Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Sep 18, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Nov 18, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Sep 18, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 12,925 task records pulled, 184 matched the filter · assignment dates Jul 16, 2026 to Nov 18, 2026

184
Ready for assignment
82
Past assignment date
6
Divisions affected
$201,103
Unassigned task pay
64d
Oldest overdue

Ready tasks by division

015304560Ogden6037 odOrem5818 odSalt Lake3511 odSt. George229 odCommercial86 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Ogden·
Orem·
Salt Lake··
St. George··
Commercial·
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 23 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionInsl Foam 1Insl WallsPenetration SealingWindow Pre WrapSet ScaffHousewrapSet Brick ScaffPaper/WireScratch CoatSidingWateringPaintRockBrickSoffit/FasciaGuttersRemove ScaffStucco CorbelsStucco ColorScaff PickupMisc. WorkInsl AtticFoundation PlasterTotal
Ogden·········
Orem············
Salt Lake·············
St. George··············
Commercial·················
Corporate······················
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 156 of 184 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorGuttersRockInsulationSidingPaintPaper/WireHousewrapSoffitBrickField OpsStucco BrownWarrantyAny tradeTotal
Ogden·····
Orem······
Salt Lake·······
St. George········
Commercial··········
Corporate··············
All divisions·

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorGuttersRockInsulationSidingPaintPaper/WireHousewrapSoffitBrickField OpsStucco BrownWarrantyAny tradeTotal
Ogden·············
Orem··········
Salt Lake···········
St. George············
Commercial················
Corporate················
All divisions········

22 crews company-wide have a hand up, counted once per division they cover (28 crew-division slots, of which 6 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Ogden — 60 tasks ready for assignment · 37 overdue · $53,094
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
108-Red Hill-IvorySet Brick ScaffAug 12, 202637d overdueUnassigned$40
71-Brookfield-LennarGuttersAug 24, 202625d overdueUnassigned$167
63-Brookfield-LennarGuttersAug 24, 202625d overdueUnassigned$236
106-Red Hill-IvorySet Brick ScaffAug 24, 202625d overdueUnassigned$0
Bldg 6-Midtown Village-DR HortonSet Brick ScaffAug 26, 202623d overdueUnassigned$0✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16
1523-Cranefield Estates-IvorySet Brick ScaffAug 26, 202623d overdueUnassigned$134
Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction GroupRockAug 31, 202618d overdueUnassigned2026-08-26$635⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-25
9-Crested Peaks-IvoryRockSep 10, 20268d overdueUnassigned2026-08-26$4,768
9-Crested Peaks-IvoryScratch CoatSep 10, 20268d overdueUnassigned$646
515-Vineyard-VisionarySidingSep 10, 20268d overdueUnassigned$4,879
102-Meadows at Hyde Park-VisionaryBrickSep 11, 20267d overdueUnassigned2026-09-14$736
108-Stagecoach Estates-McArthurRockSep 11, 20267d overdueUnassigned$906
501-Legacy Park-IvoryScaff PickupSep 11, 20267d overdueUnassigned$0Trailer ready for pick up
108-Stagecoach Estates-McArthurScratch CoatSep 11, 20267d overdueUnassigned$107
Units 47-52-Hess Farms-David Weekley HomesSet ScaffSep 11, 20267d overdueUnassigned$1,966⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-18
1709-Cranefield Estates-IvoryGuttersSep 15, 20263d overdueUnassigned$216
5-Brynlee Acres-HamletRockSep 15, 20263d overdueUnassigned$2,508✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02
TH 6-Flint Acres-Henry Walker HomesBrickSep 16, 20262d overdueUnassigned$3,737
Lot 1-6-River Bend Manor Townhomes-HamletHousewrapSep 16, 20262d overdueUnassigned$1,493
108-Stagecoach Estates-McArthurPaintSep 16, 20262d overdueUnassigned2026-09-12$173
102-Meadows at Hyde Park-VisionaryPaintSep 16, 20262d overdueUnassigned$645
5-Brynlee Acres-HamletPaintSep 16, 20262d overdueUnassigned$359✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02
102-Village at Fox Meadows-VisionaryPaintSep 16, 20262d overdueUnassigned$583✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
134-Legends Crossing-VisionaryPaper/WireSep 16, 20262d overdueUnassigned2026-09-14$50
TH 6-Flint Acres-Henry Walker HomesScratch CoatSep 16, 20262d overdueUnassigned$370
Units 1-6-VTG-Sierra HomesSidingSep 16, 20262d overdueUnassigned$3,488
Bldg 6-Midtown Village-DR HortonBrickSep 17, 20261d overdueUnassigned2026-08-31$7,058✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16
Bldg U-Village at Fox Meadows Townhomes-VisionaryGuttersSep 17, 20261d overdueUnassigned$1,001
SF 6-Flint Acres-Henry Walker HomesGuttersSep 17, 20261d overdueUnassigned$410
105-Palomino-DR HortonHousewrapSep 17, 20261d overdueUnassigned$424
4-Brynlee Acres-HamletPaintSep 17, 20261d overdueUnassigned$362
116-Meadows at Hyde Park-VisionaryPaintSep 17, 20261d overdueUnassigned$813
521-Vineyard-VisionaryPaintSep 17, 20261d overdueUnassigned$377
1710-Cranefield Estates-IvoryPaper/WireSep 17, 20261d overdueUnassigned2026-09-14$1,244
Bldg F-Legends Crossing Townhomes-VisionaryPaper/WireSep 17, 20261d overdueUnassigned$116
107-Red Hill-IvoryRemove ScaffSep 17, 20261d overdueUnassigned$0
108-Red Hill-IvoryScratch CoatSep 17, 20261d overdueUnassigned$50
SF 7-Flint Acres-Henry Walker HomesGuttersSep 18, 2026todayUnassigned$648
3-Brynlee Acres-HamletGuttersSep 18, 2026todayUnassigned$248
12-Mountainside Estates-DR HortonGuttersSep 18, 2026todayUnassigned$262
311-Legacy Park-IvoryGuttersSep 18, 2026todayUnassigned$219
11-Heritage Parkway-Sierra HomesGuttersSep 18, 2026todayUnassigned$236✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07
505-Legacy Park-IvoryGuttersSep 18, 2026todayUnassigned$197✅ 2026-09-02: 1 Days - Inspection delayed. - Erik 2026-09-03
54-Cardamine-Sierra HomesGuttersSep 18, 2026todayUnassigned$262✅ 2026-07-29: 12 Days - We don’t have vinyl materials - Jose 2026-08-15
115-Three Farms Jenkins Fields-IvoryGuttersSep 18, 2026todayUnassigned$162
227-Bristol Farms-Regal HomesGuttersSep 18, 2026todayUnassigned$406
229-Bristol Farms-Regal HomesGuttersSep 18, 2026todayUnassigned$252
113-Three Farms Jenkins Fields-IvoryHousewrapSep 18, 2026todayUnassigned$839
107-Stagecoach Estates-McArthurPaintSep 18, 2026todayUnassigned$496
723-Ridgeline Park-VisionaryPaintSep 18, 2026todayUnassigned$796⭕ 2026-09-14: the concrete guys was start doing the porch cap and driways also on the east side was working building a wall - Jose Est End: 2026-09-21 ✅ 2026-09-02: -1 Days - Can’
Bldg 6-Midtown Village-DR HortonWateringSep 18, 2026todayUnassigned$146✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16
1715-Cranefield Estates-IvoryWateringSep 18, 2026todayUnassigned$64
108-Stagecoach Estates-McArthurStucco ColorSep 19, 2026in 1dUnassigned$923
603-Vineyard-VisionaryStucco ColorSep 19, 2026in 1dUnassigned2026-09-08$1,139
108-Red Hill-IvoryRemove ScaffSep 21, 2026in 3dUnassigned$21
107-Stagecoach Estates-McArthurStucco ColorSep 21, 2026in 3dUnassigned$803
5-Brynlee Acres-HamletStucco ColorSep 21, 2026in 3dUnassigned$830✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02
814-Ridgeline Park-VisionaryStucco ColorSep 21, 2026in 3dUnassigned$1,183
Bldg 6-Midtown Village-DR HortonStucco ColorSep 22, 2026in 4dUnassigned$1,455✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16
1715-Cranefield Estates-IvoryStucco ColorSep 23, 2026in 5dUnassigned$809
Orem — 58 tasks ready for assignment · 18 overdue · $52,315
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
2014-Wildflower-Toll BrothersFoundation PlasterAug 27, 202622d overdueUnassigned$450⭕ 2026-08-21: Plaster delay - we cannot install plaster til concrete is poured - Jonathan Est End: 2026-09-18 ✅ 2026-08-04: 2 Days - Brown coat delay - need to do some fixing on l
106-Canyon Park-Tri Pointe HomesPaper/WireAug 29, 202620d overdueUnassigned2026-09-03$117⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-18 ✅ 2026-08-20:
143-Montreux-DR HortonRockSep 2, 202616d overdueUnassigned2026-08-27$706✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex 2026-09-08 ✅ 2026-08-27: 15 Days - Backside porch is missing concrete pad and columns to be fully wrapped
143-Montreux-DR HortonScratch CoatSep 2, 202616d overdueUnassigned$83✅ 2026-09-01: Material Delay - Waiting for siding to be delivered - Alex 2026-09-08 ✅ 2026-08-27: 15 Days - Backside porch is missing concrete pad and columns to be fully wrapped
2021-Wildflower-Toll BrothersRockSep 5, 202613d overdueUnassigned$1,893⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-17 ✅ 2026-09-02: 7 Days - Brown delay - missing drywall window - good to proceed on scratch -
110-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20268d overdueUnassigned2026-09-01$173⭕ 2026-09-10: Missing a few windows and inside porch framing needing to be complete. Housewrap will be delayed until those pending items are completed. - Alex Est End: 2026-09-25
109-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 20268d overdueUnassigned2026-09-02$117⭕ 2026-09-11: Possible change of plans on the front porch. Might swap pre cast stone to stucco pop out. - Alex Est End: 2026-09-18
519-Ridgeview Cottages-IvoryPaper/WireSep 11, 20267d overdueUnassigned2026-09-14$940✅ 2026-09-11: 2 Days - Need to wait for 4 way. Super told me to set scaff but not 4way - Harrison 2026-09-15
718-Highridge-EdgeSet ScaffSep 14, 20264d overdueUnassigned$831
339-Viridian-DR HortonSet ScaffSep 16, 20262d overdueUnassigned$574
102-Canton Ridge-RichmondSidingSep 16, 20262d overdueUnassigned$1,169
914-Broadview Shores-IvoryRockSep 17, 20261d overdueUnassigned2026-09-15$1,635
711-Highridge-EdgeSet ScaffSep 17, 20261d overdueUnassigned$561
525-Ridgeview Cottages-IvorySidingSep 17, 20261d overdueUnassigned$5,493⭕ 2026-09-14: Have to wait for the door to get installed - Harrison Est End: 2026-09-21
26-Tanner Flats-IvorySidingSep 17, 20261d overdueUnassigned2026-09-08$1,203✅ 2026-09-09: 3 Days - Hold on siding good for stucco brown - Jorge 2026-09-14
1018-Harmony Ridge-EdgeSoffit/FasciaSep 17, 20261d overdueUnassigned$621
26-Lakeview Fields-Keystone ConstructionStucco ColorSep 17, 20261d overdueUnassigned$1,341⭕ 2026-09-15: Windows are getting moved around the home. We will not start stucco today until lath is fixed and ready for 100% of the stucco application. Was not notified about the
25-Lakeview Fields-Keystone ConstructionStucco ColorSep 17, 20261d overdueUnassigned$1,294
2212-Wildflower-EdgeSet ScaffSep 18, 2026todayUnassigned$660
Bldg 37-Highridge-EdgeSet ScaffSep 18, 2026todayUnassigned$1,104
246-Viridian Plus-DR HortonSet ScaffSep 19, 2026in 1dUnassigned$784
16122-Harmony-Meritage HomesStucco ColorSep 20, 2026in 2dUnassigned$138
2021-Wildflower-Toll BrothersStucco ColorSep 20, 2026in 2dUnassigned$111⭕ 2026-09-04: Stone delay - material still not delivered - Jonathan Est End: 2026-09-17 ✅ 2026-09-02: 7 Days - Brown delay - missing drywall window - good to proceed on scratch -
421-Viridian-DR HortonStucco ColorSep 20, 2026in 2dUnassigned$906
Bldg 58-Harmony Ridge-EdgeStucco ColorSep 20, 2026in 2dUnassigned$2,677
26-Tanner Flats-IvoryStucco ColorSep 20, 2026in 2dUnassigned$981✅ 2026-09-09: 3 Days - Hold on siding good for stucco brown - Jorge 2026-09-14
405-Viridian-DR HortonSet ScaffSep 21, 2026in 3dUnassigned$771
518-River Point-EdgeSet ScaffSep 21, 2026in 3dUnassigned$583
314-Viridian-DR HortonSet ScaffSep 21, 2026in 3dUnassigned$627
525-River Point-EdgeSet ScaffSep 21, 2026in 3dUnassigned$671
1030-Harmony Ridge-EdgeSet ScaffSep 21, 2026in 3dUnassigned$756
313-Viridian-DR HortonStucco ColorSep 21, 2026in 3dUnassigned$909
Units 161-164-Enclave at Harmony Place-WoodsideStucco ColorSep 22, 2026in 4dUnassigned$1,611✅ 2026-08-25: Scaff Delay - Hold on scaff - Jorge 2026-09-03
712-Highridge-EdgeStucco ColorSep 22, 2026in 4dUnassigned2026-09-17$1,197✅ 2026-09-02: Scaff Delay - Scaff delay - porch cap still isn’t poured , cm told me to hold on Scaff til it’s poured - Jonathan 2026-09-08
1018-Harmony Ridge-EdgeStucco ColorSep 22, 2026in 4dUnassigned$1,055
Units 471-475-Legacy at Meadowbrook-WoodsideStucco ColorSep 22, 2026in 4dUnassigned$1,528✅ 2026-08-25: Scaff Delay - - Harrison 2026-08-28 ✅ 2026-08-05: Scaff Delay - Passed 4 way but we cannot start scaff for 2 weeks. The 18th - Harrison 2026-08-24
1031-Harmony Ridge-EdgeSet ScaffSep 23, 2026in 5dUnassigned$712
519-River Point-EdgeSet ScaffSep 23, 2026in 5dUnassigned$693
914-Broadview Shores-IvoryStucco ColorSep 23, 2026in 5dUnassigned$889
1008-Harmony Ridge-EdgeSet ScaffSep 24, 2026in 6dUnassigned$759
732-Ridgehorne-EdgeSet ScaffSep 24, 2026in 6dUnassigned$661
Bldg 35-Highridge-EdgeInsl Foam 1Sep 25, 2026in 7dUnassigned$115
Bldg 35-Highridge-EdgeInsl WallsSep 25, 2026in 7dUnassigned$912
710-Highridge-EdgeSet ScaffSep 25, 2026in 7dUnassigned$671
719-Highridge-EdgeSet ScaffSep 28, 2026in 10dUnassigned$614
Bldg 36-Highridge-EdgeSet ScaffSep 28, 2026in 10dUnassigned$1,121
106-Auburn Springs-EdgeSet ScaffSep 28, 2026in 10dUnassigned$958
235-Viridian Plus-DR HortonSet ScaffSep 29, 2026in 11dUnassigned$978
2234-Wildflower-EdgeSet ScaffSep 29, 2026in 11dUnassigned$789
Bldg 59-Harmony Ridge-EdgeSet ScaffSep 29, 2026in 11dUnassigned$1,480
1005-Harmony Ridge-EdgeSet ScaffSep 30, 2026in 12dUnassigned$815
Bldg 35-Highridge-EdgeSet ScaffSep 30, 2026in 12dUnassigned$1,121
602-River Point-EdgeSet ScaffOct 2, 2026in 14dUnassigned$653
Bldg 56-Viridian Townhomes-DR HortonSet ScaffOct 2, 2026in 14dUnassigned$1,283
2210-Wildflower-EdgeSet ScaffOct 2, 2026in 14dUnassigned$576
Bldg 39-Highridge-EdgeInsl AtticOct 9, 2026in 21dUnassigned$80
Bldg 37-Highridge-EdgeInsl AtticNov 3, 2026in 46dUnassigned$80
Bldg 35-Highridge-EdgeInsl AtticNov 13, 2026in 56dUnassigned$80
Salt Lake — 35 tasks ready for assignment · 11 overdue · $32,507
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
1004-Northstar Ranch-Destination HomesSidingSep 11, 20267d overdueUnassigned2026-09-14$1,265✅ 2026-09-09: 4 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-15
1037-Northstar Ranch-Destination HomesSidingSep 11, 20267d overdueUnassigned2026-09-14$1,921✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
1004-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 20267d overdueUnassigned$597✅ 2026-09-09: 4 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-15
1037-Northstar Ranch-Destination HomesSoffit/FasciaSep 11, 20267d overdueUnassigned$686✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28
2916-Mountain Ridge-EdgeHousewrapSep 16, 20262d overdueUnassigned$880⭕ 2026-09-16: Do not start exteriors until super approval, only set scaff - Arturo Est End: 2026-09-21
2916-Mountain Ridge-EdgePaper/WireSep 16, 20262d overdueUnassigned$74⭕ 2026-09-16: Do not start exteriors until super approval, only set scaff - Arturo Est End: 2026-09-21
122-Capitol Reef-EdgeRockSep 16, 20262d overdueUnassigned2026-09-04$346
Units 539-540-Daybreak Lexington Townhomes-Destination HomesStucco ColorSep 16, 20262d overdueUnassigned2026-09-18$1,571✅ 2026-08-25: 3 Days - Housewrap and paper and wire delay. Missing drywall windows and sheeting on beam - Facundo 2026-08-28
106-Pierson Farms-McArthurStucco ColorSep 16, 20262d overdueUnassigned2026-09-16$942
256-Boulder at Sky Ranch-WoodsideSidingSep 17, 20261d overdueUnassigned2026-09-10$1,350
Bldg 208-Mountain Ridge-EdgeStucco ColorSep 17, 20261d overdueUnassigned$1,010
Units 49-53-Holladay Hills Townhomes-Tri Pointe HomesRemove ScaffSep 18, 2026todayUnassigned$1,386
Bldg 9-Taylor Villas-EdgeRemove ScaffSep 18, 2026todayUnassigned$891✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
Bldg 18-Solari-EdgeSet ScaffSep 18, 2026todayUnassigned$1,570
Bldg 21-Solari-EdgeSidingSep 18, 2026todayUnassigned2026-09-14$1,973
1005-Northstar Ranch-Destination HomesSoffit/FasciaSep 18, 2026todayUnassigned$587✅ 2026-08-17: 4 Days - Need to wait for gas to set up scaff - Alexander 2026-08-21 ✅ 2026-08-14: 2 Days - No available scaffolding waiting for scaffolding - Alexander 2026-08-18
104-Pierson Farms-McArthurStucco ColorSep 21, 2026in 3dUnassigned$961✅ 2026-09-15: 1 Days - Electricians are fixing the electrical box and straighten it out so we cannot finish siding completely yet. Please don’t assign the Painter. - Facundo 2026-0
22-Sky Ranch Cascade-WoodsideStucco ColorSep 21, 2026in 3dUnassigned$891
Units 544-548-Daybreak Lexington Townhomes-Destination HomesStucco ColorSep 21, 2026in 3dUnassigned2026-09-16$3,582✅ 2026-08-25: 6 Days - Can’t finish paper and wire completely. Missing drywall windows. - Facundo 2026-09-02 ✅ 2026-08-13: 7 Days - Paper and wire delay. Can’t finish scaffolding
2931-Mountain Ridge-EdgeSet ScaffSep 22, 2026in 4dUnassigned$712
1004-Northstar Ranch-Destination HomesStucco ColorSep 22, 2026in 4dUnassigned$999✅ 2026-09-09: 4 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-15
122-Capitol Reef-EdgeStucco ColorSep 22, 2026in 4dUnassigned$953
112-Creek Ridge Cove-RichmondStucco ColorSep 22, 2026in 4dUnassigned$1,344✅ 2026-08-28: 8 Days - We can’t finish lath and housewrap until framers finish front posts and install the side garage door - Arturo 2026-09-09
186-Daybreak-Rainey HomesStucco ColorSep 22, 2026in 4dUnassigned$402✅ 2026-08-24: Material Delay - Wrong material was delivered. They delivered miratec trims and straight shake, the correct material is supposed to be allura trims and scattered shak
2927-Mountain Ridge-EdgeSet ScaffSep 25, 2026in 7dUnassigned$708
Bldg 9-Taylor Villas-EdgeInsl AtticSep 29, 2026in 11dUnassigned$179✅ 2026-08-12: Scaff Delay - Missing roof shingles - Dustin 2026-08-18
2907-Mountain Ridge-EdgeSet ScaffSep 29, 2026in 11dUnassigned$653
Bldg 205-Mountain Ridge-EdgeInsl WallsSep 30, 2026in 12dUnassigned$1,048
Bldg 1-Solari-EdgeInsl AtticOct 1, 2026in 13dUnassigned$143✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19
2904-Mountain Ridge-EdgeSet ScaffOct 1, 2026in 13dUnassigned$747
Bldg 205-Mountain Ridge-EdgeSet ScaffOct 5, 2026in 17dUnassigned$1,499
Bldg 208-Mountain Ridge-EdgeInsl AtticOct 14, 2026in 26dUnassigned$144
Bldg 22-Solari-EdgeInsl AtticOct 26, 2026in 38dUnassigned$160
Bldg 19-Solari-EdgeInsl AtticNov 3, 2026in 46dUnassigned$192
Bldg 205-Mountain Ridge-EdgeInsl AtticNov 18, 2026in 61dUnassigned$143
St. George — 22 tasks ready for assignment · 9 overdue · $32,854
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
52-Zion Shores-Split RockRockSep 10, 20268d overdueUnassigned$7,478
37-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20268d overdueUnassigned$100
33-Legacy at Sand Hollow-VisionaryWindow Pre WrapSep 10, 20268d overdueUnassigned$100
37-Legacy at Sand Hollow-VisionaryHousewrapSep 11, 20267d overdueUnassigned$181
323-Finley Farms-RichmondRemove ScaffSep 13, 20265d overdueUnassigned$463
323-Finley Farms-RichmondStucco ColorSep 13, 20265d overdueUnassigned$3,068
323-Finley Farms-RichmondStucco CorbelsSep 13, 20265d overdueUnassigned$90
4159-Long Valley Rambler-DR HortonPaintSep 17, 20261d overdueUnassigned$50
Bldg 124-Long Valley Townhomes-DR HortonRockSep 17, 20261d overdueUnassigned2026-09-09$50
4159-Long Valley Rambler-DR HortonRockSep 18, 2026todayUnassigned2026-09-10$406
4270-Long Valley-DR HortonRockSep 18, 2026todayUnassigned2026-09-10$504
4293-Long Valley-DR HortonRockSep 18, 2026todayUnassigned2026-09-09$707
4270-Long Valley-DR HortonScratch CoatSep 18, 2026todayUnassigned$69
4293-Long Valley-DR HortonScratch CoatSep 18, 2026todayUnassigned$97
4270-Long Valley-DR HortonSidingSep 18, 2026todayUnassigned2026-09-14$473
4293-Long Valley-DR HortonSidingSep 18, 2026todayUnassigned2026-09-14$1,039
4271-Long Valley-DR HortonStucco ColorSep 19, 2026in 1dUnassigned$1,766
403-The Preserve at Alaia-VisionaryStucco ColorSep 20, 2026in 2dUnassigned$2,380
Bldg 124-Long Valley Townhomes-DR HortonStucco ColorSep 21, 2026in 3dUnassigned2026-09-14$4,999
4159-Long Valley Rambler-DR HortonStucco ColorSep 22, 2026in 4dUnassigned$1,303
75-Divario-VisionaryStucco ColorSep 22, 2026in 4dUnassigned$2,824
33-Black Desert North Village-H2 HomesStucco ColorSep 22, 2026in 4dUnassigned2026-08-17$4,708
Commercial — 8 tasks ready for assignment · 6 overdue · $30,332
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-RimrockScratch CoatJul 16, 202664d overdueUnassigned$1,811
Bldg D-Residence at Millcreek-RimrockRemove ScaffAug 6, 202643d overdueUnassigned$7,542
Bldg RU-1-ARA Southwest-Campbell ConstructionPenetration SealingAug 15, 202634d overdueUnassigned$0
White Dome Chapel-St George-Grass CreekSet ScaffAug 27, 202622d overdueUnassigned$57
Bldg D-Residence at Millcreek-RimrockRockSep 9, 20269d overdueUnassigned$15,588
Bldg RU-1-ARA Southwest-Campbell ConstructionSet ScaffSep 16, 20262d overdueUnassigned$2,000West Walls Setup
Garage 4-Residence at Millcreek-RimrockRockSep 18, 2026todayUnassigned2026-09-02$1,190
Garage 4-Residence at Millcreek-RimrockStucco ColorSep 23, 2026in 5dUnassigned$2,145
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-UnknownMisc. WorkAug 17, 202632d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 296 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: