Tasks Ready for Assignment — Corporate

Every division. Tasks with an assignment date set but no team assigned and not yet completed.

Generated Oct 4, 2026 · Go to the current version →

This will not tie to your division view — it is wider on three axes and narrower on one. Most tasks in a division's Tasks Ready For Assignment - My Division view appear here, but neither list contains the other.

● All 6 divisions, not just yours — the division scoping is removed.
● No 7-day cap. The division view only shows assignments due inside a week; this carries the whole book — the overdue tail reaching back to Jul 16, 2026 and forward assignments out to Dec 2, 2026.
● Delayed assignments are not excluded. The division view drops tasks flagged Task Assignment Is Delayed; that field is not available to this report, so those tasks are still counted here.
● Finaled jobs are excluded here. The source view is scoped to active jobs, so an unassigned task on a finaled job shows in your division view and not here — the one direction where your view is larger than this report.

Treat these numbers as the company-wide assignment backlog, not as a division worklist. See How this was filtered at the bottom for the exact conditions.

Generated Oct 4, 2026 · source: TrackVia MCP Task Data For Pipeline Matrix Report (view 2818) · 12,324 task records pulled, 151 matched the filter · assignment dates Jul 16, 2026 to Dec 2, 2026

151
Ready for assignment
75
Past assignment date
6
Divisions affected
$162,554
Unassigned task pay
80d
Oldest overdue

Ready tasks by division

015304661Orem6124 odOgden3922 odSalt Lake277 odSt. George1412 odCommercial99 odCorporate11 od

past assignment date   due today or upcoming

Pivot — division × assignment age

Click any number to see the tasks behind it. Esc closes.

DivisionOverdue 30+ daysOverdue 8-30 daysOverdue 1-7 daysDue todayNext 7 daysBeyond 7 daysTotal
Orem·
Ogden···
Salt Lake·
St. George···
Commercial···
Corporate·····
All divisions

Pivot — division × task type

Which trades the backlog is sitting in, in construction sequence. Scroll sideways for all 23 task types.

Click any number to see the tasks behind it. Esc closes.

DivisionInsl Foam 1Insl WallsPenetration SealingPorch OSBSet ScaffHousewrapSet Brick ScaffPaper/WireStucco BrownScratch CoatSidingPaintRockBrickSoffit/FasciaGuttersRemove ScaffShuttersStucco ColorMisc. WorkInsl AtticFoundation PlasterFaux ConcreteTotal
Orem·········
Ogden···········
Salt Lake················
St. George·················
Commercial·················
Corporate······················
All divisions

Is there a crew for it? — the backlog and available crews on one axis

Tasks are typed by task type, crews by trade, so trade is the axis both sides share. The two tables below carry identical rows and columns — read straight down a column: work waiting on top, crews with a hand up underneath. 100 of 151 tasks sit in a division-and-trade with nobody available — those cells are amber. Red still means past its assignment date, as everywhere else in this report.

Click any number to see the tasks — or the crews — behind it. Esc closes.

Tasks needing assignment

DivisionScaffoldingStucco ColorRockInsulationPaper/WireSidingHousewrapBrickPaintStucco BrownGuttersSoffitField OpsAny tradeTotal
Orem·····
Ogden···
Salt Lake········
St. George·········
Commercial········
Corporate·············
All divisions

Crews with a hand up — available to that division

DivisionScaffoldingStucco ColorRockInsulationPaper/WireSidingHousewrapBrickPaintStucco BrownGuttersSoffitField OpsAny tradeTotal
Orem·····
Ogden·············
Salt Lake·······
St. George············
Commercial···············
Corporate···············
All divisions·····

31 crews company-wide have a hand up, counted once per division they cover (44 crew-division slots, of which 13 are crews working outside their home division). A crew is available to every division in its coverage list, which is how the real queue behaves.

Detail by division

Click a division to see the underlying tasks, oldest assignment date first.

Orem — 61 tasks ready for assignment · 24 overdue · $58,823
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
2024-Wildflower-Toll Brothers Faux ConcreteSep 8, 202626d overdueUnassigned$1,532⭕ 2026-09-16: Plaster delay - concrete needs to be poured first - Jonathan Est End: 2026-10-02 ✅ 2026-08-26: 3 Days - Siding delay - still missing a few windows - Jonathan 2026-0
2021-Wildflower-Toll Brothers Faux ConcreteSep 8, 202626d overdueUnassigned$1,669⭕ 2026-09-28: Stone delay - stone guy needed more material to complete job - waiting on material to arrive - Jonathan Est End: 2026-10-02 ⭕ 2026-09-23: Plaster delay - concrete ne
44-Lakeview Fields-Keystone Construction Paper/WireSep 22, 202612d overdueUnassigned2026-09-02$1,170⭕ 2026-09-22: Cannot start lath. Missing man door to the side of the garage. - Alex Est End: 2026-10-02
518-Ridgeview Cottages-Ivory BrickSep 29, 20265d overdueUnassigned2026-09-14$2,970✅ 2026-09-10: Scaff Delay - They have to replace a window - Harrison 2026-09-11
335-Mountain Vista at Sunset Flats-Pulte Homes Paper/WireSep 30, 20264d overdueUnassigned2026-09-28$1,361⭕ 2026-09-30: We can’t lath we need to pass Housewrap inspection before we lath please don’t send any lath crew thanks - Victor Est End: 2026-10-05
344-Mountain Vista at Sunset Flats-Pulte Homes Paper/WireSep 30, 20264d overdueUnassigned2026-09-23$1,379⭕ 2026-09-30: We need to pass the Housewrap before we can lath please don’t send lath crew thanks - Victor Est End: 2026-10-05
721-Ridgehorne-Edge RockSep 30, 20264d overdueUnassigned2026-09-25$281✅ 2026-09-22: 2 Days - Lath delay - good to proceed on lath for stone - missing windows - Jonathan 2026-09-24
Units 476-480-Legacy at Meadowbrook-Woodside Set ScaffSep 30, 20264d overdueUnassigned$1,451⭕ 2026-09-30: Scaff Delay - Woodside cm requested that we hold off on scaff - Harrison Est End: 2026-09-08
41-Lakeview Fields-Keystone Construction RockOct 1, 20263d overdueUnassigned2026-09-08$143⭕ 2026-10-01: The window was replaced after we had already installed the lath and completed the work. We are delaying the stucco brown application until the lath is repaired. - Ale
119-Canyon Park-Tri Pointe Homes Set Brick ScaffOct 1, 20263d overdueUnassigned$133⭕ 2026-10-01: Scaff Delay - Shear passed. Waiting on Ty to confirm when it start scaffold. - Alex Est End: 2026-10-07
107-Canyon Park-Tri Pointe Homes Set ScaffOct 1, 20263d overdueUnassigned$1,250⭕ 2026-10-01: Scaff Delay - Shear passed. Scaffold is on standby until I get confirmation to resume. - Alex Est End: 2026-10-05
119-Canyon Park-Tri Pointe Homes Set ScaffOct 1, 20263d overdueUnassigned$500⭕ 2026-10-01: Scaff Delay - Shear passed. Waiting on Ty to confirm when it start scaffold. - Alex Est End: 2026-10-07
Bldg 56-Harmony Ridge-Edge Stucco ColorOct 1, 20263d overdueUnassigned$3,142
835-Broadview Shores-Ivory BrickOct 2, 20262d overdueUnassigned2026-09-22$5,489
2021-Wildflower-Toll Brothers Foundation PlasterOct 2, 20262d overdueUnassigned$450⭕ 2026-09-28: Stone delay - stone guy needed more material to complete job - waiting on material to arrive - Jonathan Est End: 2026-10-02 ⭕ 2026-09-23: Plaster delay - concrete ne
732-Ridgehorne-Edge RockOct 2, 20262d overdueUnassigned2026-10-02$359⭕ 2026-09-30: Brown delay - framer has to come to install a pc of framing on a section by the beam so we can install the lath properly - Jonathan Est End: 2026-10-02 ✅ 2026-09-29:
Bldg 36-Highridge-Edge RockOct 2, 20262d overdueUnassigned2026-09-25$702⭕ 2026-09-29: Brown delay and siding delay - missing window , ok to proceed on scratch - Jonathan Est End: 2026-10-02
732-Ridgehorne-Edge Scratch CoatOct 2, 20262d overdueUnassigned$52⭕ 2026-09-30: Brown delay - framer has to come to install a pc of framing on a section by the beam so we can install the lath properly - Jonathan Est End: 2026-10-02 ✅ 2026-09-29:
Bldg 36-Highridge-Edge Scratch CoatOct 2, 20262d overdueUnassigned$106⭕ 2026-09-29: Brown delay and siding delay - missing window , ok to proceed on scratch - Jonathan Est End: 2026-10-02
Bldg 36-Highridge-Edge SidingOct 2, 20262d overdueUnassigned2026-09-28$3,280⭕ 2026-09-29: Brown delay and siding delay - missing window , ok to proceed on scratch - Jonathan Est End: 2026-10-02
835-Broadview Shores-Ivory SidingOct 2, 20262d overdueUnassigned2026-09-28$1,437
732-Ridgehorne-Edge Stucco BrownOct 2, 20262d overdueUnassigned$1,275⭕ 2026-09-30: Brown delay - framer has to come to install a pc of framing on a section by the beam so we can install the lath properly - Jonathan Est End: 2026-10-02 ✅ 2026-09-29:
Bldg 36-Highridge-Edge Stucco BrownOct 2, 20262d overdueUnassigned$1,522⭕ 2026-09-29: Brown delay and siding delay - missing window , ok to proceed on scratch - Jonathan Est End: 2026-10-02
835-Broadview Shores-Ivory Stucco BrownOct 2, 20262d overdueUnassigned$775
106-Canyon Park-Tri Pointe Homes RockOct 4, 2026todayUnassigned2026-10-01$1,231✅ 2026-09-03: 15 Days - Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex 2026-09-24 ✅ 2026-08-20:
106-Canyon Park-Tri Pointe Homes Scratch CoatOct 4, 2026todayUnassigned$145✅ 2026-09-03: 15 Days - Delay on lath install. Possible plan change for the porch headers. May want to change to stucco popouts instead of precast. - Alex 2026-09-24 ✅ 2026-08-20:
713-Ridgehorne-Edge Set ScaffOct 6, 2026in 2dUnassigned$829
104-Auburn Springs-Edge Set ScaffOct 6, 2026in 2dUnassigned$1,029
521-River Point-Edge Set ScaffOct 6, 2026in 2dUnassigned$766
2210-Wildflower-Edge Set ScaffOct 6, 2026in 2dUnassigned$585
1030-Harmony Ridge-Edge Stucco ColorOct 6, 2026in 2dUnassigned$1,258
721-Ridgehorne-Edge Stucco ColorOct 6, 2026in 2dUnassigned$795✅ 2026-09-22: 2 Days - Lath delay - good to proceed on lath for stone - missing windows - Jonathan 2026-09-24
Bldg 38-Highridge-Edge Stucco ColorOct 6, 2026in 2dUnassigned$1,302
354-Viridian Emerald-DR Horton Set ScaffOct 7, 2026in 3dUnassigned$0
102-Auburn Springs-Edge Set ScaffOct 7, 2026in 3dUnassigned$931
405-Viridian-DR Horton Stucco ColorOct 7, 2026in 3dUnassigned$1,238
339-Viridian-DR Horton Stucco ColorOct 7, 2026in 3dUnassigned$825
41-Lakeview Fields-Keystone Construction Stucco ColorOct 7, 2026in 3dUnassigned$1,181⭕ 2026-10-01: The window was replaced after we had already installed the lath and completed the work. We are delaying the stucco brown application until the lath is repaired. - Ale
605-River Point-Edge Set ScaffOct 8, 2026in 4dUnassigned$578
110-Auburn Springs-Edge Set ScaffOct 8, 2026in 4dUnassigned$650
238-Canton Ridge-Richmond Stucco ColorOct 8, 2026in 4dUnassigned$1,133
Bldg 39-Highridge-Edge Insl AtticOct 9, 2026in 5dUnassigned$80
132-Auburn Springs-Edge Set ScaffOct 9, 2026in 5dUnassigned$800
1022-Harmony Ridge-Edge Set ScaffOct 9, 2026in 5dUnassigned$829
Bldg 51-Highridge-Edge Insl Foam 1Oct 12, 2026in 8dUnassigned$0
Bldg 51-Highridge-Edge Insl WallsOct 12, 2026in 8dUnassigned$50
2190-Wildflower-Edge Set ScaffOct 12, 2026in 8dUnassigned$781
516-River Point-Edge Set ScaffOct 13, 2026in 9dUnassigned$720
515-River Point-Edge Set ScaffOct 13, 2026in 9dUnassigned$730
372-Viridian Plus-DR Horton Set ScaffOct 14, 2026in 10dUnassigned$742
737-Ridgehorne-Edge Set ScaffOct 14, 2026in 10dUnassigned$482
Bldg 55-Harmony Ridge-Edge Set ScaffOct 14, 2026in 10dUnassigned$1,682
2223-Wildflower-Edge Set ScaffOct 14, 2026in 10dUnassigned$587
143-Auburn Springs-Edge Set ScaffOct 14, 2026in 10dUnassigned$844
144-Auburn Springs-Edge Set ScaffOct 15, 2026in 11dUnassigned$814
703-The Ridge at Mt Saratoga SF-Edge Set ScaffOct 15, 2026in 11dUnassigned$876
Bldg 51-Highridge-Edge Set ScaffOct 15, 2026in 11dUnassigned$1,015
2211-Wildflower-Edge Set ScaffOct 16, 2026in 12dUnassigned$682
Bldg 37-Highridge-Edge Insl AtticNov 3, 2026in 30dUnassigned$80
Bldg 35-Highridge-Edge Insl AtticNov 13, 2026in 40dUnassigned$80⭕ 2026-10-01: Siding and brown delay - missing windows - Jonathan Est End: 2026-10-02
Bldg 51-Highridge-Edge Insl AtticDec 2, 2026in 59dUnassigned$50
Ogden — 39 tasks ready for assignment · 22 overdue · $42,830
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
180-Mountain Gate-Sierra Homes SidingSep 28, 20266d overdueUnassigned$302✅ 2026-09-18: 6 Days - Is missing some windows - Jose 2026-09-28
72-Brookfield-Lennar ShuttersSep 29, 20265d overdueUnassigned2026-09-23$50
58-Harvest Acres-Sierra Homes Paper/WireSep 30, 20264d overdueUnassigned$50⭕ 2026-09-30: Material Delay - We still don’t has any order on the job - Jose Est End: 2026-10-09
127-Red Hill-Ivory Set Brick ScaffSep 30, 20264d overdueUnassigned$21⭕ 2026-10-01: missing a couple of windows - George Est End: 2026-10-07
Units 1-6-VTG-Sierra Homes Stucco ColorSep 30, 20264d overdueUnassigned$1,121⭕ 2026-10-01: Material Delay - brick and stone are in back order about 2 weeks out 5hats what supplier told me - George Est End: 2026-10-15
209-Stagecoach Estates-McArthur RockOct 1, 20263d overdueUnassigned2026-09-24$465
115-Stagecoach Estates-McArthur Set ScaffOct 1, 20263d overdueUnassigned$579
115-Stagecoach Estates-McArthur HousewrapOct 2, 20262d overdueUnassigned$583
217-Sugar Creek-Visionary PaintOct 2, 20262d overdueUnassigned$231
716-Ridgeline Park-Visionary PaintOct 2, 20262d overdueUnassigned$927✅ 2026-09-17: 9 Days - they want to do tha flat work first - Jose 2026-09-30
607-Vineyard-Visionary PaintOct 2, 20262d overdueUnassigned$1,941
180-Mountain Gate-Sierra Homes RockOct 2, 20262d overdueUnassigned$1,801✅ 2026-09-18: 6 Days - Is missing some windows - Jose 2026-09-28
107-Village at Fox Meadows-Visionary RockOct 2, 20262d overdueUnassigned2026-09-29$435✅ 2026-09-15: 7 Days - We can start this job on this date because they stills has the porch cap missing - Jose 2026-09-24
103-Meadows at Hyde Park-Visionary Set ScaffOct 2, 20262d overdueUnassigned$609⭕ 2026-10-02: we still don't has any material order - Jose Est End: 2026-10-09
103-Meadows at Hyde Park-Visionary SidingOct 2, 20262d overdueUnassigned$1,517⭕ 2026-10-02: we still don't has any material order - Jose Est End: 2026-10-09
Bldg 1-Railrunner-DAI Construction SidingOct 2, 20262d overdueUnassigned$782✅ 2026-09-21: 14 Days - HVAC. still doing some work around the building inspection hasn't pass yet - George 2026-10-09
112-Meadows at Hyde Park-Visionary BrickOct 3, 20261d overdueUnassigned$773
112-Meadows at Hyde Park-Visionary PaintOct 3, 20261d overdueUnassigned$662
101-Legends Crossing-Visionary RockOct 3, 20261d overdueUnassigned2026-09-25$260
Units 47-52-Hess Farms-David Weekley Homes RockOct 3, 20261d overdueUnassigned$9,686✅ 2026-09-22: 5 Days - Builders requested us to wait for scaffold until dry wall gets delivered - Alexander 2026-09-29 ✅ 2026-09-11: 10 Days - Wait for house wrap inspection - Al
101-Legends Crossing-Visionary Scratch CoatOct 3, 20261d overdueUnassigned$50
607-Village at Fox Meadows-Visionary SidingOct 3, 20261d overdueUnassigned$4,166
113-Three Farms Jenkins Fields-Ivory BrickOct 4, 2026todayUnassigned2026-10-03$2,008
237-Westwood Estates-Meritage Homes GuttersOct 4, 2026todayUnassigned$498
176-Mountain Gate-Sierra Homes GuttersOct 4, 2026todayUnassigned$464
26-Hylands Ranch-Dixon Homes BrickOct 5, 2026in 1dUnassigned$840✅ 2026-09-18: hadn't pass 4way yet - George 2026-09-18
109-Stagecoach Estates-McArthur Paper/WireOct 5, 2026in 1dUnassigned2026-09-24$1,004
503-Vineyard-Visionary Stucco ColorOct 5, 2026in 1dUnassigned2026-09-30$783
820-Ridgeline Park-Visionary Stucco ColorOct 5, 2026in 1dUnassigned2026-09-30$1,187
1710-Cranefield Estates-Ivory Stucco ColorOct 5, 2026in 1dUnassigned$1,006
723-Ridgeline Park-Visionary Stucco ColorOct 5, 2026in 1dUnassigned$618✅ 2026-09-14: 5 Days - the concrete guys was start doing the porch cap and driways also on the east side was working building a wall - Jose 2026-09-21 ✅ 2026-09-02: -1 Days - Can’
26-Hylands Ranch-Dixon Homes Stucco ColorOct 6, 2026in 2dUnassigned$1,020✅ 2026-09-18: hadn't pass 4way yet - George 2026-09-18
52-Mountainside Estates-DR Horton Stucco ColorOct 6, 2026in 2dUnassigned$928
19-Hylands Ranch-Dixon Homes BrickOct 7, 2026in 3dUnassigned$983✅ 2026-09-28: 3 Days - the house hasn't pass 4way yet - George 2026-09-28
Bldg F-Legends Crossing Townhomes-Visionary PaintOct 7, 2026in 3dUnassigned2026-10-03$212
19-Hylands Ranch-Dixon Homes Stucco ColorOct 7, 2026in 3dUnassigned$1,075✅ 2026-09-28: 3 Days - the house hasn't pass 4way yet - George 2026-09-28
214-Bristol Farms-Regal Homes Stucco ColorOct 7, 2026in 3dUnassigned$1,178
209-Stagecoach Estates-McArthur Stucco ColorOct 7, 2026in 3dUnassigned$932
1712-Cranefield Estates-Ivory Stucco ColorOct 9, 2026in 5dUnassigned$1,085
Salt Lake — 27 tasks ready for assignment · 7 overdue · $24,805
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
2927-Mountain Ridge-Edge HousewrapSep 23, 202611d overdueUnassigned$814⭕ 2026-09-23: Windows won’t be installed until October, delay exteriors only set scaff. - Arturo Est End: 2026-10-05
2927-Mountain Ridge-Edge Paper/WireSep 23, 202611d overdueUnassigned$63⭕ 2026-09-23: Windows won’t be installed until October, delay exteriors only set scaff. - Arturo Est End: 2026-10-05
2904-Mountain Ridge-Edge Set ScaffOct 1, 20263d overdueUnassigned$747
441-Daybreak Cottage Courts-Destination Homes Stucco ColorOct 1, 20263d overdueUnassigned2026-09-30$805✅ 2026-09-10: 11 Days - City inspection is on delay until drywall window is installed so we can finish lath around it. - Arturo 2026-09-25
Units 541-543-Daybreak Lexington Townhomes-Destination Homes Stucco ColorOct 1, 20263d overdueUnassigned2026-09-30$1,192✅ 2026-09-01: 11 Days - Do not start Housewrap until framing issue is fixed - Arturo 2026-09-16
2931-Mountain Ridge-Edge Soffit/FasciaOct 2, 20262d overdueUnassigned$576⭕ 2026-10-02: Don’t send soffit and fascia crews until framers fix the front entryway. It doesn’t match plans. - Arturo Est End: 2026-10-05
256-Boulder at Sky Ranch-Woodside Remove ScaffOct 3, 20261d overdueUnassigned$364
Bldg 21-Solari-Edge Remove ScaffOct 4, 2026todayUnassigned$931
Bldg 203-Mountain Ridge-Edge Stucco ColorOct 4, 2026todayUnassigned$1,553
Bldg 17-Solari-Edge Set ScaffOct 5, 2026in 1dUnassigned$1,355
1027-Northstar Ranch-Destination Homes Stucco ColorOct 6, 2026in 2dUnassigned$1,180
1028-Northstar Ranch-Destination Homes Stucco ColorOct 6, 2026in 2dUnassigned$882✅ 2026-09-15: 6 Days - Siding back patio cap. Lathe not completed - Dustin 2026-09-23
2918-Mountain Ridge-Edge Set ScaffOct 7, 2026in 3dUnassigned$743
Bldg 19-Solari-Edge Stucco ColorOct 7, 2026in 3dUnassigned$2,578
Bldg 204-Mountain Ridge-Edge Stucco ColorOct 8, 2026in 4dUnassigned$1,580
Bldg 206-Mountain Ridge-Edge Set ScaffOct 9, 2026in 5dUnassigned$1,706
Bldg 23-Solari-Edge Set ScaffOct 12, 2026in 8dUnassigned$1,778
2906-Mountain Ridge-Edge Set ScaffOct 12, 2026in 8dUnassigned$781
205-Capitol Reef-Edge Set ScaffOct 13, 2026in 9dUnassigned$459
2905-Mountain Ridge-Edge Set ScaffOct 16, 2026in 12dUnassigned$734
Bldg 207-Mountain Ridge-Edge Set ScaffOct 19, 2026in 15dUnassigned$1,501
207-Capitol Reef-Edge Set ScaffOct 19, 2026in 15dUnassigned$728
Bldg 19-Solari-Edge Insl AtticNov 3, 2026in 30dUnassigned$192
201-Capitol Reef-Edge Set ScaffNov 6, 2026in 33dUnassigned$663
203-Capitol Reef-Edge Set ScaffNov 9, 2026in 36dUnassigned$577
Bldg 205-Mountain Ridge-Edge Insl AtticNov 18, 2026in 45dUnassigned$143
Bldg 206-Mountain Ridge-Edge Insl AtticNov 24, 2026in 51dUnassigned$179
St. George — 14 tasks ready for assignment · 12 overdue · $26,499
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
52-Zion Shores-Split Rock RockSep 10, 202624d overdueUnassigned2026-09-21$7,478
33-Black Desert North Village-H2 Homes Stucco ColorSep 22, 202612d overdueUnassigned2026-08-17$4,708
7-Chelsey-DR Horton Remove ScaffSep 25, 20269d overdueUnassigned$306
4160-Long Valley Rambler-DR Horton HousewrapSep 28, 20266d overdueUnassigned$50
4160-Long Valley Rambler-DR Horton Paper/WireSep 28, 20266d overdueUnassigned2026-09-29$1,418
4160-Long Valley Rambler-DR Horton Porch OSBSep 28, 20266d overdueUnassigned$85
4269-Long Valley-DR Horton Stucco ColorSep 30, 20264d overdueUnassigned$1,883
4296-Long Valley-DR Horton HousewrapOct 3, 20261d overdueUnassigned$153
4173-Long Valley-DR Horton HousewrapOct 3, 20261d overdueUnassigned$68
4266-Long Valley-DR Horton RockOct 3, 20261d overdueUnassigned2026-09-29$773
52-Zion Shores-Split Rock Stucco ColorOct 3, 20261d overdueUnassigned$4,818
33-Legacy at Sand Hollow-Visionary Stucco ColorOct 3, 20261d overdueUnassigned$1,799
4158-Long Valley Rambler-DR Horton Stucco ColorOct 5, 2026in 1dUnassigned$1,656✅ 2026-09-21: 4 Days - Cannot finish lath at back patio since slider door will be missing - Daniel 2026-09-25
4163-Long Valley Rambler-DR Horton Stucco ColorOct 7, 2026in 3dUnassigned$1,303
Commercial — 9 tasks ready for assignment · 9 overdue · $9,598
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Bldg C-Residence at Millcreek-Rimrock Scratch CoatJul 16, 202680d overdueUnassigned$1,811
Bldg RU-1-ARA Southwest-Campbell Construction Penetration SealingAug 15, 202650d overdueUnassigned$0
White Dome Chapel-St George-Grass Creek Set ScaffAug 27, 202638d overdueUnassigned$57
Bldg RU-1-ARA Southwest-Campbell Construction Set ScaffSep 16, 202618d overdueUnassigned$2,000West Walls Setup
Garage 4-Residence at Millcreek-Rimrock RockSep 18, 202616d overdueUnassigned2026-09-02$1,190
Garage 3-Residence at Millcreek-Rimrock RockSep 25, 20269d overdueUnassigned$1,148
Garage 3-Residence at Millcreek-Rimrock Scratch CoatSep 25, 20269d overdueUnassigned$127
Garage 3-Residence at Millcreek-Rimrock Stucco BrownSep 25, 20269d overdueUnassigned$2,178
Bldg A-Residence at Millcreek-Rimrock HousewrapSep 30, 20264d overdueUnassigned$1,088
Corporate — 1 task ready for assignment · 1 overdue · $0
JobTaskAssignedAgeStatusMaterials duePayDelay / notes
Cascade West Haven Warehouse-Overhead Projects (Ogden)-Unknown Misc. WorkAug 17, 202648d overdueUnassigned$0Por favor de pintar el parte exterior enfrente de el edeficio. Solomante el parte blanco. Por favor de marcar me si tiene preguntas. FP

How this was filtered

Filter applied (corporate equivalent of the TrackVia view Tasks Ready For Assignment - My Division, view 2607 / filter 3955, with the division scoping removed):

Crew availability (the trade-axis tables) comes from MCP Task Team Info (view 2835), 304 crews, filtered to the hand-raise checkbox ¿Listo para otro trabajo?: