 519-River Point-Edge | Set Scaff | Sep 23, 2026 | in 12d | Unassigned | $693 | ||
| 710-Highridge-Edge | Set Scaff | Sep 23, 2026 | in 12d | Unassigned | $668 | ||
| 1008-Harmony Ridge-Edge | Set Scaff | Sep 24, 2026 | in 13d | Unassigned | $759 | ||
| 732-Ridgehorne-Edge | Set Scaff | Sep 24, 2026 | in 13d | Unassigned | $661 | ||
| Bldg 38-Highridge-Edge | Set Scaff | Sep 28, 2026 | in 17d | Unassigned | $1,104 | ||
| 2234-Wildflower-Edge | Set Scaff | Sep 29, 2026 | in 18d | Unassigned | $782 | ||
| Bldg 59-Harmony Ridge-Edge | Set Scaff | Sep 29, 2026 | in 18d | Unassigned | $1,480 | ||
| Bldg 39-Highridge-Edge | Insl Attic | Oct 9, 2026 | in 28d | Unassigned | $80 | ||
| Bldg 37-Highridge-Edge | Insl Attic | Nov 3, 2026 | in 53d | Unassigned | $80 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 153-Pierson Farms-McArthur | Rock | Sep 9, 2026 | 2d overdue | Unassigned | 2026-09-01 | $871 | |
| Bldg 9-Taylor Villas-Edge | Stucco Color | Sep 9, 2026 | 2d overdue | Unassigned | $1,948 | ✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18 | |
| 256-Boulder at Sky Ranch-Woodside | Paper/Wire | Sep 10, 2026 | 1d overdue | Unassigned | $939 | ||
| 126-Capitol Reef-Edge | Rock | Sep 11, 2026 | today | Unassigned | 2026-09-04 | $502 | |
| 126-Capitol Reef-Edge | Scratch Coat | Sep 11, 2026 | today | Unassigned | $73 | ||
| 1004-Northstar Ranch-Destination Homes | Siding | Sep 11, 2026 | today | Unassigned | $1,265 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 | |
| 1037-Northstar Ranch-Destination Homes | Siding | Sep 11, 2026 | today | Unassigned | $1,921 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 | |
| 1004-Northstar Ranch-Destination Homes | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $597 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 | |
| 1037-Northstar Ranch-Destination Homes | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $686 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 | |
| Bldg 202-Mountain Ridge-Edge | Soffit/Fascia | Sep 11, 2026 | today | Unassigned | $1,420 | ||
| 1004-Northstar Ranch-Destination Homes | Stucco Brown | Sep 11, 2026 | today | Unassigned | $1,157 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 | |
| 1037-Northstar Ranch-Destination Homes | Stucco Brown | Sep 11, 2026 | today | Unassigned | 2026-08-27 | $1,134 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 |
| Bldg 201-Mountain Ridge-Edge | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | $1,854 | ||
| Bldg 202-Mountain Ridge-Edge | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | $1,620 | ||
| 153-Pierson Farms-McArthur | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $1,069 | ||
| 2929-Mountain Ridge-Edge | Set Scaff | Sep 15, 2026 | in 4d | Unassigned | $577 | ||
| Units 508-509-Daybreak Duets-Destination Homes | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | $1,941 | ||
| 111-Creek Ridge Cove-Richmond | Stucco Color | Sep 15, 2026 | in 4d | Unassigned | $1,251 | ✅ 2026-08-28: 3 Days - Can’t finish lath and housewrap until back sliding door gets installed - Arturo 2026-09-02 | |
| Units 539-540-Daybreak Lexington Townhomes-Destination Homes | Stucco Color | Sep 16, 2026 | in 5d | Unassigned | $1,571 | ✅ 2026-08-25: 3 Days - Housewrap and paper and wire delay. Missing drywall windows and sheeting on beam - Facundo 2026-08-28 | |
| 2916-Mountain Ridge-Edge | Set Scaff | Sep 17, 2026 | in 6d | Unassigned | $756 | ||
| Bldg 18-Solari-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $1,570 | ||
| Bldg 19-Solari-Edge | Set Scaff | Sep 18, 2026 | in 7d | Unassigned | $1,570 | ||
| Bldg 203-Mountain Ridge-Edge | Set Scaff | Sep 22, 2026 | in 11d | Unassigned | $1,474 | ||
| 2931-Mountain Ridge-Edge | Set Scaff | Sep 22, 2026 | in 11d | Unassigned | $712 | ||
| Bldg 204-Mountain Ridge-Edge | Set Scaff | Sep 24, 2026 | in 13d | Unassigned | $1,501 | ||
| 2927-Mountain Ridge-Edge | Set Scaff | Sep 25, 2026 | in 14d | Unassigned | $708 | ||
| Bldg 9-Taylor Villas-Edge | Insl Attic | Sep 29, 2026 | in 18d | Unassigned | $179 | ✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18 | |
| Bldg 1-Solari-Edge | Insl Attic | Oct 1, 2026 | in 20d | Unassigned | $143 | ✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19 | |
| Bldg 208-Mountain Ridge-Edge | Insl Attic | Oct 14, 2026 | in 33d | Unassigned | $144 | ||
| Bldg 202-Mountain Ridge-Edge | Insl Attic | Oct 20, 2026 | in 39d | Unassigned | $143 | ||
| Bldg 22-Solari-Edge | Insl Attic | Oct 26, 2026 | in 45d | Unassigned | $160 | ||
| Bldg 19-Solari-Edge | Insl Attic | Nov 3, 2026 | in 53d | Unassigned | $192 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 35-Legacy at Sand Hollow-Visionary | Stucco Color | Sep 7, 2026 | 4d overdue | Unassigned | 2026-09-09 | $2,569 | |
| 4156-Long Valley Rambler-DR Horton | Stucco Color | Sep 9, 2026 | 2d overdue | Unassigned | $1,303 | ||
| 52-Zion Shores-Split Rock | Rock | Sep 10, 2026 | 1d overdue | Unassigned | $7,062 | ||
| 7-Chelsey-DR Horton | Set Scaff | Sep 10, 2026 | 1d overdue | Unassigned | $557 | ||
| 413-The Preserve at Alaia-Visionary | Stucco Color | Sep 10, 2026 | 1d overdue | Unassigned | $2,163 | ||
| 37-Legacy at Sand Hollow-Visionary | Window Pre Wrap | Sep 10, 2026 | 1d overdue | Unassigned | $100 | ||
| 33-Legacy at Sand Hollow-Visionary | Window Pre Wrap | Sep 10, 2026 | 1d overdue | Unassigned | $100 | ||
| 37-Legacy at Sand Hollow-Visionary | Housewrap | Sep 11, 2026 | today | Unassigned | $181 | ||
| 4294-Long Valley-DR Horton | Housewrap | Sep 11, 2026 | today | Unassigned | $151 | ||
| 33-Legacy at Sand Hollow-Visionary | Housewrap | Sep 11, 2026 | today | Unassigned | $50 | ||
| 32-Legacy at Sand Hollow-Visionary | Stucco Color | Sep 12, 2026 | in 1d | Unassigned | $2,126 | ||
| 323-Finley Farms-Richmond | Stucco Color | Sep 13, 2026 | in 2d | Unassigned | $3,068 | ||
| 104-La Spazio-Lennar | Stucco Color | Sep 13, 2026 | in 2d | Unassigned | 2026-09-08 | $2,146 | |
| 105-La Spazio-Lennar | Stucco Color | Sep 14, 2026 | in 3d | Unassigned | $1,763 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Bldg C-Residence at Millcreek-Rimrock | Scratch Coat | Jul 16, 2026 | 57d overdue | Unassigned | $1,811 | ||
| Bldg D-Residence at Millcreek-Rimrock | Remove Scaff | Aug 6, 2026 | 36d overdue | Unassigned | $7,542 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | Penetration Sealing | Aug 15, 2026 | 27d overdue | Unassigned | $0 | ||
| Bldg C-Residence at Millcreek-Rimrock | Paint | Aug 24, 2026 | 18d overdue | Unassigned | $1,838 | ||
| White Dome Chapel-St George-Grass Creek | Set Scaff | Aug 27, 2026 | 15d overdue | Unassigned | $57 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | EIFS Weather Barrier | Sep 1, 2026 | 10d overdue | Unassigned | $1,843 | ||
| Bldg D-Residence at Millcreek-Rimrock | Rock | Sep 9, 2026 | 2d overdue | Unassigned | $15,588 | ||
| Bldg D-Residence at Millcreek-Rimrock | Scratch Coat | Sep 9, 2026 | 2d overdue | Unassigned | $2,008 | ||
| Bldg D-Residence at Millcreek-Rimrock | Stucco Brown | Sep 9, 2026 | 2d overdue | Unassigned | $8,885 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Cascade West Haven Warehouse-Overhead Projects (Ogden)-Unknown | Misc. Work | Aug 17, 2026 | 25d overdue | Unassigned | $0 | Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP |
Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):
Assigned Task Date is not blankTeam (Task Team) is blankCompleted Date/Time is blankTeam and Team Name agree on every record
(0 disagreements), so "no team assigned" is unambiguous.Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 291 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: