Every division. Tasks with an assignment date set but no team assigned and not yet completed.
Generated Sep 15, 2026 · Go to the current version →
This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.
● All 6 divisions, not just yours — the
division scoping is removed.
● No 7-day cap. The division view only shows assignments due
inside a week; this carries the whole book — the overdue tail reaching back to
Jul 16, 2026 and forward assignments out to Nov 3, 2026.
● Delayed assignments are not excluded. The division view drops
tasks flagged Task Assignment Is Delayed; that field is not available to this
report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to
active jobs, so an unassigned task on a finaled job shows in your division view and
not here — the one direction where your view is larger than this
report.
Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.
Generated Sep 15, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 14,492 task records pulled, 205 matched the filter · assignment dates Jul 16, 2026 to Nov 3, 2026
past assignment date due today or upcoming
Click any number to see the tasks behind it. Esc closes.
| Division | Overdue 30+ days | Overdue 8-30 days | Overdue 1-7 days | Due today | Next 7 days | Beyond 7 days | Total |
|---|---|---|---|---|---|---|---|
| Orem | · | ||||||
| Ogden | · | ||||||
| Salt Lake | · | · | |||||
| St. George | · | · | · | ||||
| Commercial | · | · | · | ||||
| Corporate | · | · | · | · | · | ||
| All divisions |
Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 27 task types.
Click any number to see the tasks behind it. Esc closes.
| Division | Insl Foam 1 | Insl Walls | Penetration Sealing | Window Pre Wrap | Set Scaff | Housewrap | Set Brick Scaff | Paper/Wire | EIFS Weather Barrier | Stucco Brown | Scratch Coat | Paint | Siding | Rock | Brick | Vinyl | Soffit/Fascia | Brown & Mesh | Gutters | Remove Scaff | Shutters | Stucco Color | Scaff Pickup | Misc. Work | Insl Attic | Foundation Plaster | NewTech | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Orem | · | · | · | · | · | · | · | · | · | · | · | · | ||||||||||||||||
| Ogden | · | · | · | · | · | · | · | · | ||||||||||||||||||||
| Salt Lake | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||||||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions |
Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 134 of 205 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.
Click any number to see the tasks — or the crews — behind it. Esc closes.
Tasks needing assignment
| Division | Scaffolding | Stucco Color | Rock | Gutters | Siding | Insulation | Stucco Brown | Soffit | Paint | Paper/Wire | Housewrap | Brick | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Orem | · | · | · | · | ||||||||||||
| Ogden | · | · | ||||||||||||||
| Salt Lake | · | · | · | · | · | · | ||||||||||
| St. George | · | · | · | · | · | · | · | · | · | |||||||
| Commercial | · | · | · | · | · | · | · | · | · | |||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions | · |
Crews with a hand up — available to that division
| Division | Scaffolding | Stucco Color | Rock | Gutters | Siding | Insulation | Stucco Brown | Soffit | Paint | Paper/Wire | Housewrap | Brick | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Orem | · | · | · | · | · | · | ||||||||||
| Ogden | · | · | · | · | · | · | · | · | · | · | · | · | · | |||
| Salt Lake | · | · | · | · | · | · | · | · | · | |||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | |||||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| All divisions | · | · | · | · |
38 crews company-wide have a hand up, counted once per division they cover (49 crew-division slots, of which 11 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.
Click a division to see the underlying tasks, oldest assignment date first.
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 2014-Wildflower-Toll Brothers | Foundation Plaster | Aug 27, 2026 | 19d overdue | Unassigned | $450 | ⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-16 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l | |
| 106-Canyon Park-Tri Pointe Homes | Paper/Wire | Aug 29, 2026 | 17d overdue | Unassigned | 2026-09-03 | $117 | ⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-16 ✅ 2026-08-20: |
| 143-Montreux-DR Horton | Rock | Sep 2, 2026 | 13d overdue | Unassigned | 2026-08-27 | $706 | ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-15 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - |
| 143-Montreux-DR Horton | Scratch Coat | Sep 2, 2026 | 13d overdue | Unassigned | $83 | ⭕ 2026-08-27: Backside porch is missing concrete pad and columns to be fully wrapped - Alex Est End: 2026-09-15 ✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - | |
| 16122-Harmony-Meritage Homes | Soffit/Fascia | Sep 4, 2026 | 11d overdue | Unassigned | $438 | ||
| 2021-Wildflower-Toll Brothers | Rock | Sep 5, 2026 | 10d overdue | Unassigned | $1,893 | ⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-14 ✅ 2026-09-02: 7 Days - Brown delay - missing drywall window - good to proceed on scratch - | |
| 1027-Harmony Ridge-Edge | Rock | Sep 5, 2026 | 10d overdue | Unassigned | 2026-09-08 | $187 | |
| 254-Canton Ridge-Richmond | Brick | Sep 9, 2026 | 6d overdue | Unassigned | 2026-09-09 | $1,441 | |
| 102-Canton Ridge-Richmond | Rock | Sep 9, 2026 | 6d overdue | Unassigned | 2026-09-01 | $1,094 | |
| 110-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 5d overdue | Unassigned | 2026-09-01 | $173 | ⭕ 2026-09-10: Missing a few windows and inside porch framing needing to be complete. Housewrap will be delayed until those pending items are completed. - Alex Est End: 2026-09-25 |
| 109-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 5d overdue | Unassigned | 2026-09-02 | $117 | ⭕ 2026-09-11: Possible change of plans on the front porch. Might swap pre cast stone to stucco pop out. - Alex Est End: 2026-09-16 |
| 814-Broadview Shores-Ivory | Siding | Sep 10, 2026 | 5d overdue | Unassigned | 2026-09-10 | $3,491 | ✅ 2026-09-09: 2 Days - Failed inspection, hold on scratch coat. - Manuel 2026-09-11 |
| 25-Lakeview Fields-Keystone Construction | Brick | Sep 11, 2026 | 4d overdue | Unassigned | 2026-08-28 | $644 | |
| 519-Ridgeview Cottages-Ivory | Paper/Wire | Sep 11, 2026 | 4d overdue | Unassigned | 2026-09-14 | $940 | ⭕ 2026-09-11: Need to wait for 4 way. Super told me to set scaff but not 4way - Harrison Est End: 2026-09-15 |
| 25-Lakeview Fields-Keystone Construction | Scratch Coat | Sep 11, 2026 | 4d overdue | Unassigned | $67 | ||
| 16119-Harmony-Meritage Homes | Soffit/Fascia | Sep 11, 2026 | 4d overdue | Unassigned | $418 | ||
| Bldg 58-Harmony Ridge-Edge | Rock | Sep 12, 2026 | 3d overdue | Unassigned | 2026-09-01 | $2,077 | |
| 2226 (FP)-Wildflower-Edge | Brick | Sep 14, 2026 | 1d overdue | Unassigned | $180 | ||
| 726-Highridge-Edge | Paint | Sep 14, 2026 | 1d overdue | Unassigned | $196 | ||
| Units 481-485-Regency at Meadowbrook-Woodside | Paper/Wire | Sep 14, 2026 | 1d overdue | Unassigned | $2,474 | ||
| 2226 (FP)-Wildflower-Edge | Scratch Coat | Sep 14, 2026 | 1d overdue | Unassigned | $50 | ||
| 314-Viridian-DR Horton | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $627 | ||
| 420-Viridian-DR Horton | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $681 | ||
| 711-Ridgehorne-Edge | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $747 | ||
| 718-Highridge-Edge | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $831 | ||
| Units 975-979-Anderson Farms Townhomes-Ivory | Soffit/Fascia | Sep 14, 2026 | 1d overdue | Unassigned | $1,239 | ||
| 422-Viridian-DR Horton | Soffit/Fascia | Sep 14, 2026 | 1d overdue | Unassigned | $684 | ||
| Units 975-979-Anderson Farms Townhomes-Ivory | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | $1,760 | ||
| 254-Canton Ridge-Richmond | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | $1,165 | ||
| 102-Canton Ridge-Richmond | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | 2026-09-14 | $1,045 | |
| 717-Highridge-Edge | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | 2026-09-14 | $960 | |
| 723-Highridge-Edge | Remove Scaff | Sep 15, 2026 | today | Unassigned | $412 | ||
| 1018-Harmony Ridge-Edge | Rock | Sep 15, 2026 | today | Unassigned | 2026-09-09 | $493 | |
| 1018-Harmony Ridge-Edge | Scratch Coat | Sep 15, 2026 | today | Unassigned | $71 | ||
| 115-Auburn Springs-Edge | Set Scaff | Sep 15, 2026 | today | Unassigned | $780 | ||
| 1018-Harmony Ridge-Edge | Siding | Sep 15, 2026 | today | Unassigned | 2026-09-08 | $738 | |
| Units 161-164-Enclave at Harmony Place-Woodside | Stucco Brown | Sep 15, 2026 | today | Unassigned | $1,831 | ✅ 2026-08-25: Scaff Delay - Hold on scaff - Jorge 2026-09-03 | |
| 1018-Harmony Ridge-Edge | Stucco Brown | Sep 15, 2026 | today | Unassigned | $1,222 | ||
| 339-Viridian-DR Horton | Set Scaff | Sep 16, 2026 | in 1d | Unassigned | $574 | ||
| 16118-Harmony-Meritage Homes | Stucco Color | Sep 16, 2026 | in 1d | Unassigned | $134 | ||
| 726-Highridge-Edge | Stucco Color | Sep 16, 2026 | in 1d | Unassigned | 2026-09-11 | $1,467 | |
| Bldg 37-Highridge-Edge | Insl Foam 1 | Sep 17, 2026 | in 2d | Unassigned | $115 | ||
| Bldg 37-Highridge-Edge | Insl Walls | Sep 17, 2026 | in 2d | Unassigned | $912 | ||
| 523-River Point-Edge | Set Scaff | Sep 17, 2026 | in 2d | Unassigned | $745 | ||
| 147-Auburn Springs-Edge | Set Scaff | Sep 17, 2026 | in 2d | Unassigned | $723 | ||
| 711-Highridge-Edge | Set Scaff | Sep 17, 2026 | in 2d | Unassigned | $561 | ||
| 16119-Harmony-Meritage Homes | Stucco Color | Sep 17, 2026 | in 2d | Unassigned | $118 | ||
| 16121-Harmony-Meritage Homes | Stucco Color | Sep 17, 2026 | in 2d | Unassigned | $148 | ||
| 26-Lakeview Fields-Keystone Construction | Stucco Color | Sep 17, 2026 | in 2d | Unassigned | $1,341 | ✅ 2026-08-10: 14 Days - Missing man door, can’t start lath - Alex 2026-08-28 | |
| 25-Lakeview Fields-Keystone Construction | Stucco Color | Sep 17, 2026 | in 2d | Unassigned | $1,294 | ||
| 2212-Wildflower-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $660 | ||
| 133-Auburn Springs-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $991 | ||
| 246-Viridian Plus-DR Horton | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $784 | ||
| 2228-Wildflower-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $807 | ||
| Bldg 37-Highridge-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $1,104 | ||
| 16120-Harmony-Meritage Homes | Stucco Color | Sep 18, 2026 | in 3d | Unassigned | $134 | ||
| Bldg 39-Highridge-Edge | Stucco Color | Sep 18, 2026 | in 3d | Unassigned | $1,302 | ||
| 346-Mountain Vista at Sunset Flats-Pulte Homes | Stucco Color | Sep 18, 2026 | in 3d | Unassigned | $1,370 | ✅ 2026-08-31: 6 Days - We need to wait to lath we need to pass Housewrap inspections before we can lath thanks ?? - Victor 2026-09-08 | |
| 422-Viridian-DR Horton | Stucco Color | Sep 19, 2026 | in 4d | Unassigned | $1,238 | ||
| 1027-Harmony Ridge-Edge | Stucco Color | Sep 20, 2026 | in 5d | Unassigned | $965 | ||
| 405-Viridian-DR Horton | Set Scaff | Sep 21, 2026 | in 6d | Unassigned | $771 | ||
| 518-River Point-Edge | Set Scaff | Sep 21, 2026 | in 6d | Unassigned | $583 | ||
| 525-River Point-Edge | Set Scaff | Sep 21, 2026 | in 6d | Unassigned | $671 | ||
| 1030-Harmony Ridge-Edge | Set Scaff | Sep 21, 2026 | in 6d | Unassigned | $756 | ||
| 721-Ridgehorne-Edge | Set Scaff | Sep 22, 2026 | in 7d | Unassigned | $530 | ||
| 1031-Harmony Ridge-Edge | Set Scaff | Sep 23, 2026 | in 8d | Unassigned | $712 | ||
| 519-River Point-Edge | Set Scaff | Sep 23, 2026 | in 8d | Unassigned | $693 | ||
| 1008-Harmony Ridge-Edge | Set Scaff | Sep 24, 2026 | in 9d | Unassigned | $759 | ||
| 732-Ridgehorne-Edge | Set Scaff | Sep 24, 2026 | in 9d | Unassigned | $661 | ||
| 710-Highridge-Edge | Set Scaff | Sep 25, 2026 | in 10d | Unassigned | $671 | ||
| 102-Auburn Springs-Edge | Set Scaff | Sep 28, 2026 | in 13d | Unassigned | $931 | ||
| 719-Highridge-Edge | Set Scaff | Sep 28, 2026 | in 13d | Unassigned | $614 | ||
| Bldg 36-Highridge-Edge | Set Scaff | Sep 28, 2026 | in 13d | Unassigned | $1,104 | ||
| 106-Auburn Springs-Edge | Set Scaff | Sep 28, 2026 | in 13d | Unassigned | $958 | ||
| Bldg 38-Highridge-Edge | Set Scaff | Sep 28, 2026 | in 13d | Unassigned | $1,104 | ||
| 235-Viridian Plus-DR Horton | Set Scaff | Sep 29, 2026 | in 14d | Unassigned | $978 | ||
| 521-River Point-Edge | Set Scaff | Sep 29, 2026 | in 14d | Unassigned | $766 | ||
| 2234-Wildflower-Edge | Set Scaff | Sep 29, 2026 | in 14d | Unassigned | $782 | ||
| Bldg 59-Harmony Ridge-Edge | Set Scaff | Sep 29, 2026 | in 14d | Unassigned | $1,480 | ||
| 602-River Point-Edge | Set Scaff | Oct 1, 2026 | in 16d | Unassigned | $653 | ||
| Bldg 39-Highridge-Edge | Insl Attic | Oct 9, 2026 | in 24d | Unassigned | $80 | ||
| Bldg 37-Highridge-Edge | Insl Attic | Nov 3, 2026 | in 49d | Unassigned | $80 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 108-Red Hill-Ivory | Set Brick Scaff | Aug 12, 2026 | 34d overdue | Unassigned | $40 | ||
| 206-Fremont Meadows-Sterling Homes | Scratch Coat | Aug 13, 2026 | 33d overdue | Unassigned | $50 | ||
| 71-Brookfield-Lennar | Gutters | Aug 24, 2026 | 22d overdue | Unassigned | $167 | ||
| 63-Brookfield-Lennar | Gutters | Aug 24, 2026 | 22d overdue | Unassigned | $236 | ||
| 106-Red Hill-Ivory | Set Brick Scaff | Aug 24, 2026 | 22d overdue | Unassigned | $0 | ||
| 108-Red Hill-Ivory | Scratch Coat | Aug 25, 2026 | 21d overdue | Unassigned | $50 | ||
| Bldg 6-Midtown Village-DR Horton | Set Brick Scaff | Aug 26, 2026 | 20d overdue | Unassigned | $0 | ⭕ 2026-09-08: not ready for lathe is missing the metal cap - George Est End: 2026-09-16 | |
| 1523-Cranefield Estates-Ivory | Set Brick Scaff | Aug 26, 2026 | 20d overdue | Unassigned | $134 | ||
| 176-Mountain Gate-Sierra Homes | Siding | Aug 27, 2026 | 19d overdue | Unassigned | 2026-09-11 | $50 | |
| 106-Red Hill-Ivory | Brick | Aug 28, 2026 | 18d overdue | Unassigned | 2026-08-26 | $50 | |
| Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction Group | Rock | Aug 31, 2026 | 15d overdue | Unassigned | 2026-08-26 | $635 | ⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-15 |
| 338-Sugar Creek-Visionary | Siding | Sep 1, 2026 | 14d overdue | Unassigned | $489 | ||
| 4-Heritage Parkway-Sierra Homes | Remove Scaff | Sep 2, 2026 | 13d overdue | Unassigned | $13 | ✅ 2026-07-29: 4 Days - We still don’t have vinyl material - Jose 2026-08-04 | |
| SF 7-Flint Acres-Henry Walker Homes | Scratch Coat | Sep 5, 2026 | 10d overdue | Unassigned | $331 | ||
| 227-Bristol Farms-Regal Homes | Shutters | Sep 5, 2026 | 10d overdue | Unassigned | 2026-09-05 | $50 | |
| 176-Mountain Gate-Sierra Homes | Vinyl | Sep 8, 2026 | 7d overdue | Unassigned | 2026-09-11 | $671 | |
| 11-Heritage Parkway-Sierra Homes | Paint | Sep 9, 2026 | 6d overdue | Unassigned | $580 | ✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07 | |
| 821-Ridgeline Park-Visionary | Rock | Sep 9, 2026 | 6d overdue | Unassigned | 2026-09-01 | $483 | |
| 339-Sugar Creek-Visionary | Siding | Sep 9, 2026 | 6d overdue | Unassigned | $364 | ||
| 9-Crested Peaks-Ivory | Rock | Sep 10, 2026 | 5d overdue | Unassigned | 2026-08-26 | $4,768 | |
| 116-Meadows at Hyde Park-Visionary | Scratch Coat | Sep 10, 2026 | 5d overdue | Unassigned | $121 | ||
| 9-Crested Peaks-Ivory | Scratch Coat | Sep 10, 2026 | 5d overdue | Unassigned | $646 | ||
| 126-Red Hill-Ivory | Set Scaff | Sep 10, 2026 | 5d overdue | Unassigned | $36 | ||
| 515-Vineyard-Visionary | Siding | Sep 10, 2026 | 5d overdue | Unassigned | $4,879 | ||
| 503-Vineyard-Visionary | Siding | Sep 10, 2026 | 5d overdue | Unassigned | $1,338 | ||
| 107-Red Hill-Ivory | Soffit/Fascia | Sep 10, 2026 | 5d overdue | Unassigned | $554 | ||
| 102-Meadows at Hyde Park-Visionary | Brick | Sep 11, 2026 | 4d overdue | Unassigned | 2026-09-14 | $736 | |
| 102-Meadows at Hyde Park-Visionary | Brown & Mesh | Sep 11, 2026 | 4d overdue | Unassigned | $1,390 | ||
| 330-Riverside Estates-Fieldstone Homes | Gutters | Sep 11, 2026 | 4d overdue | Unassigned | $321 | ||
| SF 7-Flint Acres-Henry Walker Homes | Paint | Sep 11, 2026 | 4d overdue | Unassigned | $1,430 | ||
| Bldg G-Legends Crossing Townhomes-Visionary | Paint | Sep 11, 2026 | 4d overdue | Unassigned | $187 | ||
| 6-Heritage Parkway-Sierra Homes | Remove Scaff | Sep 11, 2026 | 4d overdue | Unassigned | $9 | ||
| 108-Stagecoach Estates-McArthur | Rock | Sep 11, 2026 | 4d overdue | Unassigned | $906 | ||
| 501-Legacy Park-Ivory | Scaff Pickup | Sep 11, 2026 | 4d overdue | Unassigned | $0 | Trailer ready for pick up | |
| 108-Stagecoach Estates-McArthur | Scratch Coat | Sep 11, 2026 | 4d overdue | Unassigned | $107 | ||
| 102-Meadows at Hyde Park-Visionary | Scratch Coat | Sep 11, 2026 | 4d overdue | Unassigned | $77 | ||
| Units 47-52-Hess Farms-David Weekley Homes | Set Scaff | Sep 11, 2026 | 4d overdue | Unassigned | $2,216 | ⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-18 | |
| 115-Meadows at Hyde Park-Visionary | Paint | Sep 12, 2026 | 3d overdue | Unassigned | $726 | ||
| 106-Red Hill-Ivory | Soffit/Fascia | Sep 12, 2026 | 3d overdue | Unassigned | $606 | ||
| 1708-Cranefield Estates-Ivory | Gutters | Sep 14, 2026 | 1d overdue | Unassigned | $266 | ||
| 126-Red Hill-Ivory | Housewrap | Sep 14, 2026 | 1d overdue | Unassigned | $473 | ||
| 126-Red Hill-Ivory | Paper/Wire | Sep 14, 2026 | 1d overdue | Unassigned | $76 | ||
| 104-Seasons at Taylor Landing-Richmond | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $0 | ||
| 1710-Cranefield Estates-Ivory | Set Scaff | Sep 14, 2026 | 1d overdue | Unassigned | $782 | ||
| 609-Village at Fox Meadows-Visionary | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | $786 | ||
| 116-Meadows at Hyde Park-Visionary | Brown & Mesh | Sep 15, 2026 | today | Unassigned | $1,000 | ||
| Units 41-46-Hess Farms-David Weekley Homes | Foundation Plaster | Sep 15, 2026 | today | Unassigned | $450 | ✅ 2026-08-04: Scaff Delay - Building is not ready for Scafold. - Erik 2026-08-07 | |
| Bldg U-Village at Fox Meadows Townhomes-Visionary | Gutters | Sep 15, 2026 | today | Unassigned | $1,001 | ||
| 3-Brynlee Acres-Hamlet | Gutters | Sep 15, 2026 | today | Unassigned | $248 | ||
| 12-Mountainside Estates-DR Horton | Gutters | Sep 15, 2026 | today | Unassigned | $262 | ||
| 1709-Cranefield Estates-Ivory | Gutters | Sep 15, 2026 | today | Unassigned | $216 | ||
| 115-Three Farms Jenkins Fields-Ivory | Gutters | Sep 15, 2026 | today | Unassigned | $162 | ||
| 227-Bristol Farms-Regal Homes | Gutters | Sep 15, 2026 | today | Unassigned | $406 | ||
| 229-Bristol Farms-Regal Homes | Gutters | Sep 15, 2026 | today | Unassigned | $252 | ||
| 1710-Cranefield Estates-Ivory | Housewrap | Sep 15, 2026 | today | Unassigned | $895 | ||
| 2-Brynlee Acres-Hamlet | Paint | Sep 15, 2026 | today | Unassigned | $284 | ||
| 55-Cardamine-Sierra Homes | Paint | Sep 15, 2026 | today | Unassigned | $86 | ✅ 2026-08-12: Material Delay - We don’t have vinyl materials - Jose 2026-08-31 | |
| 5-Brynlee Acres-Hamlet | Rock | Sep 15, 2026 | today | Unassigned | $2,508 | ✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02 | |
| Units 35-40-Hess Farms-David Weekley Homes | Rock | Sep 15, 2026 | today | Unassigned | $9,797 | ✅ 2026-09-03: Scaff Delay - Due to drywall delivery Scafold will not be available for use. - Erik 2026-09-08 ✅ 2026-08-24: 5 Days - Waiting for wrap inspection to get lath and wir | |
| 5-Brynlee Acres-Hamlet | Scratch Coat | Sep 15, 2026 | today | Unassigned | $262 | ✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02 | |
| 4-Brynlee Acres-Hamlet | Siding | Sep 15, 2026 | today | Unassigned | 2026-08-26 | $888 | |
| 609-Village at Fox Meadows-Visionary | Soffit/Fascia | Sep 15, 2026 | today | Unassigned | $606 | ||
| 5-Brynlee Acres-Hamlet | Stucco Brown | Sep 15, 2026 | today | Unassigned | $961 | ✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02 | |
| 229-Bristol Farms-Regal Homes | Foundation Plaster | Sep 16, 2026 | in 1d | Unassigned | $450 | ||
| SF 6-Flint Acres-Henry Walker Homes | Gutters | Sep 16, 2026 | in 1d | Unassigned | $410 | ||
| 115-Three Farms Jenkins Fields-Ivory | Remove Scaff | Sep 16, 2026 | in 1d | Unassigned | $393 | ||
| 108-Stagecoach Estates-McArthur | Stucco Color | Sep 19, 2026 | in 4d | Unassigned | $923 | ||
| 603-Vineyard-Visionary | Stucco Color | Sep 19, 2026 | in 4d | Unassigned | 2026-09-08 | $1,139 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 1004-Northstar Ranch-Destination Homes | Siding | Sep 11, 2026 | 4d overdue | Unassigned | 2026-09-14 | $1,265 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-15 |
| 1037-Northstar Ranch-Destination Homes | Siding | Sep 11, 2026 | 4d overdue | Unassigned | 2026-09-14 | $1,921 | ✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 |
| 1004-Northstar Ranch-Destination Homes | Soffit/Fascia | Sep 11, 2026 | 4d overdue | Unassigned | $597 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-15 | |
| 1037-Northstar Ranch-Destination Homes | Soffit/Fascia | Sep 11, 2026 | 4d overdue | Unassigned | $686 | ✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 | |
| 1004-Northstar Ranch-Destination Homes | Stucco Brown | Sep 11, 2026 | 4d overdue | Unassigned | $1,157 | ⭕ 2026-09-09: Delayed for scaff taken down for gas line. - Dustin Est End: 2026-09-15 | |
| 1037-Northstar Ranch-Destination Homes | Stucco Brown | Sep 11, 2026 | 4d overdue | Unassigned | 2026-08-27 | $1,134 | ✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 |
| 104-Pierson Farms-McArthur | Rock | Sep 12, 2026 | 3d overdue | Unassigned | 2026-09-08 | $1,371 | |
| 153-Pierson Farms-McArthur | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | $1,069 | ||
| 126-Capitol Reef-Edge | Paint | Sep 15, 2026 | today | Unassigned | $1,778 | ||
| Units 508-509-Daybreak Duets-Destination Homes | Stucco Color | Sep 15, 2026 | today | Unassigned | 2026-09-14 | $1,941 | |
| 111-Creek Ridge Cove-Richmond | Stucco Color | Sep 15, 2026 | today | Unassigned | $1,251 | ✅ 2026-08-28: 3 Days - Can’t finish lath and housewrap until back sliding door gets installed - Arturo 2026-09-02 | |
| 122-Capitol Reef-Edge | Rock | Sep 16, 2026 | in 1d | Unassigned | 2026-09-04 | $346 | |
| 122-Capitol Reef-Edge | Scratch Coat | Sep 16, 2026 | in 1d | Unassigned | $50 | ||
| 122-Capitol Reef-Edge | Siding | Sep 16, 2026 | in 1d | Unassigned | 2026-09-03 | $702 | |
| 122-Capitol Reef-Edge | Stucco Brown | Sep 16, 2026 | in 1d | Unassigned | $1,103 | ||
| Units 539-540-Daybreak Lexington Townhomes-Destination Homes | Stucco Color | Sep 16, 2026 | in 1d | Unassigned | $1,571 | ✅ 2026-08-25: 3 Days - Housewrap and paper and wire delay. Missing drywall windows and sheeting on beam - Facundo 2026-08-28 | |
| 106-Pierson Farms-McArthur | Stucco Color | Sep 16, 2026 | in 1d | Unassigned | $942 | ||
| 2916-Mountain Ridge-Edge | Set Scaff | Sep 17, 2026 | in 2d | Unassigned | $756 | ||
| Bldg 208-Mountain Ridge-Edge | Stucco Color | Sep 17, 2026 | in 2d | Unassigned | $1,010 | ||
| Bldg 18-Solari-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $1,570 | ||
| Bldg 19-Solari-Edge | Set Scaff | Sep 18, 2026 | in 3d | Unassigned | $1,570 | ||
| Bldg 203-Mountain Ridge-Edge | Set Scaff | Sep 22, 2026 | in 7d | Unassigned | $1,474 | ||
| 2931-Mountain Ridge-Edge | Set Scaff | Sep 22, 2026 | in 7d | Unassigned | $712 | ||
| Bldg 204-Mountain Ridge-Edge | Set Scaff | Sep 24, 2026 | in 9d | Unassigned | $1,493 | ||
| 2927-Mountain Ridge-Edge | Set Scaff | Sep 25, 2026 | in 10d | Unassigned | $708 | ||
| Bldg 9-Taylor Villas-Edge | Insl Attic | Sep 29, 2026 | in 14d | Unassigned | $179 | ✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18 | |
| 2907-Mountain Ridge-Edge | Set Scaff | Sep 29, 2026 | in 14d | Unassigned | $653 | ||
| Bldg 1-Solari-Edge | Insl Attic | Oct 1, 2026 | in 16d | Unassigned | $143 | ✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19 | |
| Bldg 208-Mountain Ridge-Edge | Insl Attic | Oct 14, 2026 | in 29d | Unassigned | $144 | ||
| Bldg 202-Mountain Ridge-Edge | Insl Attic | Oct 20, 2026 | in 35d | Unassigned | $143 | ||
| Bldg 22-Solari-Edge | Insl Attic | Oct 26, 2026 | in 41d | Unassigned | $160 | ||
| Bldg 19-Solari-Edge | Insl Attic | Nov 3, 2026 | in 49d | Unassigned | $192 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 4156-Long Valley Rambler-DR Horton | Stucco Color | Sep 9, 2026 | 6d overdue | Unassigned | $1,303 | ||
| 52-Zion Shores-Split Rock | Rock | Sep 10, 2026 | 5d overdue | Unassigned | $7,062 | ||
| 37-Legacy at Sand Hollow-Visionary | Window Pre Wrap | Sep 10, 2026 | 5d overdue | Unassigned | $100 | ||
| 33-Legacy at Sand Hollow-Visionary | Window Pre Wrap | Sep 10, 2026 | 5d overdue | Unassigned | $100 | ||
| 37-Legacy at Sand Hollow-Visionary | Housewrap | Sep 11, 2026 | 4d overdue | Unassigned | $181 | ||
| 33-Legacy at Sand Hollow-Visionary | Housewrap | Sep 11, 2026 | 4d overdue | Unassigned | $50 | ||
| 323-Finley Farms-Richmond | Stucco Color | Sep 13, 2026 | 2d overdue | Unassigned | $3,068 | ||
| 104-La Spazio-Lennar | Stucco Color | Sep 13, 2026 | 2d overdue | Unassigned | 2026-09-08 | $2,146 | |
| 105-La Spazio-Lennar | Stucco Color | Sep 14, 2026 | 1d overdue | Unassigned | $1,763 | ||
| 75-Divario-Visionary | Brick | Sep 15, 2026 | today | Unassigned | 2026-09-03 | $2,373 | |
| 75-Divario-Visionary | NewTech | Sep 15, 2026 | today | Unassigned | 2026-09-08 | $1,423 | |
| 75-Divario-Visionary | Scratch Coat | Sep 15, 2026 | today | Unassigned | $306 | ||
| 75-Divario-Visionary | Stucco Brown | Sep 15, 2026 | today | Unassigned | $2,327 | ||
| 4271-Long Valley-DR Horton | Stucco Color | Sep 19, 2026 | in 4d | Unassigned | $1,766 | ||
| 403-The Preserve at Alaia-Visionary | Stucco Color | Sep 20, 2026 | in 5d | Unassigned | $2,380 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Bldg C-Residence at Millcreek-Rimrock | Scratch Coat | Jul 16, 2026 | 61d overdue | Unassigned | $1,811 | ||
| Bldg D-Residence at Millcreek-Rimrock | Remove Scaff | Aug 6, 2026 | 40d overdue | Unassigned | $7,542 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | Penetration Sealing | Aug 15, 2026 | 31d overdue | Unassigned | $0 | ||
| Bldg C-Residence at Millcreek-Rimrock | Paint | Aug 24, 2026 | 22d overdue | Unassigned | $1,838 | ||
| White Dome Chapel-St George-Grass Creek | Set Scaff | Aug 27, 2026 | 19d overdue | Unassigned | $57 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | EIFS Weather Barrier | Sep 1, 2026 | 14d overdue | Unassigned | $1,843 | ||
| Bldg D-Residence at Millcreek-Rimrock | Rock | Sep 9, 2026 | 6d overdue | Unassigned | $15,588 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Cascade West Haven Warehouse-Overhead Projects (Ogden)-Unknown | Misc. Work | Aug 17, 2026 | 29d overdue | Unassigned | $0 | Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP |
Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):
Assigned Task Date is not blankTeam (Task Team) is blankCompleted Date/Time is blankTeam and Team Name agree on every record
(0 disagreements), so "no team assigned" is unambiguous.Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 295 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: