Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Sep 12, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Nov 3, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Sep 12, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 14,117 task records pulled, 237 matched the filter · assignment dates Jul 16, 2026 to Nov 3, 2026

237
Ready for assignment
133
Past assignment date
6
Divisions affected
$262,451
Unassigned task pay
58d
Oldest overdue

Ready tasks by division

024487397Orem9744 odOgden8261 odSalt Lake348 odSt. George1410 odCommercial99 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Orem·
Ogden·
Salt Lake··
St. George···
Commercial···
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 28 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionInsl Foam 1Insl WallsPenetration SealingPorch OSBWindow Pre WrapSet ScaffHousewrapSet Brick ScaffSpecial CorbelsPaper/WireEIFS Weather BarrierStucco BrownScratch CoatPaintSidingRockBrickVinylSoffit/FasciaBrown & MeshGuttersRemove ScaffShuttersStucco ColorScaff PickupMisc. WorkInsl AtticFoundation PlasterTotal
Orem··········
Ogden··········
Salt Lake····················
St. George·····················
Commercial····················
Corporate···························
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 162 of 237 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorSidingRockGuttersInsulationPaintStucco BrownSoffitPaper/WireHousewrapBrickField OpsWarrantyAny tradeTotal
Orem···
Ogden··
Salt Lake·······
St. George··········
Commercial········
Corporate··············
All divisions·

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorSidingRockGuttersInsulationPaintStucco BrownSoffitPaper/WireHousewrapBrickField OpsWarrantyAny tradeTotal
Orem·······
Ogden·············
Salt Lake···········
St. George···········
Commercial················
Corporate················
All divisions······

30 crews company-wide have a hand up, counted once per division they cover (36 crew-division slots, of which 6 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Orem — 97 tasks ready for assignment · 44 overdue · $93,795
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
47-Lakeview Fields-Keystone ConstructionMisc. WorkAug 25, 202618d overdueUnassigned$60Gutter was damaged during scaffolding removal and needs to be replaced.
2014-Wildflower-Toll BrothersFoundation PlasterAug 27, 202616d overdueUnassigned$450⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-11 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l
106-Canyon Park-Tri Pointe HomesPaper/WireAug 29, 202614d overdueUnassigned2026-09-03$117⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-14 ✅ 2026-08-20:
130-Montreux-DR HortonSoffit/FasciaSep 1, 202611d overdueUnassigned$608✅ 2026-08-28: Material Delay - Missing all the siding - Alex 2026-09-03
102-Canton Ridge-RichmondSpecial CorbelsSep 1, 202611d overdueUnassigned$50
143-Montreux-DR HortonRockSep 2, 202610d overdueUnassigned2026-08-27$706⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-14 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
143-Montreux-DR HortonScratch CoatSep 2, 202610d overdueUnassigned$83⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-14 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered -
16122-Harmony-Meritage HomesSoffit/FasciaSep 4, 20268d overdueUnassigned$438
2021-Wildflower-Toll BrothersRockSep 5, 20267d overdueUnassigned$1,893⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan
1027-Harmony Ridge-EdgeRockSep 5, 20267d overdueUnassigned2026-09-08$187
1027-Harmony Ridge-EdgeScratch CoatSep 5, 20267d overdueUnassigned$50
2021-Wildflower-Toll BrothersStucco BrownSep 5, 20267d overdueUnassigned$129⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ⭕ 2026-09-02: Brown delay - missing drywall window - good to proceed on scratch - Jonathan
Units 975-979-Anderson Farms Townhomes-IvoryBrickSep 9, 20263d overdueUnassigned2026-09-01$14,239
254-Canton Ridge-RichmondBrickSep 9, 20263d overdueUnassigned2026-09-09$1,441
102-Canton Ridge-RichmondRockSep 9, 20263d overdueUnassigned2026-09-01$1,094
135-Auburn Springs-EdgeRockSep 9, 20263d overdueUnassigned2026-09-04$1,036✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11
135-Auburn Springs-EdgeScratch CoatSep 9, 20263d overdueUnassigned$150✅ 2026-09-08: 3 Days - Columns are twisted - Harrison 2026-09-11
234-Viridian Plus-DR HortonSet ScaffSep 9, 20263d overdueUnassigned$763
340-Viridian-DR HortonSet ScaffSep 9, 20263d overdueUnassigned$606
254-Canton Ridge-RichmondSidingSep 9, 20263d overdueUnassigned2026-09-11$1,523
102-Canton Ridge-RichmondSidingSep 9, 20263d overdueUnassigned$1,169
16121-Harmony-Meritage HomesSoffit/FasciaSep 9, 20263d overdueUnassigned$452
26-Lakeview Fields-Keystone ConstructionBrickSep 10, 20262d overdueUnassigned2026-08-11$934✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28
142-Montreux-DR HortonHousewrapSep 10, 20262d overdueIn Progress2026-09-11$743✅ 2026-09-01: Material Delay - Siding material is delayed. Alside mentioned they only had partial order, they are waiting for more. - Alex 2026-09-10 ✅ 2026-08-27: 10 Days - Backsi
Roundabout Wall Phase 4-Viridian Townhomes-DR HortonPaper/WireSep 10, 20262d overdueUnassigned$260
110-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20262d overdueUnassigned2026-09-01$173⭕ 2026-09-10: Missing a few windows and inside porch framing needing to be complete. Housewrap will be delayed until those pending items are completed. - Alex Est End: 2026-09-14
109-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20262d overdueUnassigned2026-09-02$117
2024-Wildflower-Toll BrothersRemove ScaffSep 10, 20262d overdueUnassigned$595✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-08-31
26-Lakeview Fields-Keystone ConstructionScratch CoatSep 10, 20262d overdueUnassigned$98✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28
814-Broadview Shores-IvorySidingSep 10, 20262d overdueUnassigned2026-09-10$3,491✅ 2026-09-09: 2 Days - Failed inspection, hold on scratch coat. - Manuel 2026-09-11
26-Tanner Flats-IvoryStucco BrownSep 10, 20262d overdueUnassigned$1,136⭕ 2026-09-09: Hold on siding good for stucco brown - Jorge Est End: 2026-09-14
25-Lakeview Fields-Keystone ConstructionBrickSep 11, 20261d overdueUnassigned2026-08-28$644
Units 975-979-Anderson Farms Townhomes-IvoryPaintSep 11, 20261d overdueUnassigned$778
422-Viridian-DR HortonPaintSep 11, 20261d overdueUnassigned$308
Bldg 49-Viridian Townhomes-DR HortonPaintSep 11, 20261d overdueUnassigned$1,400
519-Ridgeview Cottages-IvoryPaper/WireSep 11, 20261d overdueUnassigned2026-09-10$940⭕ 2026-09-11: Need to wait for 4 way. Super told me to set scaff but not 4way - Harrison Est End: 2026-09-15
2232-Wildflower-EdgeRemove ScaffSep 11, 20261d overdueUnassigned$456
741-Broadview Shores-IvoryRemove ScaffSep 11, 20261d overdueUnassigned$368
45-Tanner Flats-IvoryRemove ScaffSep 11, 20261d overdueUnassigned$386
527-River Point-EdgeRockSep 11, 20261d overdueUnassigned2026-09-10$1,290
527-River Point-EdgeScratch CoatSep 11, 20261d overdueUnassigned$187
25-Lakeview Fields-Keystone ConstructionScratch CoatSep 11, 20261d overdueUnassigned$67
16119-Harmony-Meritage HomesSoffit/FasciaSep 11, 20261d overdueUnassigned$418
507-River Point-EdgeSoffit/FasciaSep 11, 20261d overdueUnassigned$548✅ 2026-08-31: 2 Days - Finish columns - Harrison 2026-09-02
49-Tanner Flats-IvoryRemove ScaffSep 12, 2026todayUnassigned$371
Bldg 58-Harmony Ridge-EdgeRockSep 12, 2026todayUnassigned2026-09-01$2,077
Bldg 58-Harmony Ridge-EdgeScratch CoatSep 12, 2026todayUnassigned$313
16120-Harmony-Meritage HomesSidingSep 12, 2026todayUnassigned2026-09-02$3,821
Bldg 58-Harmony Ridge-EdgeSidingSep 12, 2026todayUnassigned2026-09-02$2,402
527-River Point-EdgeSidingSep 12, 2026todayUnassigned2026-09-08$4,040
16120-Harmony-Meritage HomesSoffit/FasciaSep 12, 2026todayUnassigned$415
16122-Harmony-Meritage HomesStucco BrownSep 12, 2026todayUnassigned$160
Bldg 58-Harmony Ridge-EdgeStucco BrownSep 12, 2026todayUnassigned$3,041
107-Vista at Harmony Place-WoodsideStucco ColorSep 12, 2026todayUnassigned$768
248-Canton Ridge-RichmondStucco ColorSep 12, 2026todayUnassigned2026-09-10$874
434-Viridian-DR HortonStucco ColorSep 13, 2026in 1dUnassigned$1,212✅
314-Viridian-DR HortonSet ScaffSep 14, 2026in 2dUnassigned$627
2227-Wildflower-EdgeSet ScaffSep 14, 2026in 2dUnassigned$758
420-Viridian-DR HortonSet ScaffSep 14, 2026in 2dUnassigned$681
711-Ridgehorne-EdgeSet ScaffSep 14, 2026in 2dUnassigned$747
1021-Harmony Ridge-EdgeSet ScaffSep 14, 2026in 2dUnassigned$786
718-Highridge-EdgeSet ScaffSep 14, 2026in 2dUnassigned$831
Units 975-979-Anderson Farms Townhomes-IvoryStucco ColorSep 14, 2026in 2dUnassigned$1,760
254-Canton Ridge-RichmondStucco ColorSep 14, 2026in 2dUnassigned$1,165
102-Canton Ridge-RichmondStucco ColorSep 14, 2026in 2dUnassigned$1,045
109-Vista at Harmony Place-WoodsideStucco ColorSep 14, 2026in 2dUnassigned$802
717-Highridge-EdgeStucco ColorSep 14, 2026in 2dUnassigned$960
Bldg 56-Harmony Ridge-EdgeSet ScaffSep 15, 2026in 3dUnassigned$1,906
115-Auburn Springs-EdgeSet ScaffSep 15, 2026in 3dUnassigned$780
108-Auburn Springs-EdgeSet ScaffSep 15, 2026in 3dUnassigned$930
Bldg 49-Viridian Townhomes-DR HortonStucco ColorSep 15, 2026in 3dUnassigned$1,560
339-Viridian-DR HortonSet ScaffSep 16, 2026in 4dUnassigned$574
16118-Harmony-Meritage HomesStucco ColorSep 16, 2026in 4dUnassigned$134
726-Highridge-EdgeStucco ColorSep 16, 2026in 4dUnassigned2026-09-11$1,467
Bldg 37-Highridge-EdgeInsl Foam 1Sep 17, 2026in 5dUnassigned$115
Bldg 37-Highridge-EdgeInsl WallsSep 17, 2026in 5dUnassigned$912
523-River Point-EdgeSet ScaffSep 17, 2026in 5dUnassigned$745
147-Auburn Springs-EdgeSet ScaffSep 17, 2026in 5dUnassigned$723
711-Highridge-EdgeSet ScaffSep 17, 2026in 5dUnassigned$561
16119-Harmony-Meritage HomesStucco ColorSep 17, 2026in 5dUnassigned$118
16121-Harmony-Meritage HomesStucco ColorSep 17, 2026in 5dUnassigned$148
2212-Wildflower-EdgeSet ScaffSep 18, 2026in 6dUnassigned$660
133-Auburn Springs-EdgeSet ScaffSep 18, 2026in 6dUnassigned$991
246-Viridian Plus-DR HortonSet ScaffSep 18, 2026in 6dUnassigned$784
2228-Wildflower-EdgeSet ScaffSep 18, 2026in 6dUnassigned$807
Bldg 37-Highridge-EdgeSet ScaffSep 18, 2026in 6dUnassigned$1,104
518-River Point-EdgeSet ScaffSep 21, 2026in 9dUnassigned$583
525-River Point-EdgeSet ScaffSep 21, 2026in 9dUnassigned$671
1030-Harmony Ridge-EdgeSet ScaffSep 21, 2026in 9dUnassigned$756
721-Ridgehorne-EdgeSet ScaffSep 22, 2026in 10dUnassigned$530
1031-Harmony Ridge-EdgeSet ScaffSep 23, 2026in 11dUnassigned$712
519-River Point-EdgeSet ScaffSep 23, 2026in 11dUnassigned$693
732-Ridgehorne-EdgeSet ScaffSep 24, 2026in 12dUnassigned$661
710-Highridge-EdgeSet ScaffSep 25, 2026in 13dUnassigned$671
Bldg 38-Highridge-EdgeSet ScaffSep 28, 2026in 16dUnassigned$1,104
Bldg 39-Highridge-EdgeInsl AtticOct 9, 2026in 27dUnassigned$80
Bldg 37-Highridge-EdgeInsl AtticNov 3, 2026in 52dUnassigned$80
Ogden — 82 tasks ready for assignment · 61 overdue · $74,917
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
108-Red Hill-IvorySet Brick ScaffAug 12, 202631d overdueUnassigned$40
206-Fremont Meadows-Sterling HomesScratch CoatAug 13, 202630d overdueUnassigned$50
71-Brookfield-LennarGuttersAug 24, 202619d overdueUnassigned$167
63-Brookfield-LennarGuttersAug 24, 202619d overdueUnassigned$236
106-Red Hill-IvorySet Brick ScaffAug 24, 202619d overdueUnassigned$0
108-Red Hill-IvoryScratch CoatAug 25, 202618d overdueUnassigned$50
Bldg 6-Midtown Village-DR HortonSet Brick ScaffAug 26, 202617d overdueUnassigned$0⭕ 2026-09-08: not ready for lathe is missing the metal cap - George Est End: 2026-09-11
1523-Cranefield Estates-IvorySet Brick ScaffAug 26, 202617d overdueUnassigned$134
176-Mountain Gate-Sierra HomesSidingAug 27, 202616d overdueUnassigned2026-09-11$50
106-Red Hill-IvoryBrickAug 28, 202615d overdueUnassigned2026-08-26$50
Bldg 2-Railrunner-DAI ConstructionSidingAug 28, 202615d overdueUnassigned2026-08-26$782✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0
Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction GroupRockAug 31, 202612d overdueUnassigned2026-08-26$635⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15
102-Meadows at Hyde Park-VisionarySidingAug 31, 202612d overdueUnassigned$1,261
338-Sugar Creek-VisionarySidingSep 1, 202611d overdueUnassigned$489
4-Heritage Parkway-Sierra HomesRemove ScaffSep 2, 202610d overdueUnassigned$13✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04
603-Vineyard-VisionaryScratch CoatSep 2, 202610d overdueUnassigned$74
102-Village at Fox Meadows-VisionarySet ScaffSep 3, 20269d overdueUnassigned$446✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
102-Village at Fox Meadows-VisionarySidingSep 3, 20269d overdueUnassigned2026-09-04$1,217✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
SF 7-Flint Acres-Henry Walker HomesScratch CoatSep 5, 20267d overdueUnassigned$331
227-Bristol Farms-Regal HomesShuttersSep 5, 20267d overdueUnassigned2026-09-05$50
2-Brynlee Acres-HamletStucco ColorSep 8, 20264d overdueUnassigned$692
176-Mountain Gate-Sierra HomesVinylSep 8, 20264d overdueUnassigned2026-09-11$671
11-Heritage Parkway-Sierra HomesPaintSep 9, 20263d overdueUnassigned$580✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07
821-Ridgeline Park-VisionaryRockSep 9, 20263d overdueUnassigned2026-09-01$483
229-Bristol Farms-Regal HomesShuttersSep 9, 20263d overdueUnassigned2026-09-05$100
339-Sugar Creek-VisionarySidingSep 9, 20263d overdueUnassigned$364
Bldg L-Sugar Creek Townhomes-VisionarySidingSep 9, 20263d overdueUnassigned2026-08-10$6,419
1709-Cranefield Estates-IvoryStucco ColorSep 9, 20263d overdueUnassigned$790
Bldg 2-Railrunner-DAI ConstructionVinylSep 9, 20263d overdueUnassigned$9,494✅ 2026-07-09: 21 Days - The superintendent said he was ready but I check the building and it’s not ready 100% still has a lot the superintendent apologized for this - George 2026-0
116-Meadows at Hyde Park-VisionaryBrown & MeshSep 10, 20262d overdueUnassigned$1,000
102-Legends Crossing-VisionaryPaintSep 10, 20262d overdueUnassigned$102
103-Legends Crossing-VisionaryPaper/WireSep 10, 20262d overdueUnassigned$50
9-Crested Peaks-IvoryRockSep 10, 20262d overdueUnassigned2026-08-26$4,768
116-Meadows at Hyde Park-VisionaryScratch CoatSep 10, 20262d overdueUnassigned$121
9-Crested Peaks-IvoryScratch CoatSep 10, 20262d overdueUnassigned$646
503-Vineyard-VisionarySet ScaffSep 10, 20262d overdueUnassigned$490
515-Vineyard-VisionarySet ScaffSep 10, 20262d overdueUnassigned$0
126-Red Hill-IvorySet ScaffSep 10, 20262d overdueUnassigned$36
515-Vineyard-VisionarySidingSep 10, 20262d overdueUnassigned$4,879
503-Vineyard-VisionarySidingSep 10, 20262d overdueUnassigned$1,338
4-Brynlee Acres-HamletSidingSep 10, 20262d overdueUnassigned2026-08-26$888
107-Red Hill-IvorySoffit/FasciaSep 10, 20262d overdueUnassigned$554
108-Red Hill-IvorySoffit/FasciaSep 10, 20262d overdueUnassigned$553
102-Meadows at Hyde Park-VisionaryBrickSep 11, 20261d overdueUnassigned$736
102-Meadows at Hyde Park-VisionaryBrown & MeshSep 11, 20261d overdueUnassigned$1,390
330-Riverside Estates-Fieldstone HomesGuttersSep 11, 20261d overdueUnassigned$321
126-Red Hill-IvoryHousewrapSep 11, 20261d overdueUnassigned$473
SF 7-Flint Acres-Henry Walker HomesPaintSep 11, 20261d overdueUnassigned$1,430
2-Brynlee Acres-HamletPaintSep 11, 20261d overdueUnassigned$284
609-Village at Fox Meadows-VisionaryPaintSep 11, 20261d overdueUnassigned$583
Bldg G-Legends Crossing Townhomes-VisionaryPaintSep 11, 20261d overdueUnassigned$187
339-Sugar Creek-VisionaryPaper/WireSep 11, 20261d overdueUnassigned$998
6-Heritage Parkway-Sierra HomesRemove ScaffSep 11, 20261d overdueUnassigned$9
108-Stagecoach Estates-McArthurRockSep 11, 20261d overdueUnassigned$906
501-Legacy Park-IvoryScaff PickupSep 11, 20261d overdueUnassigned$0Trailer ready for pick up
108-Stagecoach Estates-McArthurScratch CoatSep 11, 20261d overdueUnassigned$107
102-Meadows at Hyde Park-VisionaryScratch CoatSep 11, 20261d overdueUnassigned$77
609-Village at Fox Meadows-VisionaryScratch CoatSep 11, 20261d overdueUnassigned$50
Units 47-52-Hess Farms-David Weekley HomesSet ScaffSep 11, 20261d overdueUnassigned$2,216⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-18
108-Stagecoach Estates-McArthurSidingSep 11, 20261d overdueUnassigned2026-09-11$369
108-Stagecoach Estates-McArthurStucco BrownSep 11, 20261d overdueUnassigned$1,069
253-Westwood Estates-Meritage HomesGuttersSep 12, 2026todayUnassigned$464
254-Westwood Estates-Meritage HomesGuttersSep 12, 2026todayUnassigned$287
Bldg U-Village at Fox Meadows Townhomes-VisionaryGuttersSep 12, 2026todayUnassigned$1,001
3-Brynlee Acres-HamletGuttersSep 12, 2026todayUnassigned$248
SF 6-Flint Acres-Henry Walker HomesGuttersSep 12, 2026todayUnassigned$410
12-Mountainside Estates-DR HortonGuttersSep 12, 2026todayUnassigned$262
115-Three Farms Jenkins Fields-IvoryGuttersSep 12, 2026todayUnassigned$162
1708-Cranefield Estates-IvoryGuttersSep 12, 2026todayUnassigned$266
Units 14-19-River Valley-Sierra HomesGuttersSep 12, 2026todayUnassigned$470
Units 47-52-Hess Farms-David Weekley HomesHousewrapSep 12, 2026todayUnassigned$2,779⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-18
115-Meadows at Hyde Park-VisionaryPaintSep 12, 2026todayUnassigned$726
Units 35-40-Hess Farms-David Weekley HomesRockSep 12, 2026todayUnassigned$9,797⭕ 2026-09-03: Scaff Delay - Due to drywall delivery Scafold will not be available for use. - Erik Est End: 2026-09-08 ✅ 2026-08-24: 5 Days - Waiting for wrap inspection to get lat
520-Vineyard-VisionaryStucco ColorSep 12, 2026todayUnassigned2026-09-08$518✅ 2026-08-20: Scaff Delay - we still don't has initial order material - Jose 2026-08-24
227-Bristol Farms-Regal HomesGuttersSep 13, 2026in 1dUnassigned$406
229-Bristol Farms-Regal HomesGuttersSep 13, 2026in 1dUnassigned$252
609-Village at Fox Meadows-VisionaryStucco ColorSep 14, 2026in 2dUnassigned$786
821-Ridgeline Park-VisionaryStucco ColorSep 14, 2026in 2dUnassigned$452
115-Meadows at Hyde Park-VisionaryStucco ColorSep 14, 2026in 2dUnassigned$867
4-Brynlee Acres-HamletStucco ColorSep 15, 2026in 3dUnassigned$806
603-Vineyard-VisionaryStucco ColorSep 15, 2026in 3dUnassigned2026-09-08$1,139
1523-Cranefield Estates-IvoryStucco ColorSep 15, 2026in 3dUnassigned$520
Salt Lake — 34 tasks ready for assignment · 8 overdue · $32,961
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
126-Capitol Reef-EdgeRockSep 11, 20261d overdueUnassigned2026-09-04$502
126-Capitol Reef-EdgeScratch CoatSep 11, 20261d overdueUnassigned$73
1004-Northstar Ranch-Destination HomesSidingSep 11, 20261d overdueUnassigned$1,265⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesSidingSep 11, 20261d overdueUnassigned$1,921⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
1004-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 20261d overdueUnassigned$597⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 20261d overdueUnassigned$686⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
1004-Northstar Ranch-Destination HomesStucco BrownSep 11, 20261d overdueUnassigned$1,157⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11
1037-Northstar Ranch-Destination HomesStucco BrownSep 11, 20261d overdueUnassigned2026-08-27$1,134⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-11 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
104-Pierson Farms-McArthurRockSep 12, 2026todayUnassigned2026-09-08$1,371
Bldg 208-Mountain Ridge-EdgeRockSep 12, 2026todayUnassigned2026-08-27$695
104-Pierson Farms-McArthurScratch CoatSep 12, 2026todayUnassigned$161
Units 544-548-Daybreak Lexington Townhomes-Destination HomesSidingSep 12, 2026todayUnassigned2026-08-27$2,211✅ 2026-08-25: 6 Days - Can’t finish paper and wire completely. Missing drywall windows. - Facundo 2026-09-02 ✅ 2026-08-13: 7 Days - Paper and wire delay. Can’t finish scaffolding
104-Pierson Farms-McArthurStucco BrownSep 12, 2026todayUnassigned$1,113
Bldg 201-Mountain Ridge-EdgeStucco ColorSep 12, 2026todayUnassigned$1,854
Bldg 202-Mountain Ridge-EdgeStucco ColorSep 12, 2026todayUnassigned$1,620
153-Pierson Farms-McArthurStucco ColorSep 14, 2026in 2dUnassigned$1,069
2929-Mountain Ridge-EdgeSet ScaffSep 15, 2026in 3dUnassigned$577
Units 508-509-Daybreak Duets-Destination HomesStucco ColorSep 15, 2026in 3dUnassigned$1,941
111-Creek Ridge Cove-RichmondStucco ColorSep 15, 2026in 3dUnassigned$1,251✅ 2026-08-28: 3 Days - Can’t finish lath and housewrap until back sliding door gets installed - Arturo 2026-09-02
Units 539-540-Daybreak Lexington Townhomes-Destination HomesStucco ColorSep 16, 2026in 4dUnassigned$1,571✅ 2026-08-25: 3 Days - Housewrap and paper and wire delay. Missing drywall windows and sheeting on beam - Facundo 2026-08-28
106-Pierson Farms-McArthurStucco ColorSep 16, 2026in 4dUnassigned$942
2916-Mountain Ridge-EdgeSet ScaffSep 17, 2026in 5dUnassigned$756
Bldg 18-Solari-EdgeSet ScaffSep 18, 2026in 6dUnassigned$1,570
Bldg 19-Solari-EdgeSet ScaffSep 18, 2026in 6dUnassigned$1,570
Bldg 203-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 10dUnassigned$1,474
2931-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 10dUnassigned$712
Bldg 204-Mountain Ridge-EdgeSet ScaffSep 24, 2026in 12dUnassigned$1,501
2927-Mountain Ridge-EdgeSet ScaffSep 25, 2026in 13dUnassigned$708
Bldg 9-Taylor Villas-EdgeInsl AtticSep 29, 2026in 17dUnassigned$179✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
Bldg 1-Solari-EdgeInsl AtticOct 1, 2026in 19dUnassigned$143✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19
Bldg 208-Mountain Ridge-EdgeInsl AtticOct 14, 2026in 32dUnassigned$144
Bldg 202-Mountain Ridge-EdgeInsl AtticOct 20, 2026in 38dUnassigned$143
Bldg 22-Solari-EdgeInsl AtticOct 26, 2026in 44dUnassigned$160
Bldg 19-Solari-EdgeInsl AtticNov 3, 2026in 52dUnassigned$192
St. George — 14 tasks ready for assignment · 10 overdue · $21,207
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
4156-Long Valley Rambler-DR HortonStucco ColorSep 9, 20263d overdueUnassigned$1,303
52-Zion Shores-Split RockRockSep 10, 20262d overdueUnassigned$7,062
7-Chelsey-DR HortonSet ScaffSep 10, 20262d overdueUnassigned$557
37-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20262d overdueUnassigned$100
33-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20262d overdueUnassigned$100
37-Legacy at Sand Hollow-VisionaryHousewrapSep 11, 20261d overdueUnassigned$181
4294-Long Valley-DR HortonHousewrapSep 11, 20261d overdueUnassigned$151
33-Legacy at Sand Hollow-VisionaryHousewrapSep 11, 20261d overdueUnassigned$50
4294-Long Valley-DR HortonPaper/WireSep 11, 20261d overdueUnassigned$2,431
4294-Long Valley-DR HortonPorch OSBSep 11, 20261d overdueUnassigned$168
32-Legacy at Sand Hollow-VisionaryStucco ColorSep 12, 2026todayUnassigned$2,126
323-Finley Farms-RichmondStucco ColorSep 13, 2026in 1dUnassigned$3,068
104-La Spazio-LennarStucco ColorSep 13, 2026in 1dUnassigned2026-09-08$2,146
105-La Spazio-LennarStucco ColorSep 14, 2026in 2dUnassigned$1,763
Commercial — 9 tasks ready for assignment · 9 overdue · $39,571
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-RimrockScratch CoatJul 16, 202658d overdueUnassigned$1,811
Bldg D-Residence at Millcreek-RimrockRemove ScaffAug 6, 202637d overdueUnassigned$7,542
Bldg RU-1-ARA Southwest-Campbell ConstructionPenetration SealingAug 15, 202628d overdueUnassigned$0
Bldg C-Residence at Millcreek-RimrockPaintAug 24, 202619d overdueUnassigned$1,838
White Dome Chapel-St George-Grass CreekSet ScaffAug 27, 202616d overdueUnassigned$57
Bldg RU-1-ARA Southwest-Campbell ConstructionEIFS Weather BarrierSep 1, 202611d overdueUnassigned$1,843
Bldg D-Residence at Millcreek-RimrockRockSep 9, 20263d overdueUnassigned$15,588
Bldg D-Residence at Millcreek-RimrockScratch CoatSep 9, 20263d overdueUnassigned$2,008
Bldg D-Residence at Millcreek-RimrockStucco BrownSep 9, 20263d overdueUnassigned$8,885
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-UnknownMisc. WorkAug 17, 202626d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 292 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: