Every division. Tasks with an assignment date set but no team assigned and not yet completed.
Generated Sep 23, 2026 · Go to the current version →
This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.
● All 6 divisions, not just yours — the
division scoping is removed.
● No 7-day cap. The division view only shows assignments due
inside a week; this carries the whole book — the overdue tail reaching back to
Jul 16, 2026 and forward assignments out to Nov 18, 2026.
● Delayed assignments are not excluded. The division view drops
tasks flagged Task Assignment Is Delayed; that field is not available to this
report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to
active jobs, so an unassigned task on a finaled job shows in your division view and
not here — the one direction where your view is larger than this
report.
Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.
Generated Sep 23, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 12,642 task records pulled, 152 matched the filter · assignment dates Jul 16, 2026 to Nov 18, 2026
past assignment date due today or upcoming
Click any number to see the tasks behind it. Esc closes.
| Division | Overdue 30+ days | Overdue 8-30 days | Overdue 1-7 days | Due today | Next 7 days | Beyond 7 days | Total |
|---|---|---|---|---|---|---|---|
| Ogden | · | ||||||
| Orem | · | ||||||
| Salt Lake | · | · | |||||
| St. George | · | · | |||||
| Commercial | · | ||||||
| Corporate | · | · | · | · | · | ||
| All divisions |
Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 21 task types.
Click any number to see the tasks behind it. Esc closes.
| Division | Insl Walls | Penetration Sealing | Window Pre Wrap | Set Scaff | Housewrap | Set Brick Scaff | Paper/Wire | Stucco Brown | Scratch Coat | Siding | Paint | Rock | Brick | Vinyl | Soffit/Fascia | Brown & Mesh | Gutters | Remove Scaff | Stucco Color | Misc. Work | Insl Attic | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | · | · | · | |||||||||||||||||
| Orem | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||||
| Salt Lake | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||||||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | |||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions |
Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 119 of 152 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.
Click any number to see the tasks — or the crews — behind it. Esc closes.
Tasks needing assignment
| Division | Scaffolding | Stucco Color | Insulation | Paper/Wire | Rock | Siding | Gutters | Paint | Housewrap | Soffit | Stucco Brown | Brick | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | · | |||||||||||||
| Orem | · | · | · | · | · | · | · | |||||||||
| Salt Lake | · | · | · | · | · | · | · | · | ||||||||
| St. George | · | · | · | · | · | · | · | · | · | · | ||||||
| Commercial | · | · | · | · | · | · | · | · | · | · | ||||||
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | ||
| All divisions | · |
Crews with a hand up — available to that division
| Division | Scaffolding | Stucco Color | Insulation | Paper/Wire | Rock | Siding | Gutters | Paint | Housewrap | Soffit | Stucco Brown | Brick | Field Ops | Warranty | Any trade | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ogden | · | · | · | · | · | · | · | · | · | · | · | · | · | |||
| Orem | · | · | · | · | · | · | · | · | · | · | ||||||
| Salt Lake | · | · | · | · | · | · | · | · | · | · | ||||||
| St. George | · | · | · | · | · | · | · | · | · | · | · | · | · | |||
| Commercial | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| Corporate | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · | · |
| All divisions | · | · | · | · | · | · | · |
21 crews company-wide have a hand up, counted once per division they cover (25 crew-division slots, of which 4 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.
Click a division to see the underlying tasks, oldest assignment date first.
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 71-Brookfield-Lennar | Gutters | Aug 24, 2026 | 30d overdue | Unassigned | $167 | ||
| 63-Brookfield-Lennar | Gutters | Aug 24, 2026 | 30d overdue | Unassigned | $236 | ||
| 106-Red Hill-Ivory | Set Brick Scaff | Aug 24, 2026 | 30d overdue | Unassigned | $0 | ||
| Bldg 6-Midtown Village-DR Horton | Set Brick Scaff | Aug 26, 2026 | 28d overdue | Unassigned | $0 | ✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16 | |
| 1523-Cranefield Estates-Ivory | Set Brick Scaff | Aug 26, 2026 | 28d overdue | Unassigned | $134 | ||
| Jorgensen Residence CMU-Custom Jobs (Huntsville)-Jed Slama Construction Group | Rock | Aug 31, 2026 | 23d overdue | Unassigned | 2026-08-26 | $635 | ⭕ 2026-08-24: Material Delay - we're waiting on the stone to get the fireplace completed - George Est End: 2026-09-25 |
| 102-Meadows at Hyde Park-Visionary | Brick | Sep 11, 2026 | 12d overdue | Unassigned | 2026-09-14 | $736 | |
| Units 47-52-Hess Farms-David Weekley Homes | Set Scaff | Sep 11, 2026 | 12d overdue | Unassigned | $1,966 | ⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-23 | |
| TH 6-Flint Acres-Henry Walker Homes | Brick | Sep 16, 2026 | 7d overdue | Unassigned | $3,737 | ||
| TH 6-Flint Acres-Henry Walker Homes | Scratch Coat | Sep 16, 2026 | 7d overdue | Unassigned | $370 | ||
| 4-Brynlee Acres-Hamlet | Paint | Sep 17, 2026 | 6d overdue | Unassigned | $362 | ||
| 12-Mountainside Estates-DR Horton | Gutters | Sep 18, 2026 | 5d overdue | Unassigned | $262 | ||
| 723-Ridgeline Park-Visionary | Paint | Sep 18, 2026 | 5d overdue | Unassigned | $796 | ⭕ 2026-09-14: the concrete guys was start doing the porch cap and driways also on the east side was working building a wall - Jose Est End: 2026-09-21 ✅ 2026-09-02: -1 Days - Can’ | |
| 5-Valley Meadows-Dixon Homes | Brick | Sep 19, 2026 | 4d overdue | Unassigned | $13,668 | ||
| 176-Mountain Gate-Sierra Homes | Brown & Mesh | Sep 19, 2026 | 4d overdue | Unassigned | 2026-09-15 | $1,815 | |
| Bldg L-Sugar Creek Townhomes-Visionary | Paint | Sep 19, 2026 | 4d overdue | Unassigned | $2,304 | ||
| 176-Mountain Gate-Sierra Homes | Rock | Sep 19, 2026 | 4d overdue | Unassigned | 2026-09-11 | $1,213 | |
| 176-Mountain Gate-Sierra Homes | Scratch Coat | Sep 19, 2026 | 4d overdue | Unassigned | $140 | ||
| 505-Legacy Park-Ivory | Gutters | Sep 21, 2026 | 2d overdue | Unassigned | $197 | ✅ 2026-09-02: 1 Days - Inspection delayed. - Erik 2026-09-03 | |
| 124-Three Farms Jenkins Fields-Ivory | Set Brick Scaff | Sep 21, 2026 | 2d overdue | Unassigned | $24 | ||
| Bldg L-Sugar Creek Townhomes-Visionary | Brown & Mesh | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-10 | $1,428 | |
| 124-Three Farms Jenkins Fields-Ivory | Housewrap | Sep 22, 2026 | 1d overdue | Unassigned | $834 | ||
| 503-Vineyard-Visionary | Paint | Sep 22, 2026 | 1d overdue | Unassigned | $622 | ||
| 113-Three Farms Jenkins Fields-Ivory | Paper/Wire | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-17 | $1,080 | |
| Bldg L-Sugar Creek Townhomes-Visionary | Rock | Sep 22, 2026 | 1d overdue | Unassigned | $530 | ||
| 339-Sugar Creek-Visionary | Scratch Coat | Sep 22, 2026 | 1d overdue | Unassigned | $50 | ||
| Bldg L-Sugar Creek Townhomes-Visionary | Scratch Coat | Sep 22, 2026 | 1d overdue | Unassigned | $53 | ||
| Bldg 14-Midtown Village-DR Horton | Set Scaff | Sep 22, 2026 | 1d overdue | Unassigned | $1,318 | ||
| Bldg F-Legends Crossing Townhomes-Visionary | Siding | Sep 22, 2026 | 1d overdue | Unassigned | $438 | ||
| Bldg L-Sugar Creek Townhomes-Visionary | Stucco Brown | Sep 22, 2026 | 1d overdue | Unassigned | $1,428 | ||
| Bldg 6-Midtown Village-DR Horton | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $1,455 | ✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16 | |
| Bldg F-Legends Crossing Townhomes-Visionary | Vinyl | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-02 | $4,732 | |
| 203-Stagecoach Estates-McArthur | Window Pre Wrap | Sep 22, 2026 | 1d overdue | Unassigned | $100 | ||
| Bldg 13-Midtown Village-DR Horton | Brick | Sep 23, 2026 | today | Unassigned | $6,903 | ||
| 2-Brynlee Acres-Hamlet | Gutters | Sep 23, 2026 | today | Unassigned | $301 | ||
| 203-Weber View-Ivory | Gutters | Sep 23, 2026 | today | Unassigned | $376 | ||
| 11-Heritage Parkway-Sierra Homes | Gutters | Sep 23, 2026 | today | Unassigned | $236 | ✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07 | |
| 1711-Cranefield Estates-Ivory | Housewrap | Sep 23, 2026 | today | Unassigned | $1,100 | ||
| 1712-Cranefield Estates-Ivory | Housewrap | Sep 23, 2026 | today | Unassigned | $989 | ||
| 176-Mountain Gate-Sierra Homes | Paint | Sep 23, 2026 | today | Unassigned | $50 | ||
| Bldg 13-Midtown Village-DR Horton | Scratch Coat | Sep 23, 2026 | today | Unassigned | $752 | ||
| Bldg Y-North Point Townhomes-Visionary | Scratch Coat | Sep 23, 2026 | today | Unassigned | $186 | ||
| Bldg Z-North Point Townhomes-Visionary | Set Scaff | Sep 23, 2026 | today | Unassigned | $1,444 | ||
| 241-Westwood Estates-Meritage Homes | Siding | Sep 23, 2026 | today | Unassigned | 2026-09-17 | $4,632 | |
| Bldg 13-Midtown Village-DR Horton | Siding | Sep 23, 2026 | today | Unassigned | 2026-09-18 | $3,062 | |
| 241-Westwood Estates-Meritage Homes | Soffit/Fascia | Sep 23, 2026 | today | Unassigned | $527 | ||
| 176-Mountain Gate-Sierra Homes | Soffit/Fascia | Sep 23, 2026 | today | Unassigned | $1,022 | ||
| 338-Sugar Creek-Visionary | Stucco Color | Sep 23, 2026 | today | Unassigned | $1,028 | ||
| 1523-Cranefield Estates-Ivory | Gutters | Sep 24, 2026 | in 1d | Unassigned | $382 | ||
| 102-Meadows at Hyde Park-Visionary | Stucco Color | Sep 24, 2026 | in 1d | Unassigned | $978 | ||
| 116-Meadows at Hyde Park-Visionary | Stucco Color | Sep 26, 2026 | in 3d | Unassigned | $704 | ||
| 521-Vineyard-Visionary | Stucco Color | Sep 26, 2026 | in 3d | Unassigned | $585 | ||
| 216-Sugar Creek-Visionary | Stucco Color | Sep 27, 2026 | in 4d | Unassigned | 2026-09-16 | $1,236 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 106-Canyon Park-Tri Pointe Homes | Paper/Wire | Aug 29, 2026 | 25d overdue | Unassigned | 2026-09-03 | $117 | ⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-23 ✅ 2026-08-20: |
| 110-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 13d overdue | Unassigned | 2026-09-01 | $173 | ⭕ 2026-09-10: Missing a few windows and inside porch framing needing to be complete. Housewrap will be delayed until those pending items are completed. - Alex Est End: 2026-09-25 |
| 109-Canyon Park-Tri Pointe Homes | Paper/Wire | Sep 10, 2026 | 13d overdue | Unassigned | 2026-09-02 | $117 | ⭕ 2026-09-11: Possible change of plans on the front porch. Might swap pre cast stone to stucco pop out. - Alex Est End: 2026-09-23 |
| 26-Lakeview Fields-Keystone Construction | Stucco Color | Sep 17, 2026 | 6d overdue | Unassigned | $1,341 | ⭕ 2026-09-21: Waiting on color selection for grout. - Alex Est End: 2026-09-23 ✅ 2026-09-15: 2 Days - Windows are getting moved around the home. We will not start stucco today unti | |
| 246-Viridian Plus-DR Horton | Set Scaff | Sep 19, 2026 | 4d overdue | Unassigned | $786 | ||
| Bldg 58-Harmony Ridge-Edge | Stucco Color | Sep 20, 2026 | 3d overdue | Unassigned | $2,677 | ||
| 718-Highridge-Edge | Paper/Wire | Sep 21, 2026 | 2d overdue | Unassigned | 2026-09-18 | $59 | |
| 2216 (FP)-Wildflower-Edge | Paper/Wire | Sep 21, 2026 | 2d overdue | Unassigned | $50 | ||
| 518-River Point-Edge | Set Scaff | Sep 21, 2026 | 2d overdue | Unassigned | $583 | ⭕ 2026-09-21: We can set staff, but we need to hold off on Weather barrier till further notice - Harrison Est End: 2026-09-23 | |
| 525-River Point-Edge | Set Scaff | Sep 21, 2026 | 2d overdue | Unassigned | $671 | ⭕ 2026-09-21: We can set staff, but we need to hold off on Weather barrier till further notice - Harrison Est End: 2026-09-23 | |
| 314-Viridian-DR Horton | Housewrap | Sep 22, 2026 | 1d overdue | Unassigned | $191 | ||
| 721-Ridgehorne-Edge | Housewrap | Sep 22, 2026 | 1d overdue | Unassigned | $150 | ⭕ 2026-09-22: Lath delay - good to proceed on lath for stone - missing windows - Jonathan Est End: 2026-09-24 | |
| 314-Viridian-DR Horton | Paper/Wire | Sep 22, 2026 | 1d overdue | Unassigned | $917 | ||
| Bldg 37-Highridge-Edge | Paper/Wire | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-22 | $1,343 | |
| 44-Lakeview Fields-Keystone Construction | Paper/Wire | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-02 | $1,170 | ⭕ 2026-09-22: Cannot start lath. Missing man door to the side of the garage. - Alex Est End: 2026-09-25 |
| 405-Viridian-DR Horton | Set Scaff | Sep 22, 2026 | 1d overdue | Unassigned | $771 | ||
| Units 161-164-Enclave at Harmony Place-Woodside | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $1,611 | ✅ 2026-08-25: Scaff Delay - Hold on scaff - Jorge 2026-09-03 | |
| Units 471-475-Legacy at Meadowbrook-Woodside | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $1,528 | ✅ 2026-08-25: Scaff Delay - - Harrison 2026-08-28 ✅ 2026-08-05: Scaff Delay - Passed 4 way but we cannot start scaff for 2 weeks. The 18th - Harrison 2026-08-24 | |
| 233-Viridian Plus-DR Horton | Scratch Coat | Sep 23, 2026 | today | Unassigned | $118 | ||
| 1031-Harmony Ridge-Edge | Set Scaff | Sep 23, 2026 | today | Unassigned | $712 | ||
| 519-River Point-Edge | Set Scaff | Sep 23, 2026 | today | Unassigned | $693 | ||
| 420-Viridian-DR Horton | Siding | Sep 23, 2026 | today | Unassigned | 2026-09-18 | $1,316 | |
| 340-Viridian-DR Horton | Siding | Sep 23, 2026 | today | Unassigned | 2026-09-17 | $1,046 | |
| 16116-Harmony-Meritage Homes | Soffit/Fascia | Sep 23, 2026 | today | Unassigned | $514 | ||
| 914-Broadview Shores-Ivory | Stucco Color | Sep 23, 2026 | today | Unassigned | $889 | ||
| 1008-Harmony Ridge-Edge | Set Scaff | Sep 24, 2026 | in 1d | Unassigned | $764 | ||
| 732-Ridgehorne-Edge | Set Scaff | Sep 24, 2026 | in 1d | Unassigned | $661 | ||
| 710-Highridge-Edge | Set Scaff | Sep 25, 2026 | in 2d | Unassigned | $671 | ||
| 719-Highridge-Edge | Set Scaff | Sep 28, 2026 | in 5d | Unassigned | $614 | ||
| 106-Auburn Springs-Edge | Set Scaff | Sep 28, 2026 | in 5d | Unassigned | $958 | ||
| 235-Viridian Plus-DR Horton | Set Scaff | Sep 29, 2026 | in 6d | Unassigned | $978 | ||
| 2234-Wildflower-Edge | Set Scaff | Sep 29, 2026 | in 6d | Unassigned | $789 | ||
| Bldg 59-Harmony Ridge-Edge | Set Scaff | Sep 29, 2026 | in 6d | Unassigned | $1,480 | ||
| 1005-Harmony Ridge-Edge | Set Scaff | Sep 30, 2026 | in 7d | Unassigned | $830 | ||
| Bldg 35-Highridge-Edge | Set Scaff | Sep 30, 2026 | in 7d | Unassigned | $1,121 | ||
| 602-River Point-Edge | Set Scaff | Oct 2, 2026 | in 9d | Unassigned | $653 | ||
| Bldg 56-Viridian Townhomes-DR Horton | Set Scaff | Oct 2, 2026 | in 9d | Unassigned | $1,283 | ||
| 714-Highridge-Edge | Set Scaff | Oct 5, 2026 | in 12d | Unassigned | $576 | ||
| 713-Ridgehorne-Edge | Set Scaff | Oct 6, 2026 | in 13d | Unassigned | $829 | ||
| 104-Auburn Springs-Edge | Set Scaff | Oct 6, 2026 | in 13d | Unassigned | $1,029 | ||
| 521-River Point-Edge | Set Scaff | Oct 6, 2026 | in 13d | Unassigned | $766 | ||
| 2210-Wildflower-Edge | Set Scaff | Oct 6, 2026 | in 13d | Unassigned | $576 | ||
| 110-Auburn Springs-Edge | Set Scaff | Oct 7, 2026 | in 14d | Unassigned | $654 | ||
| 354-Viridian Emerald-DR Horton | Set Scaff | Oct 7, 2026 | in 14d | Unassigned | $0 | ||
| 102-Auburn Springs-Edge | Set Scaff | Oct 7, 2026 | in 14d | Unassigned | $931 | ||
| Bldg 39-Highridge-Edge | Insl Attic | Oct 9, 2026 | in 16d | Unassigned | $80 | ||
| Bldg 37-Highridge-Edge | Insl Attic | Nov 3, 2026 | in 41d | Unassigned | $80 | ||
| Bldg 35-Highridge-Edge | Insl Attic | Nov 13, 2026 | in 51d | Unassigned | $80 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 122-Capitol Reef-Edge | Soffit/Fascia | Sep 21, 2026 | 2d overdue | Unassigned | $564 | ||
| Units 544-548-Daybreak Lexington Townhomes-Destination Homes | Stucco Color | Sep 21, 2026 | 2d overdue | Unassigned | 2026-09-16 | $3,582 | ✅ 2026-08-25: 6 Days - Can’t finish paper and wire completely. Missing drywall windows. - Facundo 2026-09-02 ✅ 2026-08-13: 7 Days - Paper and wire delay. Can’t finish scaffolding |
| 103-Creek Ridge Cove-Richmond | Soffit/Fascia | Sep 22, 2026 | 1d overdue | Unassigned | $686 | ||
| 1004-Northstar Ranch-Destination Homes | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $999 | ✅ 2026-09-09: 4 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-15 | |
| 122-Capitol Reef-Edge | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $953 | ||
| Units 325-330-Enclave at Sky Ranch-Woodside | Paint | Sep 23, 2026 | today | Unassigned | 2026-09-22 | $1,510 | |
| 254-Boulder at Sky Ranch-Woodside | Siding | Sep 23, 2026 | today | Unassigned | $1,209 | ||
| Bldg 22-Solari-Edge | Siding | Sep 23, 2026 | today | Unassigned | 2026-09-15 | $1,798 | |
| 254-Boulder at Sky Ranch-Woodside | Stucco Brown | Sep 23, 2026 | today | Unassigned | $1,153 | ||
| Bldg 22-Solari-Edge | Stucco Brown | Sep 23, 2026 | today | Unassigned | $2,843 | ||
| 1037-Northstar Ranch-Destination Homes | Stucco Color | Sep 23, 2026 | today | Unassigned | $979 | ✅ 2026-09-09: 3 Days - Delayed for scaff taken down for gas line. - Dustin 2026-09-14 ✅ 2026-08-24: 4 Days - Waiting on materials/initial order - Alexander 2026-08-28 | |
| 103-Creek Ridge Cove-Richmond | Stucco Color | Sep 23, 2026 | today | Unassigned | $1,219 | ||
| Bldg 21-Solari-Edge | Stucco Color | Sep 24, 2026 | in 1d | Unassigned | $2,876 | ||
| 2927-Mountain Ridge-Edge | Set Scaff | Sep 25, 2026 | in 2d | Unassigned | $708 | ||
| Units 325-330-Enclave at Sky Ranch-Woodside | Stucco Color | Sep 26, 2026 | in 3d | Unassigned | $3,498 | ||
| 154-Pierson Farms-McArthur | Stucco Color | Sep 27, 2026 | in 4d | Unassigned | $937 | ||
| 256-Boulder at Sky Ranch-Woodside | Stucco Color | Sep 27, 2026 | in 4d | Unassigned | $914 | ||
| 2907-Mountain Ridge-Edge | Set Scaff | Sep 29, 2026 | in 6d | Unassigned | $653 | ||
| Bldg 205-Mountain Ridge-Edge | Insl Walls | Sep 30, 2026 | in 7d | Unassigned | $1,048 | ||
| Bldg 1-Solari-Edge | Insl Attic | Oct 1, 2026 | in 8d | Unassigned | $143 | ✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19 | |
| 2904-Mountain Ridge-Edge | Set Scaff | Oct 1, 2026 | in 8d | Unassigned | $747 | ||
| Bldg 17-Solari-Edge | Set Scaff | Oct 5, 2026 | in 12d | Unassigned | $1,355 | ||
| Bldg 205-Mountain Ridge-Edge | Set Scaff | Oct 5, 2026 | in 12d | Unassigned | $1,492 | ||
| 2918-Mountain Ridge-Edge | Set Scaff | Oct 7, 2026 | in 14d | Unassigned | $742 | ||
| Bldg 208-Mountain Ridge-Edge | Insl Attic | Oct 14, 2026 | in 21d | Unassigned | $144 | ||
| Bldg 22-Solari-Edge | Insl Attic | Oct 26, 2026 | in 33d | Unassigned | $160 | ||
| Bldg 19-Solari-Edge | Insl Attic | Nov 3, 2026 | in 41d | Unassigned | $192 | ||
| Bldg 205-Mountain Ridge-Edge | Insl Attic | Nov 18, 2026 | in 56d | Unassigned | $143 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| 52-Zion Shores-Split Rock | Rock | Sep 10, 2026 | 13d overdue | Unassigned | 2026-09-21 | $7,478 | |
| Bldg 124-Long Valley Townhomes-DR Horton | Stucco Color | Sep 21, 2026 | 2d overdue | Unassigned | 2026-09-14 | $4,999 | |
| 4270-Long Valley-DR Horton | Paint | Sep 22, 2026 | 1d overdue | Unassigned | $50 | ||
| 4159-Long Valley Rambler-DR Horton | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | 2026-09-22 | $1,303 | |
| 75-Divario-Visionary | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | $2,824 | ||
| 33-Black Desert North Village-H2 Homes | Stucco Color | Sep 22, 2026 | 1d overdue | Unassigned | 2026-08-17 | $4,708 | |
| 114-Desert Color-Split Rock | Rock | Sep 23, 2026 | today | Unassigned | 2026-09-22 | $3,624 | |
| 33-Legacy at Sand Hollow-Visionary | Rock | Sep 23, 2026 | today | Unassigned | 2026-09-17 | $263 | |
| 33-Legacy at Sand Hollow-Visionary | Scratch Coat | Sep 23, 2026 | today | Unassigned | $50 | ||
| 33-Legacy at Sand Hollow-Visionary | Stucco Brown | Sep 23, 2026 | today | Unassigned | $1,689 | ||
| 4270-Long Valley-DR Horton | Stucco Color | Sep 23, 2026 | today | Unassigned | $1,916 | ||
| 4293-Long Valley-DR Horton | Stucco Color | Sep 23, 2026 | today | Unassigned | $2,215 | ||
| 4294-Long Valley-DR Horton | Stucco Color | Sep 26, 2026 | in 3d | Unassigned | $2,259 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Bldg C-Residence at Millcreek-Rimrock | Scratch Coat | Jul 16, 2026 | 69d overdue | Unassigned | $1,811 | ||
| Bldg D-Residence at Millcreek-Rimrock | Remove Scaff | Aug 6, 2026 | 48d overdue | Unassigned | $7,542 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | Penetration Sealing | Aug 15, 2026 | 39d overdue | Unassigned | $0 | ||
| White Dome Chapel-St George-Grass Creek | Set Scaff | Aug 27, 2026 | 27d overdue | Unassigned | $57 | ||
| Bldg D-Residence at Millcreek-Rimrock | Rock | Sep 9, 2026 | 14d overdue | Unassigned | $15,588 | ||
| Bldg RU-1-ARA Southwest-Campbell Construction | Set Scaff | Sep 16, 2026 | 7d overdue | Unassigned | $2,000 | West Walls Setup | |
| Garage 4-Residence at Millcreek-Rimrock | Rock | Sep 18, 2026 | 5d overdue | Unassigned | 2026-09-02 | $1,190 | |
| Garage 4-Residence at Millcreek-Rimrock | Stucco Color | Sep 23, 2026 | today | Unassigned | $2,145 | ||
| Bldg D-Residence at Millcreek-Rimrock | Stucco Color | Sep 27, 2026 | in 4d | Unassigned | $8,885 |
| Job | Task | Assigned | Age | Status | Materials due | Pay | Delay / notes |
|---|---|---|---|---|---|---|---|
| Cascade West Haven Warehouse-Overhead Projects (Ogden)-Unknown | Misc. Work | Aug 17, 2026 | 37d overdue | Unassigned | $0 | Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP |
Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):
Assigned Task Date is not blankTeam (Task Team) is blankCompleted Date/Time is blankTeam and Team Name agree on every record
(0 disagreements), so "no team assigned" is unambiguous.Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 300 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: