Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Sep 24, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Nov 18, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Sep 24, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 12,756 task records pulled, 148 matched the filter · assignment dates Jul 16, 2026 to Nov 18, 2026

148
Ready for assignment
68
Past assignment date
6
Divisions affected
$205,388
Unassigned task pay
70d
Oldest overdue

Ready tasks by division

012253850Orem5016 odOgden4729 odSalt Lake256 odSt. George168 odCommercial98 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Orem·
Ogden·
Salt Lake··
St. George··
Commercial··
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 20 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionPenetration SealingPorch OSBSet ScaffHousewrapSet Brick ScaffPaper/WireStucco BrownScratch CoatSidingPaintRockBrickSoffit/FasciaBrown & MeshGuttersRemove ScaffStucco ColorMisc. WorkInsl AtticFaux ConcreteTotal
Orem···········
Ogden······
Salt Lake·············
St. George···········
Commercial··············
Corporate···················
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 128 of 148 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorPaper/WireRockGuttersSoffitInsulationPaintSidingHousewrapBrickStucco BrownField OpsAny tradeTotal
Orem·····
Ogden··
Salt Lake·······
St. George······
Commercial·········
Corporate·············
All divisions

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorPaper/WireRockGuttersSoffitInsulationPaintSidingHousewrapBrickStucco BrownField OpsAny tradeTotal
Orem·········
Ogden···············
Salt Lake·········
St. George············
Commercial···············
Corporate···············
All divisions·······

15 crews company-wide have a hand up, counted once per division they cover (19 crew-division slots, of which 4 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Orem — 50 tasks ready for assignment · 16 overdue · $54,100
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
106-Canyon Park-Tri Pointe HomesPaper/WireAug 29, 202626d overdueUnassigned2026-09-03$117⭕ 2026-09-03: Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex Est End: 2026-09-23 ✅ 2026-08-20:
2024-Wildflower-Toll BrothersFaux ConcreteSep 8, 202616d overdueUnassigned$1,532⭕ 2026-09-16: Plaster delay - concrete needs to be poured first - Jonathan Est End: 2026-09-30 ✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-0
2021-Wildflower-Toll BrothersFaux ConcreteSep 8, 202616d overdueUnassigned$1,669⭕ 2026-09-23: Plaster delay - concrete needs to be poured first - Jonathan Est End: 2026-09-30 ✅ 2026-09-04: 10 Days - Stone delay - material still not delivered - Jonathan 2026-
110-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 202614d overdueUnassigned2026-09-01$173⭕ 2026-09-10: Missing a few windows and inside porch framing needing to be complete. Housewrap will be delayed until those pending items are completed. - Alex Est End: 2026-09-25
109-Canyon Park-Tri Pointe HomesPaper/WireSep 10, 202614d overdueUnassigned2026-09-02$117✅ 2026-09-11: 8 Days - Possible change of plans on the front porch. Might swap pre cast stone to stucco pop out. - Alex 2026-09-23
26-Lakeview Fields-Keystone ConstructionStucco ColorSep 17, 20267d overdueUnassigned$1,341⭕ 2026-09-21: Waiting on color selection for grout. - Alex Est End: 2026-09-23 ✅ 2026-09-15: 2 Days - Windows are getting moved around the home. We will not start stucco today unti
Bldg 58-Harmony Ridge-EdgeStucco ColorSep 20, 20264d overdueUnassigned$2,677
718-Highridge-EdgePaper/WireSep 21, 20263d overdueUnassigned2026-09-18$59
2216 (FP)-Wildflower-EdgePaper/WireSep 21, 20263d overdueUnassigned$50
721-Ridgehorne-EdgeHousewrapSep 22, 20262d overdueUnassigned$150⭕ 2026-09-22: Lath delay - good to proceed on lath for stone - missing windows - Jonathan Est End: 2026-09-24
314-Viridian-DR HortonPaper/WireSep 22, 20262d overdueUnassigned2026-09-23$917
44-Lakeview Fields-Keystone ConstructionPaper/WireSep 22, 20262d overdueUnassigned2026-09-02$1,170⭕ 2026-09-22: Cannot start lath. Missing man door to the side of the garage. - Alex Est End: 2026-09-25
405-Viridian-DR HortonSet ScaffSep 22, 20262d overdueUnassigned$771
339-Viridian-DR HortonPaper/WireSep 23, 20261d overdueUnassigned$837
Bldg 36-Highridge-EdgePaper/WireSep 23, 20261d overdueUnassigned2026-09-22$1,376
16116-Harmony-Meritage HomesSoffit/FasciaSep 23, 20261d overdueUnassigned$622
518-Ridgeview Cottages-IvoryBrickSep 24, 2026todayUnassigned2026-09-14$2,970✅ 2026-09-10: Scaff Delay - They have to replace a window - Harrison 2026-09-11
1008-Harmony Ridge-EdgeSet ScaffSep 24, 2026todayUnassigned$764
1021-Harmony Ridge-EdgeSidingSep 24, 2026todayUnassigned2026-09-17$4,955
519-Ridgeview Cottages-IvorySidingSep 24, 2026todayUnassigned2026-09-16$2,545✅ 2026-09-11: 2 Days - Need to wait for 4 way. Super told me to set scaff but not 4way - Harrison 2026-09-15
710-Highridge-EdgeSet ScaffSep 25, 2026in 1dUnassigned$671
16117-Harmony-Meritage HomesSidingSep 25, 2026in 1dUnassigned2026-09-23$3,891
109-Canyon Park-Tri Pointe HomesSidingSep 25, 2026in 1dUnassigned2026-09-14$5,288✅ 2026-09-11: 8 Days - Possible change of plans on the front porch. Might swap pre cast stone to stucco pop out. - Alex 2026-09-23
518-Ridgeview Cottages-IvorySidingSep 25, 2026in 1dUnassigned2026-09-22$1,065✅ 2026-09-10: Scaff Delay - They have to replace a window - Harrison 2026-09-11
16117-Harmony-Meritage HomesSoffit/FasciaSep 25, 2026in 1dUnassigned$575
719-Highridge-EdgeSet ScaffSep 28, 2026in 4dUnassigned$614
106-Auburn Springs-EdgeSet ScaffSep 28, 2026in 4dUnassigned$958
16116-Harmony-Meritage HomesStucco ColorSep 28, 2026in 4dUnassigned$150
233-Viridian Plus-DR HortonStucco ColorSep 28, 2026in 4dUnassigned$1,183
235-Viridian Plus-DR HortonSet ScaffSep 29, 2026in 5dUnassigned$978
2234-Wildflower-EdgeSet ScaffSep 29, 2026in 5dUnassigned$789
Bldg 59-Harmony Ridge-EdgeSet ScaffSep 29, 2026in 5dUnassigned$1,480
518-Ridgeview Cottages-IvoryStucco ColorSep 29, 2026in 5dUnassigned$842✅ 2026-09-10: Scaff Delay - They have to replace a window - Harrison 2026-09-11
1005-Harmony Ridge-EdgeSet ScaffSep 30, 2026in 6dUnassigned$830
Bldg 35-Highridge-EdgeSet ScaffSep 30, 2026in 6dUnassigned$1,121
602-River Point-EdgeSet ScaffOct 2, 2026in 8dUnassigned$653
Bldg 56-Viridian Townhomes-DR HortonSet ScaffOct 2, 2026in 8dUnassigned$1,283
714-Highridge-EdgeSet ScaffOct 5, 2026in 11dUnassigned$576
713-Ridgehorne-EdgeSet ScaffOct 6, 2026in 12dUnassigned$829
104-Auburn Springs-EdgeSet ScaffOct 6, 2026in 12dUnassigned$1,029
521-River Point-EdgeSet ScaffOct 6, 2026in 12dUnassigned$766
2210-Wildflower-EdgeSet ScaffOct 6, 2026in 12dUnassigned$585
354-Viridian Emerald-DR HortonSet ScaffOct 7, 2026in 13dUnassigned$0
102-Auburn Springs-EdgeSet ScaffOct 7, 2026in 13dUnassigned$931
605-River Point-EdgeSet ScaffOct 8, 2026in 14dUnassigned$578
110-Auburn Springs-EdgeSet ScaffOct 8, 2026in 14dUnassigned$654
Bldg 39-Highridge-EdgeInsl AtticOct 9, 2026in 15dUnassigned$80
515-River Point-EdgeSet ScaffOct 12, 2026in 18dUnassigned$730
Bldg 37-Highridge-EdgeInsl AtticNov 3, 2026in 40dUnassigned$80
Bldg 35-Highridge-EdgeInsl AtticNov 13, 2026in 50dUnassigned$80
Ogden — 47 tasks ready for assignment · 29 overdue · $52,365
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
71-Brookfield-LennarGuttersAug 24, 202631d overdueUnassigned$190
63-Brookfield-LennarGuttersAug 24, 202631d overdueUnassigned$265
106-Red Hill-IvorySet Brick ScaffAug 24, 202631d overdueUnassigned$0
Bldg 6-Midtown Village-DR HortonSet Brick ScaffAug 26, 202629d overdueUnassigned$0✅ 2026-09-08: 6 Days - not ready for lathe is missing the metal cap - George 2026-09-16
1523-Cranefield Estates-IvorySet Brick ScaffAug 26, 202629d overdueUnassigned$134
102-Meadows at Hyde Park-VisionaryBrickSep 11, 202613d overdueUnassigned2026-09-14$736
Units 47-52-Hess Farms-David Weekley HomesSet ScaffSep 11, 202613d overdueUnassigned$1,966⭕ 2026-09-11: Wait for house wrap inspection - Alexander Est End: 2026-09-23
4-Brynlee Acres-HamletPaintSep 17, 20267d overdueUnassigned$362
723-Ridgeline Park-VisionaryPaintSep 18, 20266d overdueUnassigned$796⭕ 2026-09-14: the concrete guys was start doing the porch cap and driways also on the east side was working building a wall - Jose Est End: 2026-09-21 ✅ 2026-09-02: -1 Days - Can’
5-Valley Meadows-Dixon HomesBrickSep 19, 20265d overdueUnassigned2026-09-23$13,668
176-Mountain Gate-Sierra HomesScratch CoatSep 19, 20265d overdueUnassigned$140
505-Legacy Park-IvoryGuttersSep 21, 20263d overdueUnassigned$197✅ 2026-09-02: 1 Days - Inspection delayed. - Erik 2026-09-03
124-Three Farms Jenkins Fields-IvorySet Brick ScaffSep 21, 20263d overdueUnassigned$24
Bldg L-Sugar Creek Townhomes-VisionaryBrown & MeshSep 22, 20262d overdueUnassigned2026-09-10$1,428
124-Three Farms Jenkins Fields-IvoryHousewrapSep 22, 20262d overdueUnassigned$834
503-Vineyard-VisionaryPaintSep 22, 20262d overdueUnassigned$622
113-Three Farms Jenkins Fields-IvoryPaper/WireSep 22, 20262d overdueUnassigned2026-09-17$1,080
Bldg L-Sugar Creek Townhomes-VisionaryRockSep 22, 20262d overdueUnassigned2026-09-23$530
Bldg L-Sugar Creek Townhomes-VisionaryScratch CoatSep 22, 20262d overdueUnassigned$53
Bldg L-Sugar Creek Townhomes-VisionaryStucco BrownSep 22, 20262d overdueUnassigned$1,428
Bldg 13-Midtown Village-DR HortonBrickSep 23, 20261d overdueUnassigned$6,903
1711-Cranefield Estates-IvoryHousewrapSep 23, 20261d overdueUnassigned$1,100
176-Mountain Gate-Sierra HomesPaintSep 23, 20261d overdueUnassigned$50
118-Stagecoach Estates-McArthurPaper/WireSep 23, 20261d overdueUnassigned2026-09-16$818
Bldg 13-Midtown Village-DR HortonScratch CoatSep 23, 20261d overdueUnassigned$752
241-Westwood Estates-Meritage HomesSidingSep 23, 20261d overdueUnassigned2026-09-23$4,905
216-Sugar Creek-VisionarySoffit/FasciaSep 23, 20261d overdueUnassigned$722
241-Westwood Estates-Meritage HomesSoffit/FasciaSep 23, 20261d overdueUnassigned$648
338-Sugar Creek-VisionaryStucco ColorSep 23, 20261d overdueUnassigned$1,028
5-Brynlee Acres-HamletGuttersSep 24, 2026todayUnassigned$220✅ 2026-08-31: 2 Days - they need to stack the drywall first - Jose 2026-09-02
2-Brynlee Acres-HamletGuttersSep 24, 2026todayUnassigned$301
11-Mountainside Estates-DR HortonGuttersSep 24, 2026todayUnassigned$283⭕ 2026-09-19: we are short with thing brick - Jose Est End: 2026-09-30
203-Weber View-IvoryGuttersSep 24, 2026todayUnassigned$432
1523-Cranefield Estates-IvoryGuttersSep 24, 2026todayUnassigned$382
11-Heritage Parkway-Sierra HomesGuttersSep 24, 2026todayUnassigned$236✅ 2026-08-22: Material Delay - We still don’t have vinyl materials - Jose 2026-09-07
820-Ridgeline Park-VisionaryPaintSep 24, 2026todayUnassigned$224
134-Legends Crossing-VisionaryRockSep 24, 2026todayUnassigned$198
Bldg F-Legends Crossing Townhomes-VisionaryRockSep 24, 2026todayUnassigned$1,030
134-Legends Crossing-VisionaryScratch CoatSep 24, 2026todayUnassigned$50
Bldg F-Legends Crossing Townhomes-VisionaryScratch CoatSep 24, 2026todayUnassigned$139
176-Mountain Gate-Sierra HomesSoffit/FasciaSep 24, 2026todayUnassigned$1,022
Bldg Y-North Point Townhomes-VisionarySoffit/FasciaSep 24, 2026todayUnassigned$1,511
102-Meadows at Hyde Park-VisionaryStucco ColorSep 24, 2026todayUnassigned$978
105-Palomino-DR HortonStucco BrownSep 25, 2026in 1dUnassigned$1,375
521-Vineyard-VisionaryStucco ColorSep 26, 2026in 2dUnassigned$585
216-Sugar Creek-VisionaryStucco ColorSep 27, 2026in 3dUnassigned2026-09-16$1,236
102-Village at Fox Meadows-VisionaryStucco ColorSep 28, 2026in 4dUnassigned$783✅ 2026-08-31: 3 Days - they need to do the concrete stoops first - Jose 2026-09-03
Salt Lake — 25 tasks ready for assignment · 6 overdue · $26,643
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
122-Capitol Reef-EdgeSoffit/FasciaSep 21, 20263d overdueUnassigned$564
Units 544-548-Daybreak Lexington Townhomes-Destination HomesStucco ColorSep 21, 20263d overdueUnassigned2026-09-16$3,582✅ 2026-08-25: 6 Days - Can’t finish paper and wire completely. Missing drywall windows. - Facundo 2026-09-02 ✅ 2026-08-13: 7 Days - Paper and wire delay. Can’t finish scaffolding
122-Capitol Reef-EdgeStucco ColorSep 22, 20262d overdueUnassigned2026-09-23$953
2927-Mountain Ridge-EdgeHousewrapSep 23, 20261d overdueUnassigned$814⭕ 2026-09-23: Windows won’t be installed until October, delay exteriors only set scaff. - Arturo Est End: 2026-10-05
2927-Mountain Ridge-EdgePaper/WireSep 23, 20261d overdueUnassigned$63⭕ 2026-09-23: Windows won’t be installed until October, delay exteriors only set scaff. - Arturo Est End: 2026-10-05
103-Creek Ridge Cove-RichmondStucco ColorSep 23, 20261d overdueUnassigned2026-09-23$1,219
Bldg 21-Solari-EdgePaintSep 24, 2026todayUnassigned$793
39-Sky Ranch Cascade-WoodsideSoffit/FasciaSep 24, 2026todayUnassigned$531
Bldg 21-Solari-EdgeStucco ColorSep 24, 2026todayUnassigned$2,876
Units 325-330-Enclave at Sky Ranch-WoodsideStucco ColorSep 26, 2026in 2dUnassigned$3,498
154-Pierson Farms-McArthurStucco ColorSep 27, 2026in 3dUnassigned$937
256-Boulder at Sky Ranch-WoodsideStucco ColorSep 27, 2026in 3dUnassigned$914
39-Sky Ranch Cascade-WoodsideStucco ColorSep 28, 2026in 4dUnassigned$827
Bldg 22-Solari-EdgeStucco ColorSep 28, 2026in 4dUnassigned$2,502
104-Creek Ridge Cove-RichmondStucco ColorSep 28, 2026in 4dUnassigned2026-09-23$799
2907-Mountain Ridge-EdgeSet ScaffSep 29, 2026in 5dUnassigned$653
Bldg 1-Solari-EdgeInsl AtticOct 1, 2026in 7dUnassigned$143✅ 2026-08-18: 1 Days - Delay brown and scratch for repair - Dustin 2026-08-19
2904-Mountain Ridge-EdgeSet ScaffOct 1, 2026in 7dUnassigned$747
Bldg 17-Solari-EdgeSet ScaffOct 5, 2026in 11dUnassigned$1,355
Bldg 205-Mountain Ridge-EdgeSet ScaffOct 5, 2026in 11dUnassigned$1,492
2918-Mountain Ridge-EdgeSet ScaffOct 7, 2026in 13dUnassigned$742
Bldg 208-Mountain Ridge-EdgeInsl AtticOct 14, 2026in 20dUnassigned$144
Bldg 22-Solari-EdgeInsl AtticOct 26, 2026in 32dUnassigned$160
Bldg 19-Solari-EdgeInsl AtticNov 3, 2026in 40dUnassigned$192
Bldg 205-Mountain Ridge-EdgeInsl AtticNov 18, 2026in 55dUnassigned$143
St. George — 16 tasks ready for assignment · 8 overdue · $33,063
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
52-Zion Shores-Split RockRockSep 10, 202614d overdueUnassigned2026-09-21$7,478
Bldg 124-Long Valley Townhomes-DR HortonStucco ColorSep 21, 20263d overdueUnassigned2026-09-14$4,999
4270-Long Valley-DR HortonPaintSep 22, 20262d overdueUnassigned$50
33-Black Desert North Village-H2 HomesStucco ColorSep 22, 20262d overdueUnassigned2026-08-17$4,708
114-Desert Color-Split RockRockSep 23, 20261d overdueUnassigned2026-09-22$3,624
33-Legacy at Sand Hollow-VisionaryRockSep 23, 20261d overdueUnassigned2026-09-17$263
4270-Long Valley-DR HortonStucco ColorSep 23, 20261d overdueUnassigned2026-09-23$1,916
4293-Long Valley-DR HortonStucco ColorSep 23, 20261d overdueUnassigned$2,215
6-Legacy at Sand Hollow-VisionaryHousewrapSep 24, 2026todayUnassigned$172
6-Legacy at Sand Hollow-VisionaryPaper/WireSep 24, 2026todayUnassigned2026-09-22$2,100
7-Chelsey-DR HortonPorch OSBSep 24, 2026todayUnassigned$25
4295-Long Valley-DR HortonRockSep 24, 2026todayUnassigned2026-09-18$513
4295-Long Valley-DR HortonScratch CoatSep 24, 2026todayUnassigned$70
4295-Long Valley-DR HortonSidingSep 24, 2026todayUnassigned2026-09-21$498
4295-Long Valley-DR HortonStucco BrownSep 24, 2026todayUnassigned$2,173
4294-Long Valley-DR HortonStucco ColorSep 26, 2026in 2dUnassigned$2,259
Commercial — 9 tasks ready for assignment · 8 overdue · $39,217
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-RimrockScratch CoatJul 16, 202670d overdueUnassigned$1,811
Bldg D-Residence at Millcreek-RimrockRemove ScaffAug 6, 202649d overdueUnassigned$7,542
Bldg RU-1-ARA Southwest-Campbell ConstructionPenetration SealingAug 15, 202640d overdueUnassigned$0
White Dome Chapel-St George-Grass CreekSet ScaffAug 27, 202628d overdueUnassigned$57
Bldg D-Residence at Millcreek-RimrockRockSep 9, 202615d overdueUnassigned$15,588
Bldg RU-1-ARA Southwest-Campbell ConstructionSet ScaffSep 16, 20268d overdueUnassigned$2,000West Walls Setup
Garage 4-Residence at Millcreek-RimrockRockSep 18, 20266d overdueUnassigned2026-09-02$1,190
Garage 4-Residence at Millcreek-RimrockStucco ColorSep 23, 20261d overdueUnassigned$2,145
Bldg D-Residence at Millcreek-RimrockStucco ColorSep 27, 2026in 3dUnassigned$8,885
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-UnknownMisc. WorkAug 17, 202638d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 300 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: